instruction
stringlengths 960
963
| input
stringlengths 0
5.58k
| output
stringlengths 4
732
|
---|---|---|
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-05, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 05:00: Prepared WH for installation of spool and XMT.
05:00 - 05:15: Performed tool box talk for lift of spool.
05:15 - 05:30: Removed hatch
05:30 - 06:00: Lifted down spool
06:00 - 07:00: Continuing lifting down spool and installed same on WH.
07:00 - 10:15: Tested spool piece to 35/345 bar for 5/15 min.
10:15 - 12:30: Transfered XMT from moonpool crane to chains and lowered same down onto spool. M/u same.
12:30 - 23:00: Tested spool/xmt connection. Worked on control lines connections on WH. Installed elbow on XMT and flowline. Installed half moon. Simulatneously started to prepare for and rig up WL equipment.
23:00 - 00:00: Removed XMT lifing cap and installed tree cap. Well handed over to production at 24 00 hrs.
| Prepared WH for installation of spool and XMT. Lifted down and installed spool. Lifted down and installed XMT. Tested seals. Worked on control lines and instrumentation. Installed tree cap and handed well over to production. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-06, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Well handed over to production at 00 00 hrs. Meanwhile continued instrumentation work on XMT
00:15 - 06:00: Production performing commisioning of XMT. Meanwhile finalized rigup for testing with cement unit and performed maintenance.
06:00 - 14:45: Production performing commisioning of XMT. Meanwhile spotted WL BOP in moonpool and brought WL equipment to rig floor. Built riser and lubrictaor sections for WL.
14:45 - 15:00: Held tool box talk with all involved personel for leak testing XMT.
15:00 - 16:30: Connected AWS test pump hose from WH panel
16:30 - 17:15: Performed line test from CMT unit to KWV, 20/345 bar for 5/15 min.
17:15 - 18:00: Filled XMT with packer fluid and closed SV. Confirmed line from PWV vented. Tested XMT body to 30/345 bar for 5/15 min against BPV.
18:00 - 18:30: Inflow tested MMV to 250 bar for 15 min.
18:30 - 19:00: Inflow tested HMV to 250 bar for 15 min.
19:00 - 19:15: Held tool box meeting
19:15 - 19:45: Opened HMV and closed KWV. Bled off pressure to 10 bar. Inflow tested KWV to 250 bar for 15 min.
19:45 - 21:15: Removed tree cap and retrieved dart and BPV.
21:15 - 22:00: Connected control hoses to XMT.
22:00 - 22:15: Performed tool box talk before rigging up.
22:15 - 22:45: Installed lower spool onto XMT, removed lifting cap.
22:45 - 23:30: Installed lifing cap onto WL BOP. P/u WL BOP and installed on lower spool.
23:30 - 00:00: Connected control hoses to WL BOP and function tested same.
| Handed well over to production for XMT commisioning. Received well from production. Performed inflow tests. Retrieved BPV and dart. Rigged up for WL. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-07, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: Continued to connect control hoses to WL BOP and function tested same.
00:45 - 01:15: Filled equipment with MEG
01:15 - 03:00: Tested WL riser. Observed leak in swab valve, applied back pressure and performed good test.
03:00 - 03:15: Held tool box talk
03:15 - 04:45: Installed mid riser jont and m/u same. Made up grease head and installed WL into lubrator head.
04:45 - 05:30: Installed t-bar and upper sheave on elevator. Connected slings to lubracator head.
05:30 - 06:00: P/u lubricator head
06:00 - 06:15: Continued to p/u lubricator head
06:15 - 07:00: Installed lower sheave and m/u sinker bars. Spotted slumb tool on rig floor.
07:00 - 07:15: Held tool box talk with ongoing shift.
07:15 - 08:00: P/u weight bars and m/u lubricator.
08:00 - 09:00: Tested line up to 345 bar. Tested WL lubricator and riser to 30/250 bar for 5/10 min.
09:00 - 09:15: Broke out QTS and l/d weight bars.
09:15 - 09:30: Held tool box talk.
09:30 - 15:00: Took WL head down for installation of toolstring. Tested same. P/u and m/u toolstring and guns. Tested same.
15:00 - 15:45: Tested QTS with test pump on rig floor to 30/250 bar for 5/10 min.
15:45 - 16:15: Opened MIV and filled riser and lubricator with MEG. Opened DHSV. Opened HMV.
16:15 - 20:15: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 3500 m 73,2 deg inclination.
20:15 - 00:00: Continued RIH with perforation string on WL using tractor.
| Continued rigging up WL well control equipment and tested same. P/u perforation toolstring. RIH with same on WL to 3500 m without using tractor. Continued RIH using tractor to 4300 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-08, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:00: Continued RIH with perforation string on WL with tractor from 4300 to 4400 m. Lost contact to tractor.
03:00 - 06:00: Trouble shot communication to tractor electronics cartridg
06:00 - 07:15: Trouble shot communication to tractor electronics cartridge)
07:15 - 09:15: POOH with perforation string on WL from 4200 m. Bled down lubricator, closed XMT.
09:15 - 09:30: Performed pre-job meeting prior to break out lubricator and l/d tractor unit.
09:30 - 11:45: Broke out lubricator at QST. L/d tractor unit. Checked and tested new tractor system.
11:45 - 12:00: P/u and m/u tool string.
12:00 - 12:30: M/u lubricator to QST and pressure tested connection to 30/250 bar for 5/10 min.
12:30 - 12:45: Filled lubricator and riser with MEG via MIV 240 ltr. Opened DHSV. Opened HMV.
12:45 - 15:00: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 3500 m 73,2 deg inclination.
15:00 - 18:00: RIH with perforation string on WL using tractor from 3500 m to 4400 m.
18:00 - 19:00: RIH with perforation string on WL using tractor from 4400 m to 4570 m. Observed high current on tractor. Experienced a lot of debris. Tractor can not push the gun after 4570m.
19:00 - 20:00: RIH with perforation string on WL using tractor. Worked down from 4570 m to 4600 m.
20:00 - 00:00: Switched to passthrough mode. Started correlating tool string according to program. MAX depth 4607 m. Performed first pass, second pass and third pass.
| RIH with perforation string on WL with tractor to 4400 m. Lost contact to tractor switch. Trouble shot communication to tractor. POOH with perforation string on WL. Changed out tractor unti. RIH with perforation string on WL/TRACTOR 4600 m. Started correlating tool string. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-09, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:45: Correlated tool string according to program between 4582 m to 4594 m. Performed fourth pass and fifth pass up on depth.
01:45 - 02:00: Bled off pressure on well from 52 bar to 35 bar prior to firing guns.
02:00 - 02:15: Correlated to position guns at interval 1 from 4582 m to 4594 m. Firing depht 4578 m.
02:15 - 02:30: Perforated interval from 4582 m to 4594 m with WHP 35 bar. WHP stabilized at 24,8 bar.
02:30 - 03:45: POOH with perforation string on WL from 4578 m while performed g-ray/ccl logging to 3750 m.
03:45 - 06:00: POOH with perforation string on WL from 3750 m. Powered down logging unit.
06:00 - 07:00: Tools in catcher. Closed SV, 9,8 bar siwhp. Closed HMW.
07:00 - 07:30: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to r/d lubricator and changing out tool string and l/o guns.
07:30 - 08:15: Bled off pressure in lubricator and purged clean with nitrogen.
08:15 - 10:45: Broke out lubricator at QST. L/d tractor, tool string and guns. Checked and tested new tractor system.
10:45 - 15:45: Performed test on tool string prior to p/u perforating run no. 2.
15:45 - 16:00: Performed pre-job meeting prior to p/u guns, tool string and tractor.
16:00 - 17:45: P/u guns, tool string and tractor for perforating run no. 2. M/u lubricator at QST.
17:45 - 18:15: Pressure tested lubricator to 250 bar. Filled riser with MEG.
18:15 - 22:15: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 4100 m 74,95 deg inclination.
22:15 - 23:45: RIH with perforation string on WL using tractor from 4100 m to 4565 m. WHP increased from 23,9 bar to 110 bar.
23:45 - 00:00: Correlated across interval 4524 m to 4536 m. First pass.
| Correlated across interval 4582 m to 4594 m. Perforated interval from 4582 m to 4594 m. POOH with perforation string on WL from 4578 m while performed g-ray/ccl logging to 3750 m. POOH and l/d gun assy. P/u perforating assy no. 2 and RIH with same to 4565 m. Correlated first pass. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-10, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 06:00: Correlated across interval 4524 m to 4536 m. 9 th pass.
06:00 - 06:45: Correlated across interval 4524 m to 4536 m. 9 th pass.
06:45 - 07:00: Perforated interval from 4524 m to 4536 m with WHP 15 bar. WHP stabilized at 25 bar.
07:00 - 09:30: POOH from 4536 m to 230 m with perforating gun assembly no. 2. Powered down logging unit.
09:30 - 10:00: Tools in catcher. Closed SV, 9,8 bar siwhp. Closed HMW.
10:00 - 10:30: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to r/d lubricator and changing out tool string and l/o guns.
10:30 - 10:45: Bled off pressure in lubricator and purged clean with nitrogen.
10:45 - 12:00: Broke out lubricator at QST. L/d tractor, tool string and guns. Checked and tested system.
12:00 - 16:30: Change cable head and prepared guns for run no. 3.
16:30 - 16:45: Performed pre-job meeting prior to p/u guns, tool string and tractor.
16:45 - 17:30: P/u guns, tool string and tractor for perforating run no. 3.
17:30 - 17:45: Trouble shot communication to tractor. Changed out tractor unit.
17:45 - 19:00: P/u guns, tool string and tractor for perforating run no. 3.
19:00 - 19:15: Performed pre-job meeting prior to complete and stab on lubricator.
19:15 - 19:45: M/u lubricator at QST. Pressure tested lubricator to 345 bar. Filled riser with MEG.
19:45 - 20:30: RIH with perforation string on WL to 500 m.
20:30 - 21:30: Performed test on tools. Lost communication to tools.
21:30 - 22:00: POOH from 500 m with perforation string on WL. Tools in catcher. Closed SV, 21,2 bar siwhp. Closed HMW.
22:00 - 23:00: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to break lubricator and check tool string.
23:00 - 23:30: Broke out lubricator at QST. Inspected and tested tool string firing head.
23:30 - 00:00: Removed firing head.
| Correlated across interval 4524 m to 4536 m. POOH with perforation string on WL from 4536 m. L/d gun assy. Change cable head. P/u perforating assy no. 3 and RIH with same to 500 m. Performed test on tools. Lost communication to tools. POOH with perforating assy no. 3. Inspected and tested tool string firing head. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-11, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: Checked firing head, crimped wire observed.
00:45 - 02:00: M/u firing head to tool string. Function tested tool string.
02:00 - 02:30: M/u lubricator at QST. Pressure tested lubricator to 275 bar. Filled riser with MEG.
02:30 - 03:00: Opened well and RIH with perforation string no. 3 on WL to 250 m.
03:00 - 05:45: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 4100 m 74,95 deg inclination.
05:45 - 06:00: Correlated across interval 4110 m to 4122 m.
06:00 - 08:00: Correlated across interval 4110 m to 4122 m. 5 th pass.
08:00 - 08:15: Perforated interval from 4110 m to 4122 m with WHP 10 bar. WHP stabilized at 31 bar.
08:15 - 10:30: POOH from 4112 m to 230 m with perforating gun assembly no. 3. Powered down logging unit.
10:30 - 10:45: Tools in catcher. Closed SV, 31 bar siwhp. Closed HMW.
10:45 - 11:00: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to r/d lubricator and changing out tool string and l/o guns.
11:00 - 11:15: Bled off pressure in lubricator and purged clean with nitrogen.
11:15 - 13:00: Broke out lubricator at QST. L/d tractor, tool string and guns.
13:00 - 19:00: Cutted electric line and re-connected cable head, prepared guns for run no. 4. Aker performed pressure test on rig up 20/250 bar with dummy tool string.
19:00 - 23:30: Worked on test tools and cable head. Checked and tested system.
23:30 - 23:45: Performed pre-job meeting prior to p/u guns, tool string and tractor.
23:45 - 00:00: P/u tractor and connected cabel head.
| M/u firing head to tool string. RIH with perforation string no. 3 to 4100 m. Correlated across interval 4110 m to 4122 m. Perforated interval from 4110 m to 4122 m. POOH with perforation string on WL from 4112 m. L/d gun assy. Re dressed cabel head. Pressure tested WL rig up. Checked and tested SLB system. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-12, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Performed system test on tractor. M/u lubricator at QST.
00:30 - 02:00: P/u guns and tool string for perforating run no. 4.
02:00 - 02:30: M/u lubricator at QST. Pressure tested lubricator to 275 bar. Filled riser with MEG.
02:30 - 03:15: Opened well and RIH with perforation string no. 4 on WL to 250 m.
03:15 - 06:00: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 4100 m 74,95 deg inclination.
06:00 - 07:45: Correlated across interval 4022 m to 4034 m.
07:45 - 08:00: Perforated interval from 4022 m to 4034 m with WHP 32 bar. WHP stabilized at 32 bar.
08:00 - 09:45: POOH from 4019 m to 230 m with perforating gun assembly no. 4. Powered down logging unit.
09:45 - 10:00: Tools in catcher. Closed SV, 32 bar siwhp. Closed HMW.
10:00 - 10:30: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to r/d lubricator and changing out tool string and l/o guns.
10:30 - 10:45: Bled off pressure in lubricator and purged clean with nitrogen.
10:45 - 12:00: Broke out lubricator at QST. L/d tractor, tool string and guns.
12:00 - 13:00: Performed test on cabel head.
13:00 - 15:00: Observed that the lubricator head suspension sling had caught up on elevator bolt. Performed pre-job meeting. Reslung lubricator head.
15:00 - 15:30: Serviced and inspected lubricator head. Inspected wire line upper sheave.
15:30 - 16:45: Performed test on tool string.
16:45 - 17:00: Performed pre-job meeting prior to p/u perforating assy no. 5.
17:00 - 17:45: P/u guns and tool string for perforating run no. 5.
17:45 - 18:15: M/u lubricator at QST. Pressure tested lubricator to 275 bar. Filled riser with MEG.
18:15 - 18:30: Opened well and RIH with perforation string no. 5 on WL to 250 m.
18:30 - 21:00: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 4000 m 71,3 deg inclination.
21:00 - 23:45: Correlated across interval 3890 m to 3902 m.
23:45 - 00:00: Perforated interval from 3890 m to 3902 m with WHP 32 bar. WHP stabilized at 32 bar.
| P/u guns for perforating run no. 4. RIH with perforation string to 4100 m. Correlated across interval and perforated interval from 4022 m to 4034 m. POOH from 4019 m and l/d tool string. Tested on cabel head and inspected lubricator head. P/u guns and tool string for perforating run no. 5. RIH with perforation string to 4000 m. Correlated across interval and perforated interval from 3890 m to 3902 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-13, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:15: POOH from 3987 m to 250 m with perforating gun assembly no. 5. Powered down logging unit.
02:15 - 02:30: Tools in catcher. Closed SV, 33 bar siwhp. Closed HMW.
02:30 - 04:00: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to r/d lubricator and changing out tool string and l/o guns.
04:00 - 04:15: Bled off pressure in lubricator and purged clean with nitrogen.
04:15 - 05:30: Broke out lubricator at QST. L/d tractor, tool string and guns.
05:30 - 06:00: Prepared guns for run no. 6 on deck.
06:00 - 09:15: Prepared guns for run no. 6 on deck. Tested tool string.
09:15 - 11:15: Wow. Wind speed above 40 knts. Cranes unavailabel for handling tool string. Performed pre-job meeting prior to p/u perforating assy no. 6.
11:15 - 14:15: L/o tool string from run no. 5. P/u guns and tool string for perforating run no. 6.
14:15 - 14:45: M/u lubricator at QST. Pressure tested lubricator to 250 bar. Filled riser with MEG.
14:45 - 15:00: Opened well and RIH with perforation string no. 6 on WL to 250 m.
15:00 - 19:00: RIH with perforation string on WL with 30 m/min according to program to 4045 m. Toolstring stopped moving at 3700 m 79 deg inclination. Used tractor from 3700 m to 3800 m.
19:00 - 21:45: Correlated across interval 3853 m to 3859 m.
21:45 - 22:00: Perforated interval from 3853 m to 3859 m with WHP 33,8 bar. WHP stabilized at 33 bar.
22:00 - 00:00: POOH from 3859 m to 1000 m with perforating gun assembly no. 6.
| POOH from 3859 m and l/d tool string. Prepared guns for run no. 6 on deck. Tested tool string. Wow. P/u perforation toolstring 6. RIH with same to 4045 m. Correlated across interval 3853 m to 3859 m and perforated interval. POOH to 1000 m with perforating assembly no. 6. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-14, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: POOH from 1000 m to 250 m with perforating gun assembly no. 6. Powered down logging unit.
00:30 - 00:45: Tools in catcher. Closed SV, 42 bar siwhp. Closed HMW.
00:45 - 03:30: Inflow tested HMV with siwhp 5 bar for 10 min. Meanwhile performed pre-job meeting prior to r/d lubricator and changing out tool string and l/o guns.
03:30 - 03:45: Bled off pressure in lubricator and purged clean with nitrogen.
03:45 - 05:00: Broke out lubricator at QST. L/d tractor, tool string and guns.
05:00 - 06:00: Prepared guns for run no. 7 on deck.
06:00 - 07:00: Prepared guns for run no. 7 on deck. Tested tool string.
07:00 - 07:15: Performed pre-job meeting prior to p/u perforating tool string no. 7.
07:15 - 09:00: P/u guns and tool string for perforating run no. 7.
09:00 - 09:45: M/u lubricator at QST. Pressure tested lubricator to 250 bar. Filled riser with MEG.
09:45 - 12:45: RIH with perforation string on WL with 30 m/min according to program. Toolstring stopped moving at 3620 m 77,6 deg inclination.
12:45 - 13:45: Continued RIH with perforation string on WL using tractor to 4100 m
13:45 - 15:45: Correlated across interval 3825 m to 3831 m.
15:45 - 16:00: Perforated interval from 3825 m to 3831 m with WHP 33,8 bar. WHP stabilized at 33 bar.
16:00 - 18:00: POOH from 1000 m to 250 m with perforating gun assembly no. 7. Powered down logging unit.
18:00 - 18:15: Tools in catcher. Closed SV, 42 bar siwhp. Closed HMW.
18:15 - 22:00: Inflow tested HMV with siwhp 5 bar for 10 min. Bled off pressure in lubricator and purged clean with nitrogen.
22:00 - 22:15: Performed pre-job meeting prior to r/d lubricator, tool string and l/o guns.
22:15 - 22:45: Broke out lubricator at QST. L/d tractor, tool string and guns.
22:45 - 00:00: R/d wire line equipment. B/d lubricator and l/d same on deck.
| POOH with perforating gun assembly no. 6. MU gun assembly no. 7. RIH with perforation string on WL to 3620 m. Tractor down to 4100 m. Correlated across interval 3825 m to 3831 m and perforated interval. POOH with perforating gun assembly no. 7. L/d tool string. R/d wireline. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2014-01-15, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: R/d wire line equipment. B/d lubricator and l/d same on deck.
00:45 - 01:15: Cleaned and cleared drill floor for exccess wire line equipment.
01:15 - 03:00: R/d wire line equipment. Disconnected top riser and removed wire line BOP.
03:00 - 03:45: R/d wire line equipment. Removed spool and riser joint from x-mas tree.
03:45 - 04:30: Installed half moon on f-15 and secured same.
04:30 - 04:45: Flushed lines with 1 m3 packer fluid
04:45 - 05:00: Installed tree cap and needle valve on xmas tree.
05:00 - 06:00: Started to pressure test x-mas tree, DHSV, MMV and HMV. According to procedure.
06:00 - 09:45: Bullheaded 3 m3 100 MEG, 6,6 m3 packer fluid and 1,2 m3 100 MEG.
09:45 - 11:30: Performed inflow test on DHSV, MMV and HMV.
11:30 - 12:00: R/d chicksan lines and valves from x-mas tree.
12:00 - 13:30: Pressure tested x-mas tree cap to 250 bar.
13:30 - 14:00: Cleared well head area for excces equipment.
14:00 - 15:00: Prepared and handed over well to production. Await decision for f-1 operation. Operation completed continued operation on 15/9 f-99. Await decision for f-1 operation.
| R/d wire line equipment. Installed cap and needle valve on x-mas tree. Inflow tested DHSV, MMV and HMV. R/d chicksan lines and valves. Pressure tested x-mas tree cap to 250 bar. Handed over well to production. Operation completed continued operation on 15/9 f-99. Await decision for f-1 operation. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-05, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 11:00 - 17:30: Vessel arrived rig. Spotted equipment in work area on pipedeck. Prepared equipment and checked inventory.
17:30 - 18:30: Personnel arrived rig.
18:30 - 19:30: Continued to prepare equipment on pipedeck
19:30 - 20:00: Held brief with platform management for day and night shift.
20:00 - 21:00: Continued to prepare equipment on pipedeck
21:00 - 22:00: Held start up meeting regarding well operation with all involved personnel.
22:00 - 00:00: Electrican hooked up wireline units and logging-cabin to rig power and fire gas
| Arrived rig and spotted equipment. Started to rig up wireline equipment on pipedeck. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-06, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:00: Continued to hook up units to rig power and fire gas. Meanwhile prepared hoses for BOP test and chicksan for XMT.
03:00 - 07:00: Function tested BOP. Leak tested same on stump to 345 bar. Meanwhile changed well hatch to wireline hatch in moonpool.
07:00 - 08:00: Function tested wireline winch and spooled out cable.
08:00 - 08:15: Performed TBT for building GIH.
08:15 - 10:00: Started to build GIH.
10:00 - 11:00: Performed start up meeting for operation with dayshift.
11:00 - 12:00: Continued to build GIH and threaded cable through same.
12:00 - 15:30: Spotted w/l grease and rx72 to drill floor. Rearranged equipment on pipedeck and completed z-015 checklist. Meanwhile prepared BOP for lifting.
15:30 - 16:30: Lifted BOP down to wellhead area and riser pieces to drill floor.
16:30 - 19:00: Well handed over from production to d&w. Meanwhile build lubricator and riser horizontally on drillfloor.
19:00 - 00:00: Rigged up chiksan lines on XMT kill wing manifold. Hooked up altus pump skid for local control of DHSV and HMV.
| Rigged up w/l equipment on pipe deck. Leak tested BOP on stump. Recieved well from production dept. To d&w. Installed lower riser and BOP to XMT. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-07, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: Hooked up equalizing loop from SWV to PW. Leak tested SW manifold to 20/345 bar for 5/10 min.
01:00 - 02:00: Removed top cap from XMT and installed lower riser.
02:00 - 02:15: Performed TBT for installation of wireline BOP
02:15 - 02:45: Moved BOP into position and installed BOP onto lower riser.
02:45 - 03:45: Installed hydraulic control hoses onto BOP. Function tested and performed visual connection test on lower riser and BOP against SV to 345 bar for 5 min.
03:45 - 04:00: Performed TBT prior to p/u riser.
04:00 - 05:15: P/u riser and connected onto BOP. Installed QTS onto riser stick up. Changed elevator inserts and installed t bar and wireline sheave.
05:15 - 08:00: Prepared lubricator and hooked up GIH hoses. Meanwhile recieved remaining equipment from supply vessel. gun basket and container)
08:00 - 08:15: Performed TBT for testing c/l to DHSV and HMV.
08:15 - 12:40: Tested c/l to DHSV and HMV to 520 bar. Hooked up n2 bottle rack for emergency air supply to grease skid. Meanwhile checked counter wheel on w/l winch. Secured hoses on lubricator. Meanwhile schlumberger tested perforation tools and l/d guns on pipe deck.
12:40 - 13:25: Prepared lubricator for lifting.
13:25 - 13:40: Performed TBT for lifting and installation of lubricator.
13:40 - 15:00: Lifted lubricator for installation on top of riser. Stopped lifting operation due to challenges to maneuver lubricator by using tugger.
15:00 - 15:20: Peformed TBT for lifting lubricator and installing tractor.
15:20 - 16:30: Lifted lubricator on top of riser. Had to use rig crane to assist lift.
16:30 - 18:00: Hooked up closed drain hose on wellhead. Meanwhile built toolstring for lubricator leak test. Filled lubricator with MEG.
18:00 - 19:45: Installed tractor in lubricator and leak tested rig up to 20/345 bar for 5/10 min. Leak tested bleed off line to 20/150 bar for 5/10 min.
19:45 - 21:30: Bled off lubricator, purged lubricator with n2 and drained MEG in riser to closed drain.
21:30 - 21:45: Peformed TBT prior to disconnecting lubricator and l/d toolstring.
21:45 - 22:00: Disconnected lubricator and l/d toolstring.
22:00 - 00:00: Schlumberger tested logging tools and altus tractor.
| Completed rigging up w/l equipment on well. Leak tested rig up. Started to build BHA for pef. Run. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-08, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:45: Continued testing schlumberger and altus BHA. Discovered issue with compatabilty between altus voltage protector module and schlumberger GR/CCL logging module.
01:45 - 02:15: Evaluated situation. Discussed different options.
02:15 - 07:45: Altus and schlumberger rearranged toolstring and tested different options. Decided to run single logging run without perf. Guns.
07:45 - 08:00: Performed TBT for r/u logging BHA.
08:00 - 10:05: M/u BHA for run 1 1/8'' tractor and GR/CCL). Added 40 litr ramex 50/50 MEG in riser. Leak tested lubricator/qts to 20/345 bar 5/10 min.
10:05 - 11:00: Equalized and opened HMV and pumped MEG for equalizing DHSV. Opened DHSV. WHP 68 bar. Equalized and opened SV with 43 turns.
11:00 - 14:30: RIH w/bha by gravity from 0 m to 3500 m, WHP 68 bar. Toolstring stopped at 3500 m. Depth p/u weight 500 m 1020 lbs 1000 m 1475 lbs 1500 m 2070 lbs 2000 m 2740 lbs 3000 m 3750 lbs 3500 m 4000 lbs friction factor calculated to 0,25. Held well control drill after DHSV was passed and verified open leak in GIH.
14:30 - 15:25: RIH with tractor activated from 3500 m to 3900 m. Stopped at logging depth.
15:25 - 15:30: Started to POOH to perform GR/CCL logging. Had to stop after 50 m due to noice from w/l winch drum.
15:30 - 18:10: Adjusted w/l drum position.
18:10 - 18:30: Continued to POOH for 200 m while logging GR/CCL. Observed same noice from w/l drum.
18:30 - 19:50: Called out mechanic. Was able to adjust w/l drum to correct position. Continued to POOH while logging.
19:50 - 20:30: Continued to POOH while logging GR/CCL from 3650 m to 3348 m. POOH.
20:30 - 23:10: POOH with BHA#1 from 3348 m to surface. WHP 69 bar. Meanwhile petec verified GR/CCL correlation log OK.
23:10 - 00:00: Closed SV HMV and inflow tested same. Bled off lubricator and purged r/u with n2 to closed drain.
| Troubleshoot altus and schlumberger BHA compatibility. Decided to run a sperate logging run w/o perforation guns. M/u logging BHA and performed GR/CCL pass across 3900 m to 3350 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-09, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:25: Continued to drain lubricator to closed drain.
01:25 - 01:35: Performed TBT prior to l/d toolstring.
01:35 - 02:20: Broke lubricator and l/d tractor and GR/CCL.
02:20 - 04:00: Schlumberger and altus checked compatibility issue.
04:00 - 05:45: Schlumberger and altus performed hot check for perforation run
05:45 - 06:00: Performed TBT prior to m/u tractor and perforation guns.
06:00 - 07:00: M/u BHA for perf. Run
07:00 - 07:15: Performed TBT for dayshift.
07:15 - 09:00: Continued m/u BHA 1/8'' tractor and 4,5'' perf. Guns). Added 30 litr ramex 50/50 MEG in riser. Leak tested lubricator/qts to 20/345 bar 5/10 min.
09:00 - 12:15: RIH w/ BHA by gravity from 0 m to 3521 m. WHP 71bar. Depth p/u weight 500 m 2700 lbs 1000 m 3300 lbs 1500 m 4050 lbs 2000 m 4800 lbs 2500 m 5650 lbs 3000 m 5400 lbs 3500 m 5400 lbs
12:15 - 12:50: Correlated across pup at 3472 m.
12:50 - 12:55: Continued RIH w/ BHA from 3521 m to 3565 m. Toolstring stopped.
12:55 - 13:10: RIH with tractor activated from 3565 m to 3592 m. Lost communicaton with tractor.
13:10 - 14:00: Troubleshooted tractor. Not possible to activate tractor. Decided to POOH.
14:00 - 14:10: POOH from 3592 to 3355 m. Add-on drum turned and came out of position and damaged cable.
14:10 - 14:50: Inspected cable and found wire strand damaged.
14:50 - 15:35: Time out and evaluated situation. Aligned and secured add-on drum.
15:35 - 21:00: POOH from 3355 m to surface. WHP 72 bar. Closed SV HMV and inflow tested same. Bled off lubricator and purged r/u with n2 to closed drain. Meanwhile mobilised new cable from onshore.
21:00 - 21:15: Performed TBT for l/d toolstring and lubricator.
21:15 - 00:00: Broke lubricator. L/d BHA on deck. L/d lubricator on catwalk. Spoled back cabel to winch.
| RIH wiht BHA perf. Run Lost communicaton with tractor. Add-on drum came out of position and damaged cable. POOH and l/d BHA. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-10, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 04:30: Not able to continue operation with cable. Had to order new cable from onshore. Meanwhile checked tractor failure. Cleaned drill floor. Prepared add-on drum to be shipped onshore.
04:30 - 06:00: Waited on new cable from onshore.
06:00 - 18:00: Waited on new cable from onshore.
18:00 - 00:00: Waited on new cable from onshore.
| Waited for new add-on drum with 7/16'' cable from onshore. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-11, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 06:00: Waited on new cable from onshore. Meanwhile performed well control drill with service companies involved in operation.
06:00 - 09:15: Waited on new cable from onshore.
09:15 - 09:35: New add-on drum arrived on rig. Hooked up add-on drum to WL winch. Evaluated the need to cut of cable from drum due to high resistance on cable. Meanwhile checked tractor on deck.
09:35 - 11:55: Waited on light" form onshore to cut cable.
11:55 - 13:10: Positioned add-on container for spooling of cable. Connected add-on drum and spooled of 1586 m cable into skip.
13:10 - 13:55: Repositioned add-on drum and hooked it up.
13:55 - 14:40: Threaded cable through GIH.
14:40 - 16:25: Built cable head. Meanwhile secured add-on drum with tie-down chains. Held TBT on rig floor prior to p/u lubricator.
16:25 - 17:30: Function tested tractor and schlumberger tested CCL and firing system.
17:30 - 21:45: P/u lubrictor and installed toolstring for leak test. Filled lubricator with MEG and leak tested same to 20/345bar 5/10 min.
21:45 - 22:00: Performed TBT for disconnect lubricator and m/u BHA#3 for perf. Run
22:00 - 00:00: Disconnected lubricator and m/u BHA#3 for perf. Run Added 30 litr ramex 50/50 MEG in riser.
| Received add-on drum with new 7/16'' cable from onshore. Leak tested lubricator. RIH with BHA#3 perf. Run# 1. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-12, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: Leak tested QTS to 20/345 bar 5/10 min. Equlized SV and HMV using MEG. WHP 75 bar.
01:00 - 05:00: RIH w/bha by gravity from 0 m to 3390 m, WHP 75 bar. Toolstring stopped at 3390 m. Depth p/u weight 400 m 3200 lbs 1200 m 4100 lbs 2000 m 5500 lbs 2800 m 6600 lbs 3200 m 6200 lbs friction factor 0,25.
05:00 - 05:25: RIH with tractor activated from 3390 m to 3520 m.
05:25 - 06:00: Correlated from 3520 m across pup joint at 3472 m at 10 m/min. Stopped at 3442 m. Activated tractor.
06:00 - 06:50: Tractored down at 10 m/min from 3442 m to 3810 m.
06:50 - 09:00: Performed correlation, 5 passes in interval 3810 m to 3708 m, used tractor when RIH.
09:00 - 09:10: P/u at 10 m/min to 3743 m CCL depth. Bottom BHA at 3772 m placing top shot at 3748 m and bottom shot at 3766 m. HW 5880 lbs. WHP 75,1 bar. BHP 281 bar.
09:10 - 09:15: Perforated well in interval 3748 m to 3766 m. WHP increased to 79 bar and BHP increased to 285 bar.
09:15 - 09:30: POOH at 10 m/min and logged CCL up to 3572 m.
09:30 - 10:55: Continued POOH to 500 m. Prepared for handling explosives on surface.
10:55 - 11:25: POOH to surface.
11:25 - 13:10: OOH, closed SV and HMV inflow tested same. Bled of pressure in r/u to closed drain. Flushed r/u with n2.
13:10 - 16:00: Disconnected lubricator. Production measured benzene to 10 ppm inside riser and 0 ppm outside riser. L/d BHA#3.
16:00 - 17:40: Prepared tools for BHA#4 for perf. Run#2.
17:40 - 19:30: Observed gas in cablehead, megging not satisfied. Had to ventilate gas out of cable.
19:30 - 20:50: Performed altus schlumberger tractor check.
20:50 - 21:00: Performed TBT for r/u toolstring.
21:00 - 22:55: R/u toolstring perf. Run#2. Added 40 litr ramex 50/50 MEG in riser. Leak tested QTS to 20/345 bar 5/10 min. Equlized SV and HMV using MEG. WHP 79 bar
22:55 - 00:00: RIH w/bha 1/8'' tractor and 4 1/2'' perf. Guns) by gravity from surface to 1200 m.
| RIH with BHA#3 perf. Run#1. Perforated with top shot at 3748 m and bottom shot at 3766 m. POOH and l/d BHA. Prepared and RIH with BHA#4 for perf. Run#2. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-13, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:05: Continued RIH by gravity from 1200 m to 3392 m, WHP 79 bar. Toolstring stopped at 3392 m. Depth p/u weight 400 3200 lbs 800 3700 lbs 1200 4100 lbs 1600 4950 lbs 2000 5500 lbs 2400 6300 lbs 2800 6600 lbs 3200 6200 lbs friction factor 0,19
02:05 - 02:30: RIH with tractor activated from 3392 m to 3610 m. Average running speed 15 m/min.
02:30 - 03:50: Performed 3 orientation passes from 3610 m 3450 m. Used tractor when RIH
03:50 - 05:05: Correlated across interval 3610 3450 m. Positioned gun with top shot at 3540 m and bottom shot at 3552 m. WHP 79 bar. BHP 285. 5
05:05 - 05:10: Perforated well in interval 3540 m to 3552 m. WHP increased to 82,5 bar and BHP increased to 289 bar.
05:10 - 06:00: POOH with perf. Run#2 from 3540 m to surface at 30 m/min.
06:00 - 07:45: Continued POOH to surface.
07:45 - 08:25: OOH, closed SV and HMV. Inflow tested HMV. Siwhp 81 bar.
08:25 - 09:40: Bled of pressure in lubricator and purged r/u with n2 to closed drain.
09:40 - 11:20: Disconnected lubricator and l/d BHA 1/8'' tractor and 4 1/2'' perf. Guns). All shots fired.
11:20 - 13:20: Spooled out cable. Altus tractor checked BHA components.
13:20 - 15:25: Built new cable head. Performed torsion test on cable had more than 10 turns, cable OK.
15:25 - 16:00: Function tested BHA on deck, had some problems with telemetri. Altus not able to communicate with tractor.
16:00 - 18:00: Altus tractor troubleshoted communication problems with tractor. Altus tractor re-started surface equipment and function tested OK.
18:00 - 20:00: Tested toolstring for perf. Run#3 and checked equipment according to schlumberger check list.
20:00 - 20:15: Performed TBT for m/u BHA#5 for perf. Run#3
20:15 - 21:15: M/u BHA#5 for perf. Run#3. Added 30 liter ramex and 50/50 MEG.
21:15 - 21:50: Leak tested QTS to 20/345 bar 5/10 min. Equlized SV and HMV using MEG. WHP 83 bar.
21:50 - 00:00: RIH w/bha#5 1/8'' tractor and 4 1/2'' perf. Guns) by gravity from surface to 2800m.
| RIH with perf. Run#2. Perforated with top shot at 3540 m and bottom shot at 3552 m. POOH and l/d BHA. Prepared and RIH with BHA#5 for perf. Run#3. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-14, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: Continued RIH by gravity from 2800 m to 3408m, WHP 83 bar. Toolstring stopped at 3408 m. Depth p/u weight 400 2550 lbs 800 2950 lbs 1200 3500 lbs 1600 4100 lbs 2000 4700 lbs 2400 5400 lbs 2800 5200 lbs 3200 5300 lbs 3407 5300 lbs friction factor 0,22
00:45 - 02:00: RIH with tractor activated from 3408 m to 3560 m.
02:00 - 02:45: Performed 3 orientation passes from 3545 m 3450 m. Used tractor when RIH.
02:45 - 03:15: Correlated across interval 3545 m 3450 m. Positioned gun with top shot at 3508 m and bottom shot at 3517 m WHP 83 bar. BHP 289,5 bar.
03:15 - 03:20: Perforated interval 3508 m 3518 m. WHP increased to 86 bar. BHP increased to 293 bar.
03:20 - 06:00: POOH from 3503 m to surface. Average pulling speed 30m/min.
06:00 - 06:35: OOH, closed SV and HMV. Inflow tested HMV. Siwhp bar 86 bar.
06:35 - 08:00: Bled of pressure in lubricator and purged r/u with n2 to closed drain.
08:00 - 08:10: Performed TBT for disconnecting lubricator and l/d toolstring.
08:10 - 09:30: Disconnected lubricator and l/d BHA 1/8'' tractor and 4 1/2'' perf. Guns). All shots fired.
09:30 - 09:45: Spooled out cable. Altus tractor checked BHA components.
09:45 - 12:30: Altus tractor and schlumberger function tested equipment and prepared toolstring for next run. Meanwhile tested cable head.
12:30 - 13:15: M/u BHA#6 for perf. Run#4. Added 40 liter ramex.
13:15 - 13:55: Leak tested QTS to 20/345 bar 5/10 min. Equlized SV and HMV using MEG. WHP 86 bar.
13:55 - 16:40: RIH w/bha#6 1/8'' tractor and 4 1/2'' perf. Guns) by gravity from surface to 3310 m. WHP 86 bar. Toolstring stopped at 3310 m. Depth p/u weight 400 2530 lbs 800 3100 lbs 1200 3450 lbs 1600 4040 lbs 2000 4530 lbs 2400 4800 lbs 2800 5300 lbs 3200 5600 lbs 3407 4800 lbs friction factor 0,21
16:40 - 17:00: RIH with tractor activated from 3310 m to 3535 m. Average running speed 12 m/min.
17:00 - 18:00: Performed 3 orientation passes from 3540 m to 3435 m. Used tractor when RIH.
18:00 - 18:35: Correlated across interval 3540 to 3435 m. Positioned gun with top shot at 3483 m and bottom shot at 3491m. WHP 86 bar. BHP 293,5 bar.
18:35 - 18:40: Perforated well in interval 3483 m to 3491 m. WHP increased to 87 bar and BHP increased to 294 bar.
18:40 - 21:00: POOH with perf. Run#4 from 3477 m to surface at 30 m/min.
21:00 - 22:00: OOH, closed SV and HMV. Inflow tested SV and HMV. Siwhp 87 bar.
22:00 - 22:45: Bled of pressure in lubricator and purged r/u with n2 to closed drain.
22:45 - 23:00: Performed TBT for l/u toolstring and lubricator.
23:00 - 00:00: Disconnected lubricator and l/d BHA#6 1/8'' tractor and 4 1/2'' perf. Guns). All shots fired.
| RIH with perf. Run#3 and perforated across interval 3508 m 3517 m. POOH. RIH with perf. Run#4 and perforated across interval 3483 m 3491 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-15, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:30: Continued l/d toolstring and lubricator. WHP 87 bar.
02:30 - 04:00: Closed BOP and DHSV and bled down to 5 bar above DHSV. WHP when closing DHSV 87 bar. BHP 294 bar. Inflow tested DHSV for 30 min with 87 bar below and 5 bar above. Pressure above DHSV increased 0,3 bar/30 min. Closed HMV. Meanwhile r/d altus w/l, tractor and schlumberger peforation equipment.
04:00 - 07:45: Continued to r/d altus w/l, tractor and schlumberger peforation equipment.
07:45 - 10:00: Disconnected chiksan on wellhead. Disconnected and lifted BOP to drill floor.
10:00 - 13:00: Installed and leak tested XT top cap 5/10min 20/345bar. Leak tested KWV cap 5/10min 20/345bar.
13:00 - 15:00: R/d and prepared w/l equipment for backload.
15:00 - 16:00: Handed well over to production.
16:00 - 00:00: R/d and packed w/l equipment.
| POOH with perf. Run#4. L/d toolstring and r/d wireline equipment. Tested SV and HMV. Inflow tested DHSV. Tested top cap and XMT. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-15 D on 2015-08-16, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 04:00: Cleaned drillfloor and moonpool area.
04:00 - 07:00: Cleaned pipedeck. Ended operation on well
| None |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2007-12-01, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 04:30 - 04:45: Held toolbox talk prior to skidding rig from f-9 to f-1.
04:45 - 06:00: Skidded rig port. Started to skid rig/cantilever forward.
06:00 - 08:15: Skidded rig/cantilever forward to slot f-1. Picked up stabd of drillpipe and ran through f-1 slot. Checked allignment over slot and made adjustments accordingly. Built scaffolding around f-1 wellslot. Installed 2nd hatch in moonpool.
08:15 - 08:30: Held toolbox talk prior to picking up 36" holeopener BHA.
08:30 - 09:30: Picked up 36" x 26" x 17 1/2" holeopener and hung off in RT. Removed dog collar on drill guide bushing. Made up holeopener to BHA.
09:30 - 10:15: Made up DC and ran in with 36" holeopener BHA to 133 m MD.
10:15 - 10:45: While observing with ROV, stabbed BHA into funnel at 140 m MD. Tagged seabed at 144,3 m with 5 MT wob.
10:45 - 11:00: Washed down from 144 m to 145 m with 1000 LPM.
11:00 - 15:00: Drilled 36" hole section from 145 m to 165 m MD with reduced drilling parameters flow 600-1000 LPM rotation 10-25 RPM wob 1-3 MT torque 3-16 KNM. ROV observed that drill guide bushing landed in funnel. Survey at 165 m MD 0,21 deg. High torque and excessive rattling in string from 160-165 m MD.
15:00 - 22:30: Drilled 36" hole section from 165 m to 17 1/2 TD at 226 m MD 36" TD at 223 m MD. Drilling parameters flow 4100-4400 LPM rotation 70-90 RPM wob 1-3 MT torque 5-7 KNM. Swept hole with 20 m3 hi-vis before connection. Performed survey every 10 m. Final survey at 226 m MD 0,18 deg.
22:30 - 23:00: Ciruculated hole clean by pumping 1,5 x hole volume of seawater while reaming with 10 RPM.
23:00 - 23:15: Pumped 25 m3 hi-vis sweep followed by 60 m3 sewater at 4400 LPM. Mechanical popoff on mudpump triggered unintentionally, no pressure spike observed. Discussed situation. Decided to continue operations and displace to 1,40 SG mud using only one mudpump.
23:15 - 00:00: Displaced hole from seawater to 1,40 SG WBM pumping with a limited rate of 2200 LPM.
| Skidded rig to f-1. Picked up and RIH with 36" holeopener BHA. Drilled 36" hole from seabed to 226 m MD. Displaced hole to 1,40 SG WBM. POOH with 36" holeopener BHA. Racked back BHA. Laid down DC, MWD and holeopener. Transferred tension cylinder to centralizer deck. Performed FG inspection of derrick. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2007-12-02, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Continued to displace well to 1,40 SG WBM with limited rate of 2200 LPM. Pumped a total of 95 m3 1,40 SG WBM.
00:15 - 00:45: POOH with 36" holeopener BHA from 226 m to 215 m MD. Observed 10 MT overpull at 215 MD. Pipe free to move down. Applied 5 RPM rotation and pulled through thightspot while rotating. Stopped rotating at 213 m MD and continued pulling, no excessive drag observed.
00:45 - 01:30: POOH with 36" holeopener BHA from 213 m to 150 m MD on 5 1/2" HWDP. Topped up well with 5 m3 1,40 SG WBM pumping at 1000 LPM.
01:30 - 02:00: Pulled 36" holeopener through template funnel to 128 m MD. Pumped 20 m3 seawater at 1800 LPM to clean string and surface lines.
02:00 - 04:15: Pulled and racked back BHA. Broke out and laid down 9 3/4" DC and MWD.
04:15 - 05:00: Laid out 36" x 26" x 17 1/2" holeopener and prepared for backload.
05:00 - 05:45: Transported 1 x tension cylinder from drillfloor to centralizer deck using tugger. Performed FG-CHECK in derrick.
05:45 - 06:00: Held toolbox talk prior to rigging up 30" conductor handling equipment.
06:00 - 07:00: Removed drilling bails and elevator. Installed conductor bails and elevator. Brought conductor running equipment to riigfloor.
07:00 - 07:30: Held toolbox talk prior to running conductor.
07:30 - 08:00: Removed masterbsuhing and installed 30" conductor inserts in rotary.
08:00 - 09:15: Picked up float shoe and hung off. Picked up conductor joint and made up to shoe. Filled shoe and checked for flowthrough OK.
09:15 - 11:30: Ran 30" conductor from 20 m to 68 m MD.
11:30 - 13:00: Held toolbox talk prior to changing handling gear. Changed from conductor bails/elevator/insert to 5 1/2" handling equipment.
13:00 - 15:15: Held toolbox talk prior to picking up 30 conductor housing. Made up conductor housing to conductor, applied 33000 ft lbs m/u torque. Ran in with conductor to 82 m MD. Installed c-plate in rotary and landed conductor. Removed handling cart. Filled 30" conductor with 14 m3 seawater. Meanwhile held toolbox talk for running innerstring.
15:15 - 17:15: Installed c-plate on top of conductor housing. Ran 7 ea 4 3/4" aluminum innerstring joints inside conductor. Installed centralizer on joint Changed seals on running cart. Made up cart to innerstring. Installed inclinometer and fillup valve handle on cart. Reading on inclinomenter pitch 0,3 roll 0,1.
17:15 - 17:30: Landed cart in conductor housing and made up to same by 5 lefthand turns.
17:30 - 18:15: Picked up conductor and removed c-plate in rotary. Ran conductor below rotary and installed masterbushing, hung off on slips.
18:15 - 19:15: Picked up 5 1/2" DP double and RIH with conductor. Guided conductor through centralizer deck using sling and chainhoist.
19:15 - 20:00: Ran in hole with 30" conductor on dedicated landing string to 138 m MD to put top of conductor below sealevel. Filled conductor with with 16 m3 seawater at 2000 LPM. Hookload after filling 110 MT.
20:00 - 21:30: Stabbed conductor into guide funnel while observing with ROV. Ran in with conductor to 221 m MD and landed 10 cm below 112,88 m mark on pipe relative to centralizer deck. Meanwhile engaged hotstab in bank on template base and shifted handle to Hookload at TD 100 MT, no excessive drag observed in hole.
21:30 - 21:45: Made digiquartz measurement indicating that conductor housing f-1 was 45 mm higher than reference well f-7.
21:45 - 22:00: Adjusted height of conductor by comming down 3 cm. Made new digiquartz measurement indicating f-1 25 mm higher than reference well f-7 OK. Read inclinometer on cart pitch 0,3 roll 0,11.
22:00 - 00:00: Attempted to pressure up on hotstab to energize centralizing pistons in funnels nogo observed that hotstab was leaking rapid pressure bleed off. Worked hotstab further in and re-attempted pressuring up. Correct indications on pump with regards to volume and steady 2000 psi pressure on pump, but no movment of pistons could be observed. Attempted to move handle which was bent and fell off. Discussed situation. Decided to go ahead with cement job. Meanwhile leaktested lineup from cement unit to lo-torque to 200 bar 10 min OK.
| Rigged up conductor handing equipment. Ran 30" conductor and innerstring. Made elevation measurements of wellhead housing. Made attempt to run conductor centralizing pistons nogo broke ROV handle on bank#1. Attempted to perform cement job, but got problems with bulk transfer system. Circulated out cement. Re-started cement operation. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2007-12-03, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Made x-y measurements on conductor relative to funnel FWD 38 cm aft 34 cm STB 34 cm port cm data due to bad access).
00:15 - 01:15: Circulated hole to seawater before cementing. Stepped pumps up to 1500 LPM. No annulus returns could be observed by ROV. Inspected template for returns elsewhere but none could be observed. No return observed after 60 m3 pumped. Hookload rose from 100 MT to 110 MT during displacement indicating lighter fluid in annulus.
01:15 - 02:00: Increased pump rate to 2000 LPM. Pumped another 40 m3. After 15 min pumped, observed returns from annulus. Hookload levelled out at 112 MT.
02:00 - 03:30: Attempted to mix and pump cement. Had severe problems transferring dry x-lite cement from bulk system to surge tank. Automatic transfer system was not working. Could not keep a steady transfer rate by manual operation. Not possible to obtain prescribed cement slurry. Pumped 12 m3 cement of varying weights at slow rate. Aborted operation.
03:30 - 05:45: Displaced cement to drillfloor and circulated out same by pumping 40 m3 of seawater at 2000 LPM with rigpumps. Meanwhile washed cement unit and troubleshot bulk transfer system. Rig air pressure insuffcient to operate cement bulk system.
05:45 - 06:00: Started cementing. Hookload before start 109 MT.
06:00 - 07:30: Mixed and pumped 60 m3 1,52 SG tuned light cement slurry. Pump rate 800-1100 LPM. Pump pressure 20 bar. Displaced cement with 6,5 m3 seawater to put theoretical top of cement at 217 m MD inside conductor. Hookload during cementing fell from 110 MT to 100 MT indicating annulus displaced to heavier fluid.
07:30 - 08:00: Closed lo-torque on cement strand. Broke off cement hose and flushed manifolds.
08:00 - 19:30: Waited on cement to set up. Meanwhile hotstab and guidewire work on aft PRS new rubber conveyor belt on HTS work on tensioner cylinders on f-14 PM on drillfloor
19:30 - 20:45: Performed toolbox meeting prior to disconnecting cart. Slacked off 10 MT to obtain neutral at cart. Disconnected cart from conductor housing with 5 righthand turns. Lifted out cart and set slips on landing string. Broke out and laid down cementing stand. Pumped 2 ea sponge balls at 2500 LPM to clean string. Reading on inclinometer before disconnect pitch 0,34 deg roll 0,06 deg.
20:45 - 23:15: POOH with cart tool on 5 1/2" HWDP landing string. Racked back landing string. Broke out and laid out cart for backload. Meanwhile the ROV checked elevation of conductor housing with digiquartz. F-1 was 5 mm higher than reference well f-7.
23:15 - 00:00: POOH with 4 3/4" aluminium innerstring using tugger and clamps. Cleared and tidied drillfloor.
| Cemented 30" conductor. WOC. POOH with cart running tool and innerstring. Prepared for skidding to f-14. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2007-12-04, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: Installed hatches in wellhead module slot f-1 with tugger support from drillfloor. Removed/moved scaffolding barriers in wellhead module as required. Removed stairs to cantilever in preparation for skidding. Meanwhile ROV dredged to access CTS hose which was burried in mud/cuttings. Transferred operations to f-14
| None |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-21, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 23:00 - 00:00: Held tool box talk. Skidded rig 2. 1 m port.
| Skidded rig 2. 1 m port to position well center above slot f-1 |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-22, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Skidded rig 2. 95 m total port and positioned well center above slot f-1.
00:30 - 06:00: Changed out topdrive saver sub and leak tested wash pipe. Changed handling equipment and cleared rig floor of excess equipment. Meanwhile prepared 26" steerable BHA.
06:00 - 12:15: P/u and m/u 26" mud motor steerable BHA to 36 m. Plugged-in MWD tools. Observed communication problems between bi-communicational pulse module and gyro sub.
12:15 - 14:15: Troubleshoot tool communication failure.
14:15 - 17:15: P/u and m/u 26" mud motor steerable BHA to 103 m. ROV in for close cover.
17:15 - 17:45: RIH with 26" BHA on 5 1/2" HWDP from 103 m to 130 m and removed debris cap from cuttings transport system. ROV in for close cover.
17:45 - 18:00: RIH with 26" BHA on 5 1/2" HWDP from 130 m to 145 m inside 30" conductor.
18:00 - 19:15: R/u gyro wireline sheaves and wire
19:15 - 19:30: RIH with 26" BHA on 5 1/2" HWDP from 145 m to 184 m.
19:30 - 19:45: RIH with 26" BHA on 5 1/2" DP from 184 m to 212 m.
19:45 - 20:00: Recorded up/dn weight, 98/95 MT and established washing parameters with 2500 LPM, 3 bar, 20 RPM, 3 KNM.
20:00 - 20:15: Washed down from 212 m and tagged TOC at 217 m with 2 MT.
20:15 - 00:00: Drilled out cement, float and rat hole from 217 m to 226 m with 3500 LPM, 85 bar, wob 1-2 MT, 60 RPM, 3-. 6 KNM.
| Skidded rig to slot f-1 and serviced drilling equipment. P/u and m/u 26" mud motor steerable BHA. Drilled out excess cement, 30" conductor float and rat hole. Meanwhile filled x-mas tree with MEG and pressure tested tree cap to 30/200 bar for 5/10 min. Pressure tested SV to 30/200 bar for 5/10 min bullheaded fluid train 3m3 MEG, 6. 6 m3 packer fluid and 1. 2 MEG m3 inflow tested scsssv for 30 min. Futher testing suspended untill f-1 below scsssv. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-23, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Cleaned out rat hole and reamed same 3 times with 3500 LPM, 85 bar, 60 RPM, 0-1 KNM.
00:30 - 02:30: Run wireline gyro. Orientated mud motor tool face and retrieved gyro. Meanwhile torque-up wash pipe connection.
02:30 - 05:30: Established drilling parameters. Drilled and orientated 26" hole from 226 m to 252 m with 2500-3000 LPM, 60-70 bar, wob 10-14 MT, average ROP 10 m/hr. Drilled new formation at 02 50 hrs.
05:30 - 07:00: R/u and run wireline gyro. Recorded single shot gyro and r/d wireline.
07:00 - 15:45: Drilled and orientated 26" hole from 252 m to 292 m with 4500 LPM, 140 bar, 90 RPM 8-15 KNM, wob 5-10 MT, average ROP 5 m/hr, slid/rotation ratio 35/65
15:45 - 16:30: Inspected top drive. Observed oil leak on oil cooler. Recorded on bottom survey.
16:30 - 19:15: POOH with 26" BHA on 5 1/2" DP from 292 m to 211 m inside 30" conductor. Isolated drill floor equipment and changed out leaking fitting on top drive. Meanwhile completed testing of x-mass tree on f-11.
19:15 - 19:30: RIH with 26" BHA on 5 1/2" DP from 211 m to 280 m. Recorded 5 MT down weight.
19:30 - 20:00: Worked string pass restriction from 280 m to 292 m with 3000 LPM, 65 bar, 30 RPM, 7 KNM.
20:00 - 22:45: Drilled 26" hole from 292 m to 323 m with 4500 LPM, 145 bar, 90 RPM, 4-8 KNM, wob 3 MT, average ROP 11 m/hr.
22:45 - 00:00: Orientated tool face. Drilled and orientated 26" hole from 323 m to 333 m with 4500 LPM, 135 bar, wob 1-7 MT, average ROP 10 m/hr.
| Cleaned out rat hole and reamed same 3 times. Drilled and orientated 26" hole from 226 m to 333 m. Meanwhile inflow tested HMW for 10 min. Inflow tested MMV for 10 min. Installed 2" blind cap on KWV pressure test x-mass tree KWV cap and KWV to 35/200 bar for 5/10 min. Re-istablished permanent instrumentation. Well f-11 handdover to production 23/07-2013 at 20 00 hrs. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-24, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 08:00: Drilled and orientated 26" hole from 333 m to 413m with 3500 LPM, 95 bar, 60 RPM, 7-9 KNM, wob 3-8 MT, ROP drilling 30 m/hr. Pumped 10m3 hi-visc sweep every 15m. Recorded survey on every single.
08:00 - 10:00: Made several attempts to take survey with MWD gyro no go.
10:00 - 10:15: Performed prejob meeting prior to rig up to run wireline gyro.
10:15 - 11:00: Rigged up to run wireline gyro and performed survey.
11:00 - 12:00: Drilled and orientated 26" hole from 413 m to 441m with 3700lpm, 115bar, 0-60 RPM, 2-6 KNM, wob 5-10 MT, ROP drilling 50 m/hr. Pumped 10m3 hi-visc sweep every 15m. Recorded survey on every stand with wireline gyro.
12:00 - 12:45: Attempted to perform MWD gyro survey 2 times no go.
12:45 - 00:00: Drilled and orientated 26" hole from 441m to 615m with 3700-4000lpm, 117-132bar, 0-60 RPM, 6-14 KNM, wob 5-8 MT, ROP drilling 35 m/hr. ROP sliding 25 m/hr pumped 10m3 hi-visc sweep every 15m. Recorded survey on every stand with wireline gyro.
| Drilled and oriented 26" hole from 333m MD to 615m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-25, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:45: Drilled and orientated 26" hole from 615m to 655m with 3700lpm, 116-118bar, 0-60 RPM, 4-14 KNM, wob 4-8 MT. ROP drilling 30 m/hr. ROP sliding 20 m/hr. Pumped 10m3 hi-visc sweep every 15m.
02:45 - 03:30: Ran in hole with wireline gyro and performed survey. Pulled out of hole with wireline gyro.
03:30 - 05:30: Drilled and orientated 26" hole from 655m to 696m with 3700lpm, 118-120 bar, 0-60 RPM, 5-11 KNM, wob 4-7 MT. ROP drilling 50 m/hr. ROP sliding 30 m/hr. Pumped 10m3 hi-visc sweep every 15m.
05:30 - 06:00: Ran in hole with wireline gyro and performed survey. Pulled out of hole with wireline gyro.
06:00 - 08:30: Drilled and orientated 26" hole from 696m to 736m with 3700lpm, 118-120 bar, 60 RPM, 4-15 KNM, wob 6-10 MT. ROP drilling 30 m/hr. ROP sliding 20 m/hr. Pumped 10m3 hi-visc sweep every 15m.
08:30 - 09:15: Ran in hole with wireline gyro and performed survey. Pulled out of hole with wireline gyro.
09:15 - 10:30: Drilled and orientated 26" hole from 736m to 776m with 4000 LPM, 136-137 bar, 0-60 RPM, 8-20 KNM, wob 9-13 MT. ROP drilling 50 m/hr. Pumped 10m3 hi-visc sweep every 15m.
10:30 - 11:30: Ran in hole with wireline gyro and performed survey. Pulled out of hole with wireline gyro.
11:30 - 13:00: Made up top drive and performed MWD surveys at 776m MD, 757m MD and 739m MD. Performed MWD check surveys.
13:00 - 14:30: Drilled and orientated 26" hole from 776m to 817m with 4000 LPM, 132-133 bar, 60 RPM, 10-14 KNM, wob 8-11 MT. ROP drilling 40 m/hr. Pumped 10m3 hi-visc sweep every 15m.
14:30 - 15:15: Rigged down wireline equipment and laid down to deck.
15:15 - 19:45: Drilled and orientated 26" hole from 817m to 880m with 4000 LPM, 133-137 bar, 0-60 RPM, 11-17 KNM, wob 10-14 MT. ROP drilling 40 m/hr. Pumped 10m3 hi-visc sweep every 15m. Performed MWD surveys on every stand.
19:45 - 00:00: Drilled and orientated 26" hole from 880m to 1034m with 4000-4500 LPM, 133-170 bar, 0 RPM, 0 KNM, wob 4-6 MT. ROP sliding 60-90 m/hr. Pumped 10m3 hi-visc bentonite sweep every 15m. Performed MWD surveys on every stand.
| Drilled and oriented 26" hole from 655m MD to 1034m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-26, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:15: Drilled and orientated 26" hole from 1034m to 1065m with 4000 LPM, 133-135 bar, 0 RPM, 0 KNM, wob 4-6 MT. ROP sliding 40 m/hr. Pumped 10m3 hi-visc bentonite sweep every 15m. Performed MWD surveys on every stand.
01:15 - 07:00: Drilled and orientated 26" hole from 1065m to 1140m with 4000-4500 LPM, 133-176 bar, 0-60 RPM, 9-15 KNM, wob 10-16 MT. ROP drilling 20 m/hr ROP sliding 15 m/hr. Pumped 10m3 hi-visc sweep every 15m. Performed MWD surveys on every stand.
07:00 - 12:00: Drilled 26" hole from 1140m to 1220m with 4500 LPM, 175-176 bar, 60 RPM, 7-12 KNM, wob 6-12 MT. ROP drilling 25 m/hr pumped 10m3 hi-visc sweep every 15m. Performed MWD surveys on every stand. Reamed full stand in upper hordaland group.
12:00 - 15:00: Slided and oriented 26" hole from 1220m to 1260m with 3600-4000 LPM, 126-143 bar, 0 RPM, 0 KNM, wob 10-16 MT. ROP drilling 15 m/hr pumped 10m3 hi-visc sweep every 15m. Performed MWD surveys on every stand. Reamed full stand in upper hordaland group.
15:00 - 19:00: Drilled 26" hole from 1260m to 1355m with 4500 LPM, 178-179 bar, 60 RPM, 9-15 KNM, wob 7-12 MT. ROP drilling 40-60 m/hr pumped 10m3 hi-visc sweep every 15m. Performed MWD surveys on every stand. Reamed full stand in upper hordaland group.
19:00 - 22:30: Circulated hole clean by pumping 2 x bottoms up with 4500 LPM and 158 bar.
22:30 - 00:00: Displaced hole with 1. 35 SG KCL water based mud with 4500 LPM and 120-176 bar.
| Drilled and oriented 26" hole from 1034m MD to 1355m MD. Circulated hole clean. Displaced hole to 1. 35 SG KCL water based mud. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-27, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:30: Pulled out of hole with 26" bottom hole assembly from 1355m MD to 1245m MD. At 1245m MD took 10mt overpull. Attempted to get past restriction several times up to 30mt no go. Attempted to pass restriction with 10 RPM no go string torqued up at 30 KNM.
01:30 - 02:00: Lubricated out of hole with 26" bottom hole assembly at 500 LPM seawater and 10 RPM from 1245m MD to 1222m MD. Pumped a total of one string volume. Attempted to pull string without circulation with up to 25mt no go.
02:00 - 02:30: Lubricated out of hole with 26" bottom hole assembly at 1000 LPM and 10 RPM from 1222m MD to 1182m MD.
02:30 - 05:00: Pulled out of hole with 26" bottom hole assembly from 1182m MD to 543m MD. At 543m MD, observed 30mt overpull.
05:00 - 05:45: Lubricated out of hole with 26" bottom hole assembly from 543m MD to 506m MD with 1500 LPM and 30 RPM.
05:45 - 07:00: Pulled out of hole with 26" bottom hole assembly from 506m MD to 347m MD. Observed tight spots at 505m MD, 488m MD, 479m MD and 440m MD with maximum 30mt overpull.
07:00 - 07:15: Cleaned ps21 slips due to excessive clay on pipe body.
07:15 - 07:30: Performed prejob meeting prior to perform wiper trip to TD.
07:30 - 08:45: Pulled out of hole with 26" bottom hole assembly from 347m MD to 221m MD. Observed tight spots at 284m MD and 272m MD with maximum 20mt overpull.
08:45 - 09:00: Established circulation at 4500 LPM and 128 bar to clean bottom hole assembly for clay.
09:00 - 17:15: Ran in hole with 26" bottom hole assembly from 221m MD to 1355m MD. Washed and reamed areas from 381m 390m, 1317m 1328m and 1328m 1355m with 3000 LPM, 72-80 bar and 40 RPM.
17:15 - 18:15: Pumped 20m3 hi-visc, 30m3 seawater, 30m3 hi-visc and 100m3 seawater at 3000 LPM, 72 bar and 40 RPM.
18:15 - 20:00: Displaced hole to 1. 35 SG KCL water based mud at 4600 LPM and 177 bar.
20:00 - 21:00: Pulled out of hole with 26" bottom hole assembly from 1355m MD to 1334m MD. At 1334m MD observed 20mt overpull. Attempted to pass restriction several times with up to 45mt overpull no go. Lubricated past restriction with 300 LPM from 1334m MD to 1287m MD with 30mt overpull.
21:00 - 00:00: Pulled out of hole with 26" bottom hole assembly from 1287m MD to 350m MD. Observed tight spots at 1040m MD, 635m MD and 556m MD with maximum 10mt overpull. Meanwhile while pulling out of hole, ROV jetted drillstring at seabed due to excessive clay on pipe body with good success.
| Pulled and lubricated out of hole with 26" bottom hole assembly from 1355m MD to 221m MD. Performed viper trip to TD at 1355m MD. Pulled out of hole with 26" bottom hole assembly from 1355m MD to 250m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-28, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Pulled out of hole with 26" bottom hole assembly from 250m MD to 221m MD. Meanwhile commenced shutting down producing wells f-11, f-12 and f-14.
00:15 - 01:15: Topped up hole with 1. 35 SG KCL water based mud. Serviced top drive and drill floor equipment. Greased dolly.
01:15 - 05:00: Pulled out of hole and laid down 26" bottom hole assembly from 221m MD to 51m MD.
05:00 - 06:00: Downloaded MWD.
06:00 - 09:00: Pulled out of hole and laid down 26" bottom hole assembly from 51m MD to deck.
09:00 - 11:30: Removed CTS from 30" conductor. Installed cap on top of conductor. Connected control and cement hoses. Installed storm line sheave. Racked back cement head in derrick.
11:30 - 13:45: Performed prejob meeting prior to rig up to run 20" casing.
13:45 - 19:00: Rigged up to run casing. Installed casing tong, removed drilling bails and elevator. Made up lafleur. Installed casing bails and elevator.
19:00 - 00:00: Waited on weather. Cranes down due to wind speed above 40 knots. Meanwhile function tested rig up, slips, elevator, tongs and HTS.
| Pulled out of hole with 26" bottom hole assembly from 250m MD and laid down same to deck. Rigged up to run casing. Waited on weather. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-29, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:15: Waited on weather. Cranes down due to wind speed above 40 knots.
01:15 - 02:00: Picked up shoe joint from deck and set it in slips. Installed dog collar and verified float by hosing water through it.
02:00 - 11:30: Troubleshoot elevator, not able to function open position. Laid out 20" shoe joint and weatherford elevator. Rigged up bx3 elevators and rotator.
11:30 - 11:45: Performed prejob meeting prior to running 20" casing.
11:45 - 12:00: Picked up and backup shoe joint and landing joint from deck and made up with tread lock. Verified floats by hosing water through it.
12:00 - 16:15: Ran in hole with 20" casing from 25m MD to 138m MD.
16:15 - 17:00: Attempted to stab 20" casing into 30" conductor no go. Rigged up chain hoists and guided 20" casing into 30" conductor.
17:00 - 17:45: Performed drops check of top drive.
17:45 - 00:00: Ran 20" casing from 176m MD to 515 m. Average running speed 4. 5 joints HR. Observed 20mt weight at 504-510m MD
| Waited on weather. Ran 20" casing to 515m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-30, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 08:45: Ran 20" casing from 515m MD to 1198m MD. Average running speed 6. 5 joints HR.
08:45 - 09:00: Performed prejob meeting prior to pick up and make up 18 3/4" wellhead.
09:00 - 09:45: Laid out weatherford circulating tool. Changed out to 5 1/2" handling equipment.
09:45 - 10:30: Picked up and made up 18 3/4" wellhead to 20" casing. Prepared wellhead for running in hole.
10:30 - 11:15: Changed out ps30 slips and installed master bushings.
11:15 - 11:30: Performed prejob meeting prior to rigging down weatherford casing tong.
11:30 - 14:00: Rigged down weatherford casing equipment and laid out to deck.
14:00 - 16:00: Ran in hole with 20" casing on 5 1/2" heavy weight drill pipe from 1213m MD to 1312m MD. At 1312m MD, observed 15mt weight. Established circulation in stages to 1500 LPM and 39 bar. Washed down with 20" casing on 5 1/2" heavy weight drill pipe from 1312m MD to 1335m MD.
16:00 - 16:30: Made up cement stand to 5 1/2" heavy weight drill pipe.
16:30 - 16:45: Washed in hole with 20" casing at 1500 LPM and 40 bar from 1335m MD to 1348m MD. Landed and locked wellhead. Confirmed wellhead latched by applying 20mt overpull.
16:45 - 20:00: Circulated 2 x bottoms up with 2300 LPM and 18-27 bar. Meanwhile performed prejob meeting prior to performing cement job.
20:00 - 00:00: Closed IBOP and applied 30 bar above. Opened lo-torque and dropped ball. Mixed and pumped 304m3 1. 56sg lead slurry and 30m3 1. 92sg tail slurry.
| Ran 20" casing from 515m MD to 1348m MD and landed wellhead. Cemented casing. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-07-31, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:30: Continued mixing and pumping 304m3 1. 56sg lead slurry and 30m3 1. 92sg tail slurry. Meanwhile made ready equipment for running high pressure drilling riser. Tranfered claxton tool to drill floor and attached sub. Performed general maintanence and house keeping.
02:30 - 04:00: Dropped top dart and pumped 1200 liters behind with cement unit. Observed top wiper plug sheared out with 145 bar. Closed lo-torque and opened IBOP. Displaced cement with 9669 strokes volume 1/2" shoetrack. Used 97 pump efficiency). No bump observed. Final circulating pressure observed was 60 bar at 1400 LPM.
04:00 - 04:30: Lined up down to cement unit. Bled back 540 liters to cement unit. Observed for backflow for 15 minutes no backflow observed.
04:30 - 05:30: Isolated drilling equipment for manriding. Removed control lines and cement hose from cement head.
05:30 - 06:15: Released overpull on running tool to neutral weight. Released 18 3/4" wellhead running tool by to turning 5 times clockwise. Pulled same above wellhead.
06:15 - 07:00: Racked back cement stand in derrick. Dropped 2 x wash balls into string. Made up new stand.
07:00 - 07:45: Jetted area around wellhead with 3000 LPM and 8 bar.
07:45 - 08:45: Pulled out of hole with 18 3/4" wellhead running tool on 5 1/2" heavy welght drill pipe from 130m MD. Laid out same to cantilever.
08:45 - 09:30: Laid out claxton running tool to cantilever.
09:30 - 10:30: Broke out cement stand and laid out same to cantilever. Made up single 5 1/2" heavy weight drillpipe and racked back stand.
10:30 - 10:45: Performed prejob meeting prior to start rig up to run high pressure drilling riser.
10:45 - 12:00: Picked up and made up riser spider. Installed in rotary and function tested same.
12:00 - 19:15: Rigged up to run high pressure drilling riser. Ran wellhead guide funnel and installed same in wellhead. Installed sheave and holdback lines. Installed tension ring on f-1 and teflon centralizers. Serviced top drive and installed VX gasket on wellhead.
19:15 - 19:30: Performed prejob meeting prior to start picking up and run heavy weight drilling riser.
19:30 - 20:00: Picked up TBC stress joint and ran through rotary, landed same in spider.
20:00 - 21:30: Picked up lower riser pup joint. Prepared seal faces on joint connection and made up same.
21:30 - 22:30: Function tested TBC in moonpool OK. Verified valve positions.
22:30 - 00:00: Picked up and made up intermediate riser joint
| Cemented 20" casing. Released casing running tool, pulled out of hole with same and laid out. Rigged up to run high pressure drilling riser. Ran high pressure drilling riser to 45m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-01, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:45: Ran in hole with high pressure drilling riser from 35m to 50m.
03:45 - 06:00: Picked up and made up intermediate riser joint Ran in hole with high pressure drilling riser from 50m to 64m.
06:00 - 09:45: Picked up and made up double intermediate riser joint and Ran in hole with high pressure drilling riser from 64m MD to 92m MD.
09:45 - 10:15: Waited on crane due to handling of boat.
10:15 - 12:45: Picked up and made up splash zone joint and upper pup joint. Ran in hole with high pressure drilling riser from 92m MD to 109m MD.
12:45 - 13:00: Changed to side door elevators for lifting tension joint.
13:00 - 15:30: Picked up and made up riser tension joint. Ran in hole with high pressure drilling riser from 109m MD to 114m.
15:30 - 16:15: Observed crack on flange protector. Cargo strapped cracked protector.
16:15 - 17:00: Continued running in hole with high pressure drilling riser from 114m MD to 121m MD.
17:00 - 17:15: Removed side door elevators. Installed auto elevators and rotating arm.
17:15 - 20:30: Picked up and made up BOP joint with claxton nt2 running tool. Changed flange faces, cleaned and inserted gasket.
20:30 - 21:45: Picked up riser. Removed elevators and c-plate. Removed riser spider.
21:45 - 23:00: Installed outer ring and master bushings.
23:00 - 23:15: Performed prejob meeting prior to land high pressure drilling riser.
23:15 - 23:45: Picked up x-over and 1 stand of drill pipe. Made up same to claxton running tool. Meanwhile ROV removed debris cap from well head.
23:45 - 00:00: Ran in with riser from 121m MD to above riser guide funnel at 136m.
| Ran in hole with high pressure drilling riser to 136m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-02, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:30: Ran in hole with riser from 136m to 137m. Entered riser guide funnel. Continued running in from 137m to top of wellhead. Rigged up tugger from moonpool to remove riser guide funnel.
01:30 - 02:00: Connected tugger to guide funnel and released hatch lock to disconnect riser guide funnel.
02:00 - 02:45: Lowered hotstab connector to seabed. Removed dummy stab and installed hotstab. Switched connector valves to run-position.
02:45 - 04:15: Landed connector on wellhead and set down 20mt weight. Pressured up to 3000 psi until indicator rods in closed position.
04:15 - 05:00: Performed pull test by applying 15mt overpull on riser OK. Filled riser while venting through open outlet on claxton tool.
05:00 - 06:00: Prepared to install centralizers, tension ring and cylinders. Meanwhile lined up to pressure test well with cement unit. Performed line test to 100 bar for 10 minutes OK. Built scaffolding around riser. Installed cap on claxton waco outlet.
06:00 - 09:15: Installed centralizers and boat collision tool.
09:15 - 10:00: Pressure tested riser and connector to 100 bar for 10 minutes OK. Pumped a total of 1200 liters, bled 1200 liters back.
10:00 - 18:15: Installed tension ring and cylinders.
18:15 - 18:30: Tranferred riser weight to cylinders. Tensioned up riser to 150mt.
18:30 - 19:00: Cleaned and tidied well head area and prepared to disengage claxton tool.
19:00 - 19:15: Performed prejob meeting prior to disengage claxton tool.
19:15 - 19:45: Spotted claxton control reel on drill floor. Installed control wire sheave. Meanwhile changed fittings on claxton tool.
19:45 - 20:00: Rigged up air hoses to claxton control line reel. Ran hoses through rotary and installed same on claxton tool.
20:00 - 20:45: Set down 5mt on claxton tool. Pressure up and disengaged claxton running tool. Picked up same and installed split bushings. Set claxton tool in slips. Broke out stand and racked back in derrick.
20:45 - 21:30: Picked up and made up pup joint to claxton tool. Removed outer bushings and outer ring. Picked up claxton tool to clear of rotary.
21:30 - 21:45: Installed outer ring and bushings.
21:45 - 22:00: Performed prejob meeting prior to lay out claxton tool.
22:00 - 22:45: Broke out pup joint and laid out claxton tool to cantilever.
22:45 - 00:00: Prepared to nipple up BOP. Rigged up to pressure test ibops. Modified scaffolding in moonpool.
| Ran in and landed riser on wellhead. Pressure tested riser and connector to 100 bar for 10 minutes. Installed centralizers, tension ring and cylinders. Disengaged claxton tool and laid out same to deck. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-03, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Performed prejob meeting prior to nippling up BOP.
00:15 - 00:45: Moved BOP to well centre.
00:45 - 05:00: Nippled up BOP. Meanwhile pressure tested hoses and ibops.
05:00 - 05:15: Performed prejob meeting prior to rigging up slick joint and diverter.
05:15 - 09:15: Rigged up slick joint. Attempted to lower diverter on to slick joint no go. Found skid position not aligned.
09:15 - 10:15: Checked and adjusted pressure on tension cylinders and attempted to move slick joint under diverter no go. Slacked off BOP on BOP craddle to fit BOP and slick joint below diverter no go.
10:15 - 10:45: Prepared cantilever and deck equipment for skidding. Removed staires and bridge.
10:45 - 11:00: Performed prejob meeting prior to perform skidding operation.
11:00 - 11:30: Skidded cantilever 20cm starboard. Verified alignment.
11:30 - 12:15: Lowered diverter on to slick joint. Not able to land correctly.
12:15 - 14:15: Pulled out diverter and checked same. Observed damage to alignment key on diverter. Removed alignment key and filed same to proper condition. Installed alignment key on diverter.
14:15 - 15:00: Landed off diverter. Installed hoses and activated diverter packer and overshot packer.
15:00 - 15:30: Filled up riser and BOP with seawater and verified no leaks.
15:30 - 16:15: Rigged down diverter running slips and shackles. Installed auto slips and rotating arm.
16:15 - 17:15: Picked up and made up BOP test tool. Ran in hole to 139m and landed off in wellhead.
17:15 - 17:30: Lined up to pressure test from cement unit. Closed upper pipe ram.
17:30 - 18:00: Pressure tested BOP and riser to 345 bar for 10 minutes OK. Pumped 389 liters, bled back 386 liters.
18:00 - 19:00: Pulled out of hole with BOP test tool and laid down same to cantilever.
19:00 - 19:15: Performed prejob meeting prior to pick up and make up bore protector running tool.
19:15 - 20:15: Picked up and made up bore protector running tool. Ran in hole with bore protector running tool on 5 1/2" drill pipe and set bore protector in wellhead by applying 5mt weight.
20:15 - 21:15: Released bore protector running tool by rotating one turn clockwise. Pulled out of hole with bore protector running tool on 5 1/2" drill pipe. Laid bore protector running tool out to deck.
21:15 - 21:30: Cleaned and tidied rig floor.
21:30 - 21:45: Performed prejob meeting prior to pick up and make up 17 1/2" bottom hole assembly.
21:45 - 00:00: Picked up and made up 17 1/2" bottom hole assembly to 50m.
| Nippled up BOP. Installed slick joint and diverter. Pressure tested BOP and riser to 345 bar for 10 minutes. Set bore protector in wellhead. Picked up and made up 17 1/2" bottom hole assembly to 50m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-04, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:30: Picked up and made up 17 1/2" bottom hole assembly from 50m to 109m.
03:30 - 03:45: Changed to 5 1/2" handling equipment.
03:45 - 04:15: Ran in hole with 17 1/2" bottom hole assembly on 5 1/2" heavy weight drill pipe from 109m to 230m.
04:15 - 06:30: Ran in hole with 17 1/2" bottom hole assembly on 5 1/2" drill pipe from 230m to 1000m.
06:30 - 07:30: Performed choke drill with both crews.
07:30 - 08:15: Ran in hole with 17 1/2" bottom hole assembly on 5 1/2" drill pipe from 1000m MD to 1281m MD.
08:15 - 09:00: Engaged top drive. Washed in hole from 1281m MD to 1321m MD. Tagged hard cement at 1321m MD with 10mt.
09:00 - 13:00: Drilled cement in shoetrack from 1321m MD to 1348m MD with 3800 LPM, 120 bar, 60-80 RPM and 8-16 KNM. Drilled and reamed through shoe and rat hole from 1348m MD to 1355m MD. Displaced hole to 1. 40 SG oil based mud while drilling shoe track.
13:00 - 13:30: Drilled 3 meters of new formation from 1355m MD to 1358m MD with 4200 LPM, 229 bar, 60 RPM and 7-11 KNM.
13:30 - 14:00: Circulated and conditioned mud prior to perform fit with 4200 LPM and 227 bar.
14:00 - 15:15: Closed upper pipe rams. Performed fit to 1. 55 SG at 1358m MD with 1. 40 SG oil based mud by applying 22 bar.
15:15 - 20:30: Drilled and oriented 17 1/2" hole from 1354m MD to 1440m MD with 3800-4100 LPM, 150-228 bar, 120 RPM, 9-15 KNM, 1. 41 SG ECD. Drilling ROP 35 m/hr.
20:30 - 21:00: Observed 20mt overpull when picking up pipe for connection. Reamed area with 4100 LPM, 225 bar, 60 RPM and 9-11 KNM.
21:00 - 00:00: Drilled and oriented 17 1/2" hole from 1440m MD to 1510m MD with 4100-4400 LPM, 228-257 bar, 120 RPM, 8-15 KNM, 1. 41 SG ECD. Drilling ROP 35 m/hr.
| Ran in hole with 17 1/2" bottom hole assembly from 50m to 1322m. Drilled out cement and shoe track in 20" casing from 1322m to 1349m. Displaced hole to 1. 40 SG oil based mud while drilling out shoe track. Cleaned out rat hole and drilled 3 meters new formation to 1358m. Performed fit to 1. 55 SG. Drilled and oriented 17 1/2" hole from 1358m to 1510m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-05, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: Drilled and oriented 17 1/2" hole from 1517m MD to 1527m MD with 4400 LPM, 259 bar, 120 RPM, 10-13 KNM, 1. 41 SG ECD. Drilling ROP 35 m/hr. At 1517m MD, observed plugged line from swaco cuttings unit to boat.
00:45 - 01:15: Performed slow circulation rates. Meanwhile moved boat from port side to starboard side. Hooked up line from swaco cuttings unit to boat.
01:15 - 16:15: Attempted to start-up transfer of cuttings on starboard side no go. Starboard side hose plugged. Laid out port side hose to deck. Worked on cleaning out plug on port side hose. Meanwhile reciprocated pipe with 3000-4400 LPM, 131-257 bar and 100-120 RPM. Racked back one stand every hour. Reamed area from 1515m due to 10mt overpull. Reset v-icis system. Laid down 3 1/2" drill pipe to deck. Rigged up for racking back 13 3/8" casing in derrick. Performed general maintanence and housekeeping.
16:15 - 20:30: Drilled and oriented 17 1/2" hole from 1527m MD to 1623m MD with 4500 LPM, 270 bar, 120 RPM, 12-18 KNM, 1. 41 SG ECD. Drilling ROP 35-40 m/hr at 1623m MD, observed plugged line from CCB to iso-tanks.
20:30 - 21:00: Performed slow circulation rates. Meanwhile routed cuttings to skips on deck. Racked 13 3/8" casing in derrick.
21:00 - 00:00: Cleaned out plugged hose from cleancut blower to iso-tanks. Meanwhile reciprocated pipe with 3600 LPM, 192 bar and 100 RPM. Performed general maintanence. Racked 13 3/8" casing in derrick.
| Drilled and oriented 17 1/2" hole from 1517m MD to 1527m MD. Cleared overboard hose for cuttings transport. Drilled and oriented 17 1/2" hole from 1527m MD to 1623m MD. Cleared hose from CCB funnel to iso-tanks. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-06, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:30: Continued cleaning out hose from CCB funnel to iso-tanks. Cleaned out plugged pressure sensors on CCB. Meanwhile racked 13 3/8" casing in derrick.
01:30 - 20:15: Drilled and oriented 17 1/2" hole from 1623m MD to 2047m MD with 4400 LPM, 259-282 bar, 120-140 RPM, 10-23 KNM, 8-16 MT, 1. 41-1. 42 SG ECD. Drilling ROP 25-30 m/hr.
20:15 - 20:45: Performed slow circulation rates.
20:45 - 21:30: Drilled and oriented 17 1/2" hole from 2047m MD to 2054m MD with 4400 LPM, 282 bar, 140 RPM, 11-18 KNM, 10-16 MT and 1. 41 SG ECD. Drilling ROP 25 m/hr at 2054m MD, observed shut down of mud pumps.
21:30 - 22:45: Drilled and oriented 17 1/2" hole from 2054m MD to 2062m MD with 2000-4000 LPM, 80-243 bar, 140 RPM, 9-12 KNM, 2-4 MT and 1. 40-1. 41 SG ECD. Drilled with reduced ROP due to pump problems. Meanwhile troubleshot mud pumps. Electronic pop-off tripping at low pressures.
22:45 - 00:00: Drilled and oriented 17 1/2" hole from 2062m MD to 2087m MD with 4400 LPM, 266-267 bar, 140 RPM, 15-23 KNM, 14-18 MT and 1. 41 SG ECD. Drilling ROP 25 m/hr
| Cleared hose on cleancut blower unit. Drilled and oriented 17 1/2" hole from 1623m MD to 2087m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-07, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:00: Drilled and oriented 17 1/2" hole from 2087m MD to 2127m MD with 4400 LPM, 266 bar, 140 RPM, 12-25 KNM, 10-16 MT and 1. 41 SG ECD. Drilling ROP 30 m/hr observed areas with high torque due to calcareous stringers.
02:00 - 02:45: Observed overtorqued connection. Attempted to break connection and broke off connection on top of saver sub instead. Greased lower IBOP connection, increased make up torque and made up saver sub to lower IBOP. Broke connection and made up new stand.
02:45 - 15:15: Drilled and oriented 17 1/2" hole from 2127m MD to 2325m MD with 4400 LPM, 266 bar, 120-160 RPM, 12-30 KNM, 16-20 MT and 1. 41 SG ECD. Reamed 1 single at 2207 m MD prior to connection. Reamed 1/2 single at 2249 m MD prior to connection. Reamed 1/2 single at 2290 m MD prior to connection. Drilling ROP 16 m/hr observed areas with high torque due to calcareous stringers.
15:15 - 15:30: Recorded SCR'S prior to connection.
15:30 - 17:15: Drilled and oriented 17 1/2" hole from 2325 m MD to 2369 m MD with 4400 LPM, 266 bar, 120-160 RPM, 12-30 KNM, wob 11-19 ton, 1,40 1,41 SG ECD. Average drilling ROP 25 m/hr.
17:15 - 17:45: Not able to brake out over torqued DP connection. Attempted to break connection, saver sub lower IBOP connection broke unintended. Made up saver sub lower IBOP connection, increased make up torque to 80000 ft/lbs. Broke out DP connection and made up new stand.
17:45 - 00:00: Drilled and oriented 17 1/2" hole from 2369 m MD to 2438 m MD with 4430 liter/min, 282 292 bar, 140-160 RPM, 15-24 KNM, wob 15-20 ton, 1,39 1,41 SG ECD. Average drilling ROP 11 m/hr.
| Drilled and oriented 17 1/2" hole from 2127 m MD to 2439 m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-08, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 21:45: Drilled and oriented 17 1/2" hole from 2438 m MD to 2602 m MD with 4430 liter/min, 280 290 bar, 90-140 RPM, 16-27 KNM, wob 15-20 ton, ROP 3-18 m/h, 1,39 1,41 SG ECD. Average drilling ROP 7,5 m/hr meanwhile picked up and racked back 13 3/8" casing in derrick.
21:45 - 00:00: Reciprocated string while circulating hole clean with 4365 l/min, 275-280 bar, 120 RPM, 5-9 KNM, ECD 1,391 SG. Racked back 1 stand after 1 x bottoms up.
| Drilled and orientated 17 1/2" hole from 2438 m MD to TD at 2602 m MD. Circulated hole clean. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-09, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 05:00: Reciprocated string while circulating hole clean with 4365 l/min, 275-280 bar, 120 RPM, 5-9 KNM. Racked back 1 stand after each bottoms up. Observed fair amount of cuttings coming across shakers after 3 x bottoms up. Observed minor amount of cuttings coming across shakers after 4 x bottoms up. Circulated total 4 x bottoms up.
05:00 - 05:30: Performed downlink. Recorded up down weights 163 137 ton.
05:30 - 06:00: Flow checked well for 10 minutes, OK.
06:00 - 06:30: POOH wet with 17 1/2" BHA on 5 1/2" DP from 2490 m to 2329 m.
06:30 - 07:00: Pumped 5 m3 1,74 SG slug and chased same with 1,4 SG OBM. Not able to commence tripping due to faulty finger in finger board.
07:00 - 07:15: Repaired finger in DP finger board.
07:15 - 09:00: POOH with 17 1/2" BHA on 5 1/2" DP from 2329 m to 1326 m. Restricted tripping speed to 1 min/stand.
09:00 - 09:30: Flow checked well for 10 minutes inside 20" shoe, OK. Meanwhile performed pre-job meeting. Serviced TDS and checked dolly rollers.
09:30 - 10:15: POOH with 17 1/2" BHA on 5 1/2" DP from 1326 m to 1042 m. Restricted tripping speed to 1 min/stand. Stopped tripping due to encoderfailure on aft PRS.
10:15 - 10:45: Troubleshoot aft PRS and reset same, not able to eliminate encoder failure. Continued tripping using FWD PRS.
10:45 - 12:00: POOH with 17 1/2" BHA on 5 1/2" DP from 1042 m to 136 m.
12:00 - 12:15: Flow checked well for 10 minutes prior to pull through BOP'S, OK. Meanwhile performed pre-job meeting prior to lay down BHA.
12:15 - 15:00: Removed PS-21 and installed master bushings. POOH with 17 1/2" BHA from 136 m to 24 m and laid down same to cantilever.
15:00 - 16:00: Plugged into MWD tool and down loaded data.
16:00 - 17:30: POOH with 17 1/2" BHA from 24 m to surface and laid down same to cantilever. Cleaned and cleared drill floor.
17:30 - 22:15: Picked up and made up bull nose and seat protector RRT assembly. RIH with assembly on 5 1/2" HWDP and jet washed BOP area. Continued to RIH with assembly to NSP area and jet washed same. Engaged and retrieved seat protector. Pulled free with 12 ton overpull. New datum 138,86 meter. Jet washed NSP area. Dropped 2 7/8" drift. POOH with assembly and laid down same. Cleaned and cleared drill floor.
22:15 - 00:00: Rigged up bails and BX elevators for 13 3/8" casing.
| Circulated hole clean. POOH with 17 1/2" BHA. Retrieved wear bushing. Rigged up for 13 3/8" casing. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-10, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:30: Installed casing fill up tool on TDS. Removed master bushings and installed FMS. Installed 13 3/8" casing tong.
02:30 - 02:45: Performed pre-job meeting prior to run 13 3/8" casing.
02:45 - 03:30: Picked up shoe track from derrick, made up to double, baker locked connection and RIH to 63 m. Experienced problems with running centralizers through slips, removed guides on slips and filled string to enable centralizers to run through.
03:30 - 05:30: RIH with 13 3/8" casing in stands from 63 to 210 m. Filled casing every 2. Th stand.
05:30 - 06:00: Experienced problems with casing tong, not able to release grip.
06:00 - 06:45: RIH with 13 3/8" casing in stands from 210 to 308 m. Filled casing every 2. Th stand.
06:45 - 07:15: Installed guides in slips. Held pre-job meeting with oncoming crew prior to run casing.
07:15 - 09:00: RIH with 13 3/8" casing in stands from 308 m to 504 m. Filled casing every 3. Th stand. Average running speed 112 m/hr 9 joint/hr.
09:00 - 09:30: Attempted to adjust casing fill up tool to enable filling while RIH, not applicable.
09:30 - 15:00: RIH with 13 3/8" casing in stands from 504 m to 1348 m. Filled casing every 3. Th stand. Average running speed 153 m/hr 13 joint/hr.
15:00 - 16:00: Engaged casing fill up tool and broke circulation. Circulated for 10 minutes with 400-1200 liter/min, 10-16 bar.
16:00 - 22:30: RIH with 13 3/8" casing in stands from 1348 m to 2155m. Filled casing every 3. Th stand. Average running speed 125 m/hr 10 joint/hr.
22:30 - 00:00: RIH with 13 3/8" casing in stands from 2155 m to 2228 m. Worked tight spots between 2155 m 2165 m, 2195 m 2200 m. Filled casing every 3. Th stand.
| Rigged up to run 13 3/8" casing. RIH with 13 3/8" casing in stands from surface to 2228 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-11, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:00: RIH with 13 3/8" casing in stands from 2228 m to 2448 m. Filled casing every 3. Th stand. Average running speed 110 m/hr 9 joint/hr.
02:00 - 03:00: Rigged down casing fill up tool, bails and casing elevator. Rigged up 5 1/2" DP handling equipment.
03:00 - 03:30: Picked up and made up casing hanger.
03:30 - 03:45: Removed casing slips and installed master bushings.
03:45 - 04:00: Removed protection from hanger and checked seals. Hanger not able to pass through rotary due to misalignment.
04:00 - 04:15: Rigged up snatch block to align hanger and allow it to pass through rotary.
04:15 - 04:30: Ran hanger through rotary and sat in manual slips.
04:30 - 05:45: Rigged down 13 3/8" casing tong.
05:45 - 07:15: RIH with 13 3/8" casing on 5 1/2" HWDP landing string from 2460 m to 2570 m. Experienced tight spot between 2562 m 2570 m. Worked tight spot, not able to pass 2570 meter.
07:15 - 07:30: Made up TDS to string and established circulation with 500 liter/min, 18 bar.
07:30 - 15:45: Washed and worked down 13 3/8" casing on 5 1/2" HWDP landing string from 2560 m to 2596 m with 500-1500 liter/min, 18-45 bar, 20-40 ton down weight. The hole packed off several times. Lost 500-3000 liter/hour to formation.
15:45 - 16:30: Picked up and made up cement stand to landing string. Landed casing hanger in wellhead, sat down all weight. Rotated 1/4 right hand turn.
16:30 - 19:00: Established circulation and increased rate in steps to 2200 liter/min, 29 bar. Observed pack off at 2200 liter/min, reduced rate to at 1800 liter/min, 21 bar meanwhile performed pre-job meeting prior to cement job. Rig air supply from production shut down.
19:00 - 22:15: Production troubleshot on rig air system and consumption. Tested and confirmed air supply OK. Meanwhile pressure tested surface lines and cement hose to 30 345 bar 5 10 minutes. Circulated and conditioned mud with 1800 liter/min, 21 bar.
22:15 - 00:00: Pumped 25 m3 of 1,75 SG spacer using rig pumps with 1560 liter/min, 15 bar. Lined up to pump from cement unit. Applied 20 bar pressure behind IBOP. Released dart for bottom wiper plug. Mixed and pumped 27,7 m3 of 1,90 SG cement slurry at 600 liter/min. Observed dart landing and shearing. Released dart for top wiper plug.
| RIH with 13 3/8" casing in stands from 2228 m to 2570 m. Washed and worked 13 3/8" casing down on landing string from 2570 m to 2596 m. Circulated and conditioned mud. Mixed and pumped 27,7 m3 1,90 SG cement. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-12, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:45: Displaced cement to rig floor with 3000 liter of drill water. Observed top wiper plug shear. Zeroed volume counters. Continued to displace cement using rig pumps with OBM at 1800 liter/min, 0-60 bar. Observed bottom wiper plug landing with 136 bar. Observed loss of full returns after 180 m3 pumped. Reduced rate to 1400 liter/min, still not full returns. Reduced rate to 500 liter/min after 181,5 m3 pumped. Displaced with theoretical volume 1/2 shoe track volume 186,4 m3 1,25 m3 187,6 m3. Top plug did not bump. Recorded FCP 60 bar. Lost 10,2 m3 during cement displacement.
01:45 - 02:30: Bled off pressure and checked for back flow on cement unit. No back flow observed.
02:30 - 06:00: Set and pressure tested seal assembly to 345 bar 15 min.
06:00 - 09:30: Tested BOP pipe rams and annular to 20 345 bar 5 10 minutes. Meanwhile performed pre-job meeting prior to break out and lay down cement head.
09:30 - 12:00: Released casing hanger RT. Broke out and laid down cement head. Installed 2 ea. Sponge balls in string. Circulated clean with 2230 liter/min, 19 bar. POOH with casing hanger RT and laid down same.
12:00 - 12:15: Cleaned and cleared drill floor. Held pre-job meeting prior to wear bushing run.
12:15 - 13:15: Installed wear bushing in WH, datum at 138,92 meter.
13:15 - 14:00: Continued to test BOP pipe rams to 20 345 bar 5 10 minutes.
14:00 - 15:30: Broke out and laid down jet sub wear bushing RT assembly. Cleaned and cleared drill floor.
15:30 - 18:00: Pressure tested IBOP'S, kelly hose and manifolds to 20 345 bar 5 10 minutes.
18:00 - 00:00: Waited on cement. Meanwhile performed planned maintenence on TDS and travelling block. Restarted v-icis. Replaced wash pipe. Measured TDS dolly alignment using laser equipment. Replaced solenoid valve on aft PRS
| Displaced cement. Set and tested seal assembly. Released and POOH with hanger RT. RIH and set wear bushing. Waited on cement meanwhile tested surface equipment. Performed planned maintenance. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-13, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:45: Waited on cement. Meanwhile pressure tested manifolds to 20 345 bar 5 10 minutes. Performed planned maintenence on TDS and travelling block. Installed BHA wash tool.
01:45 - 03:00: Pressure tested 13 3/8" casing to 20 320 bar 5 10 minutes against blind shear ram.
03:00 - 04:30: Made up and RIH with 12 1/4" BHA from surface to 167 meter.
04:30 - 08:45: RIH with 12 1/4" BHA on 5 1/2" DP from 167 m to 2508 m. Average tripping speed 550 m/hr 13 stds/hr. Filled pipe every 1000 meter.
08:45 - 09:15: Performed choke drill.
09:15 - 09:30: Established circulation and washed down with 12 1/4" BHA on 5 1/2" DP from 2508 m to 2548 m at 2000 liter/min, 82 bar. Tagged TOC at 2548 meter.
09:30 - 14:15: Drilled shoetrack and cement from 2548 m to 2602 m with 2000 2500 liter/min, 85-122 bar, 30-60 RPM, 8-20 KNM, wob 3-11 ton. Reduced mud weight from 1,40 SG to 1,28 SG OBM while drilling. Cleaned out rat hole in 1-2 meter steps, reamed rat hole twice. Meanwhile prepared for pick up and racking of 10 3/4" casing.
14:15 - 15:15: Drilled 3 meter new formation to 2605 meter. Pulled back into shoe without circulation or rotation to confirm no restrictions observed.
15:15 - 16:00: Circulated and conditioned mud until 1,28 SG mud in and out with 3000 liter/min, 145 bar. Meanwhile lined up and tested lines from cement unit to 120 bar 5 min
16:00 - 17:15: Performed fit to 66 bar using 1,28 SG mud, 1,55 SG EMW. Pumped 877 liter from 5 bar to 66 bar at cement unit with 55 liter/min. Bled back 811liter.
17:15 - 17:45: Flow checked well for 10 min, OK.
17:45 - 18:30: Dropped gyro. Waited for gyro to initialize.
18:30 - 18:45: Pumped 4 m3 1,56 SG slug with 1000 liter/min, 22 bar.
18:45 - 21:00: POOH with 12 1/4" BHA on 5 1/2" DP from 2590 m to 436 m. Average tripping speed 957 m/hr.
21:00 - 21:30: Made up string and took orientation shots.
21:30 - 21:45: POOH with 12 1/4" BHA on 5 1/2" DP from 436 m to 167 m. Average tripping speed 1076 m/hr.
21:45 - 22:00: Flow checked well for 10 min, OK. Meanwhile removed PS-21 slips and installed master bushings.
22:00 - 22:15: POOH with 12 1/4" BHA on 5 1/2" HWDP from 167 m to 97 m. Not able to retrieve gyro due to wrong retrival tool setup.
22:15 - 22:30: Reconfigured gyro retrieval tool.
22:30 - 22:45: Retrieved gyro.
22:45 - 00:00: POOH with 12 1/4" BHA from 97 m to surface and laid down same. Cleaned and cleared drill floor.
| Pressure tested casing to 320 bar. Made up and RIH with 12 1/4" BHA. Drilled out cement and shoe track. Performed fit to 1,55 SG EMW. POOH with 12 1/4" BHA. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-14, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Performed pre-job meeting prior to make up 8 1/2" BHA. Changed to 5" handling equipment.
00:30 - 06:00: Picked up and made up 8 1/2" drilling BHA and RIH from surface to 151 meter.
06:00 - 07:15: RIH with 8 1/2" BHA on 5 1/2" HWDP DP from 151 m to 1011 m. Average tripping speed 688 m/hr.
07:15 - 08:00: Tested MWD tools with 2000 liter/min, 118 bar.
08:00 - 10:00: RIH with 8 1/2" BHA on 5 1/2" HWDP DP from 1011m to 2585 m. Average tripping speed 787 m/hr. Filled pipe every 1000 meter.
10:00 - 11:00: Washed down from 2585 m to 2605 m with 1800 liter/min, 111 bar, 60 RPM, 9-13 KNM.
11:00 - 18:45: Drilled and oriented 8 1/2" hole from 2605 m MD to 2779 m MD with 1990 2389 liter/min, 142 207 bar, 60-130 RPM, 11-19 KNM, wob 5-10 ton, ROP 37-42 m/h, 1,31 1,34 SG ECD. Average drilling ROP 23 m/hr meanwhile picked up and racked back 10 3/4" casing in derrick.
18:45 - 00:00: Drilled and oriented 8 1/2" hole from 2779 m MD to 2905 m MD with 2400 2470 liter/min, 207 211 bar, 130-160 RPM, 17-21 KNM, wob 5-12 ton, ROP 39-18 m/h, 1,34 1,35 SG ECD. Average drilling ROP 24 m/hr meanwhile picked up and racked back 10 3/4" casing in derrick.
| POOH and laid down 12 1/4" BHA. Made up and RIH with 8 1/2" drilling BHA. Drilled 8 1/2" hole to 2905 meter. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-15, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 11:15: Drilled and oriented 8 1/2" hole from 2905 m MD to 3145m MD with 2450 2570 liter/min, 202 216 bar, 160 RPM, 18-21 KNM, wob 4-12 ton, ROP 18-25 m/h, 1,35 1,37 SG ECD. Average drilling ROP 21 m/hr meanwhile picked up and racked back 9 5/8" casing in derrick.
11:15 - 11:30: Recorded SCR'S
11:30 - 16:30: Drilled and oriented 8 1/2" hole from 3145 m MD to 3253 m MD with 2570 2707 liter/min, 205 214 bar, 160 RPM, 17-23 KNM, wob 4-8 ton, ROP 18-25 m/h, 1,37 1,39 SG ECD. Average drilling ROP 22 m/hr increased MW from 1,28 SG to 1,32 SG while drilling. Meanwhile picked up and racked back 9 5/8" casing in derrick.
16:30 - 16:45: Pulled off bottom and trouble shoot sonic tool failure. Sonic tool not fuctional.
16:45 - 00:00: Drilled and oriented 8 1/2" hole from 3253 m MD to 3364 MD with 2446 2570 liter/min, 205 213 bar, 160 RPM, 18-23 KNM, wob 4-8 ton, ROP 11-22 m/h, 1,38 1,39 SG ECD. Average drilling ROP 15 m/hr meanwhile picked up and racked back 9 5/8" casing in derrick. Total 44 stands racked back.
| Drilled and orientated 8 1/2" hole from 3145 m MD to 3364 m MD. Picked up and racked back casing offline. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-16, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 05:15: Drilled and oriented 8 1/2" hole from 3364 m MD to 3450 MD with 2389 2565 liter/min, 208 216 bar, 160 RPM, 17-23 KNM, wob 4-10 ton, ROP 9-23 m/h, 1,39 1,40 SG ECD. Average drilling ROP 16 m/hr meanwhile picked up and racked back 9 5/8" casing in derrick.
05:15 - 13:15: Drilled and oriented 8 1/2" hole from 3450 m MD to 3591 m MD with 2389-2435 liter/min, 213 220 bar, 160 RPM, 18-23 KNM, wob 3-5 ton, ROP 5-20 m/h, 1,39 1,40 SG ECD. Average drilling ROP 18 m/hr meanwhile picked up and racked back 9 5/8" casing in derrick.
13:15 - 13:30: Recorded SCR'S.
13:30 - 16:30: Drilled and oriented 8 1/2" hole from 3591 m MD to 3632 m MD with 2389 liter/min, 218 220 bar, 160 RPM, 17-22 KNM, wob 3-5 ton, ROP 5-20 m/h, 1,39 SG ECD. Average drilling ROP 14 m/hr meanwhile picked up and racked back 9 5/8" casing in derrick.
16:30 - 20:45: Circulated hole clean with 2400 liter/min, 218 bar, 142 RPM, 17-19 KNM. Circulated total 2 1/2 x bottoms up.
20:45 - 21:00: Flow checked well for 10 minutes, OK.
21:00 - 21:45: Pumped OOH from 3632 m to 3496 m with 2450 liter/min, 200 bar.
21:45 - 00:00: Attempted to take pressure points. No communication with tool.
| Drilled and orientated 8 1/2" hole from 3364 m MD to 3632 m MD. Circulated well clean. Attempted to take pressure points, tool failure. Picked up and racked back casing offline. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-17, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Run back to bottom. POOH wet with 8 1/2" BHA on 5 1/2" DP from 3632 m to 2450 m. Performed pre-job meeting prior to re-logging for 15 minutes.
00:30 - 02:30: Re-logged interval from 3390 m to 3349 m with 2450 liter/min, 210 bar, 90 RPM, 12-21 KNM.
02:30 - 03:30: RIH with 8 1/2" BHA on 5 1/2" DP from 3349 m to 3632 m.
03:30 - 04:30: Filled pipe, observed pressure increase, worked string clear. Circulated with 2450 liter/min, 215 bar, 140 RPM, 12-19 KNM.
04:30 - 05:00: Dropped gyro and pumped down same with 500 liter/min, 20 bar, 20 RPM, 12-18 KNM.
05:00 - 05:15: Flow checked well for 10 minutes, OK.
05:15 - 10:30: POOH wet with 8 1/2" BHA on 5 1/2" DP from 3632 m to 2706 m. Worked tight spots at 3472, 3126, 3075, 3064, 3028 meter. Restricted pulling speed 2 min/stand. Took gyro readings shoots.
10:30 - 10:45: Pumped 4 m3 1,56 SG slug with 1000 liter/min, 22 bar.
10:45 - 11:30: POOH with 8 1/2" BHA on 5 1/2" DP from 2706 m to 2596 m. Restricted pulling speed 2-1 min/stand. Took gyro readings shoots.
11:30 - 11:45: Flow checked well for 10 min, OK.
11:45 - 16:00: POOH with 8 1/2" BHA on 5 1/2" DP from 2596 m to 203 m. Took gyro readings shoots as required
16:00 - 16:30: Flow checked well for 10 min, OK. Held pre-job meeting prior to handling BHA.
16:30 - 16:45: Retrieved gyro from string.
16:45 - 18:15: POOH with 8 1/2" BHA on 5 1/2" HWDP DC from 203 m to 52 m. Racked back laid down BHA.
18:15 - 18:30: Performed pre-job meeting prior to handling radioactive source.
18:30 - 19:00: Removed radioactive source from BHA.
19:00 - 19:30: Held pre-job meeting for 15 minutes. POOH and broke down 8 1/2" BHA from 52 m to 45 m.
19:30 - 20:30: Down loaded data from MWD tool.
20:30 - 21:45: POOH and broke down 8 1/2" BHA from 45 m to surface.
21:45 - 22:00: Cleaned and cleared drill floor.
22:00 - 00:00: Picked up and made up 8 1/2" BHA, RIH from surface to 21 meter.
| Relogged interval from 3496 m to 3349 m. POOH with 8 1/2" drilling BHA. RIH with 8 1/2" logging BHA. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-18, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: Picked up and made up 8 1/2" BHA, RIH from 21 m to 44 m.
01:00 - 02:15: Plugged into MWD and initialized same.
02:15 - 03:00: Picked up and made up 8 1/2" BHA, RIH from 44 m to 190 m.
03:00 - 03:15: Removed master bushings and installed PS-21 power slips.
03:15 - 04:15: RIH with 8 1/2" BHA on 5 1/2" HWDP DP from 190 m to 997 m. Average tripping speed 807 m/hr.
04:15 - 05:15: Filled pipe and shallow tested MWD tools at 2400 liter/min, 121bar.
05:15 - 06:15: RIH with 8 1/2" BHA on 5 1/2" DP from 997 m to 1800 m. Average tripping speed 803 m/hr.
06:15 - 06:30: Emtied trip tank and filled pipe.
06:30 - 07:30: RIH with 8 1/2" BHA on 5 1/2" DP from 1800 m to 2571 m. Average tripping speed 771 m/hr.
07:30 - 07:45: Filled pipe.
07:45 - 08:00: Performed pre-job meeting prior to slip cut.
08:00 - 10:30: Rigged up, slipped and cut drill line. Calibrated block after slip cut.
10:30 - 11:15: RIH with 8 1/2" BHA on 5 1/2" DP from 2571 m to 2936 m. Reduced speed due to hole condition.
11:15 - 12:15: Washed and reamed tight spot between 2936 m and 2976 m with 2000 liter/min, 120 bar, 80 RPM, 8-16 KNM.
12:15 - 12:30: RIH with 8 1/2" BHA on 5 1/2" DP from 2976 m to 3215 m. Reduced speed due to hole condition.
12:30 - 13:30: Washed and reamed tight spots between 3175 m and 3215 m with 2000 liter/min, 121 bar, 80 RPM, 8-16 KNM.
13:30 - 13:45: RIH with 8 1/2" BHA on 5 1/2" DP from 3215 m to 3264 m. Reduced speed due to hole condition.
13:45 - 17:30: Washed and reamed string down from 3264 m to 3632 m with 1000 liter/min, 44 bar, 50 RPM, 8-13 KNM. At 3286 m hole packed off, stopped pumps and slided through obstruction.
17:30 - 20:30: Circulated hole clean with 2450 liter/min, 185 bar, 130-150 RPM, 14-19 KNM. Reciprocated string. Circulated total 3 x bottoms up.
20:30 - 20:45: Flow checked well for 10 min, OK.
20:45 - 21:15: POOH wet with 8 1/2" BHA on 5 1/2" DP from 3620 m to 3499 m.
21:15 - 00:00: Recorded pressure points.
| RIH with 8 1/2" logging BHA on DP. Washed and reamed tight spots. Slipped cut drill line. Circulated 3 x bottoms up. Recorded pressure points. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-19, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: Recorded pressure points.
01:00 - 01:30: RIH with 8 1/2" BHA on 5 1/2" DP from 3347 m to 3620 m. Reduced speed due to hole condition.
01:30 - 07:45: Back reamed OOH while re-logging from 3620 m to 3333 m with 2540 liter/min, 170 bar, 100 RPM, 12-22 KNM.
07:45 - 09:15: Observed tight spot at 3333 meter, attempted to work through without rotation. Hole packed off. Pulled back to 3295 without flow. Ran back in to 3335 with 1650 liter/min, 87 bar. Re-logged stand from 3333 m to 3295 m.
09:15 - 10:30: Pumped OOH from 3295 m to 3257 m, experienced tight hole. Ran back in to 3273 m without circulation. Re-logged stand from 3273 m to 3255 m.
10:30 - 19:30: Back reamed OOH while re-logging from 3255 m to 2652 m with 2540 liter/min, 160-168 bar, 100-120 RPM, 11-21 KNM.
19:30 - 20:30: POOH while re-logging from 2652 m to 2584 m with 2540 liter/min, 160-168 bar.
20:30 - 21:45: Circulated bottoms up with 2430 liter/min, 218 bar, 130 RPM.
21:45 - 22:15: Flow checked well, OK.
22:15 - 22:30: Function tested BOP.
22:30 - 23:00: Pumped 4 m3 1,56 SG slug with 1000 liter/min, 22 bar.
23:00 - 00:00: POOH with 8 1/2" BHA on 5 1/2" DP from 2584 m to 1800 m. Average tripping speed 784 meter/hr.
| Re-logged open hole with sonic tool. POOH with 8 1/2" logging BHA. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-20, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:15: POOH with 8 1/2" BHA on 5 1/2" DP from 1800 m to 877 m. Average tripping speed 723 meter/hr. Stopped due to fault on iron roughneck.
01:15 - 02:00: Repaired electical failure on iron roughneck. Meanwhile observed well on trip tank.
02:00 - 02:45: POOH with 8 1/2" BHA on 5 1/2" DP from 877 m to 190 m. Average tripping speed 916 meter/hr.
02:45 - 03:00: Flow checked well for 10 min, OK.
03:00 - 04:00: POOH with 8 1/2" BHA on 5 1/2" HWDP from 190 m to 43 m. Laid down jar and accelerator.
04:00 - 04:15: Changed handling equipment.
04:15 - 06:00: Plugged into MWD tool and down loaded data.
06:00 - 07:15: Continued laying down BHA from 43 m to surface
07:15 - 08:00: Cleaned and cleared rig floor after l/d BHA. Changed handling gear in IR and BX elevator. Removed master bushing and installed PS 21. Moved rollers on cantilever.
08:00 - 08:45: Picked up 3 1/2" DP singles, made up and RIH open ended from surface to 143 m.
08:45 - 09:15: Experienced bad connection, checked threads, cleaned box and pin. Retried to m/u no success. Layed out two singles of 3 1/2" DP
09:15 - 10:15: Continued p/u 3 1/2" DP singles and RIH from 143 m to 325 m
10:15 - 10:45: Changed handling equipment from 3 1/2" to 5 1/2"
10:45 - 12:30: RIH w/ cement stinger on 5 1/2" DP from 325 m to 2550 m Avg. Tripping speed 1270 m/hr.
12:30 - 13:15: Broke circulation at 2550 m. Staged up flow and circulated w/ 2450 l/min, 170 bar
13:15 - 14:45: RIH in open hole from 2550 m to 3154 m, restricted running speed due to open ended stinger. Avg. Tripping speed 400 m/hr
14:45 - 15:00: Broke circulation at 3154 m. Circulated w/ 1330l/min, 60 bar
15:00 - 15:45: Cont. RIH in open hole from 3154 m to 3594 m. Restricted running speed due to open ended stinger.
15:45 - 16:15: Established circulation and washed down last stand with 500 LPM, 20 bar. Tagged bottom at 3632 m.
16:15 - 18:00: Staged up pumps to 2500 LPM 190 bar. Circulated hole clean. Reciprocated and rotated pipe with 60 120 RPM while circulating.
18:00 - 18:30: Layed out one single. P/u and m/u cement assy. Connected cement hose
18:30 - 20:15: Established circulation, circulated b/u prior to cement job with 2450 LPM, 187 bar. Performed TBT for setting cement plug
20:15 - 21:30: Balanced cement plug m 3353 m pumped 11,8 m3 of 1,60 SG spacer, 800 l/min/ 30 bar. Mixed and pumped 13,3 m3 of 1,90 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water.
21:30 - 22:00: Zeroed volume counters. Pumped 5,2 m3 of 1,60 SG spacer. Displaced the cement with 31,6 m3 strokes) of 1,32 SG OBM, 2450 l/min/ 180 bar at 30 RPM.
22:00 - 22:15: Broke off cement line, layed out cement assy.
22:15 - 22:45: Pulled out of cement to 3350 m MD. Restricted speed to 3 min/stand
22:45 - 00:00: Made up TDS and circulated out excess cement, 2450 LPM, 200 bar, 80 RPM, 12 KNM.
| POOH out of hole with 8 1/2" BHA, l/d BHA. RIH with 3 1/2" cement stinger on 5 1/2" DP to 3632 m. Circulated and conditioned well before cement job. Set cement plug from 3632 to 3353 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-21, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: Circulated out excess cement, 2450 LPM, 200 bar, 80 RPM, 12 KNM. Performed TBT for setting cement plug
00:45 - 01:15: M/u cement assy and installed cement hose. Tested line to 200 bar for 5 min
01:15 - 03:00: Balanced cement plug m 3074 m pumped 11,8 m3 of 1,60 SG spacer, 800 l/min/ 29 bar. Mixed and pumped 13,3 m3 of 1,90 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 5,2 m3 of 1,60 SG spacer. Displaced the cement with 28 m3 strokes) of mud, 2450 l/min/ 114 170 bar at 30 RPM.
03:00 - 03:45: Broke off cement hose, layed out cement assy. Pulled out of cement to 3070 m. Restricted pulling speed to 3 min/stand
03:45 - 06:00: Circulated out excess cement, 2450 l/min/ 188 bar at 80 RPM, 12 KNM.
06:00 - 09:00: Circulated and conditioned mud prior to setting cement plug and mixed new spacer.
09:00 - 09:30: Rigged up cement assy, installed cement hose and positioned string at 3070 m
09:30 - 10:45: Balanced cement plug m 2795 m pumped 11,8 m3 of 1,60 SG spacer, 600 l/min/ 10 25 bar. Mixed and pumped 13,3 m3 of 1,90 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 5,2 m3 of 1,60 SG spacer. Displaced the cement with 25,1 m3 strokes) of mud, 2500 l/min/ 100 155 bar at 25 RPM.
10:45 - 11:00: Layed out cement assy.
11:00 - 11:30: Pulled out of cement to 2790 m MD. Restricted pulling speed to 2 3 min/stand
11:30 - 14:00: Circulated out excessive spacer and cement at 2790 m, 2500 LPM, 172 bar, 80 RPM.
14:00 - 14:15: Made up cement assy, installed cement hose, positioned string at 2790 m. Confirmed line-up.
14:15 - 15:45: Cement/ko plug m 2545 m pumped 11,8 m3 of 1,60 SG spacer, 800 l/min/ 10 25 bar. Mixed and pumped 13,4 m3 of 2,00 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 1,3 m3 spacer. Displaced the cement with 26,8 m3 strokes) of mud, 2500 l/min/ 140 170 bar at 25 RPM.
15:45 - 16:15: Pulled out of cement to 2590 m. Restricted pulling speed to 2 3 min/stand.
16:15 - 18:45: Installed sponge balls, circulated out excessive cement and hole clean, 2500 LPM, 170 180 bar at 60 120 RPM. Reciprocated string.
18:45 - 19:00: Flowchecked well for 15 min. Well static.
19:00 - 19:15: Pumped slug
19:15 - 19:45: POOH w/ 3 1/2" cement stinger on 5 1/2" DP from 2590 m to 2180 m Avg. Tripping speed 820 m/hr.
19:45 - 20:15: Carriage travel fault on iron roughneck, identified faulty cable, rectified and secured same
20:15 - 22:15: POOH w 5 1/2" DP from 2180 m to 326 m Avg. Tripping speed 927 m/hr.
22:15 - 22:30: Flowchecked well for 15 min. Well static. Meanwhile changed handling equipment from 5 1/2" to 3 1/2".
22:30 - 00:00: L/d 34 joints of 3 1/2 DP, 26 jnts/hr.
| Set cement plug from 3350 to 3070 m. Set cement plug from 3070 to 2790 m. Set cement plug from 2790 to 2545 m. POOH with cement string and l/d 3 1/2" cement stinger |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-22, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:00: RIH 26 5 1/2" DP stands from derrick
02:00 - 02:45: Installed sponge balls, made up TDS and circulated 3x string volume w/ 2500 l/min, 29 bar
02:45 - 04:15: POOH stands and racked same
04:15 - 05:00: Cleanend and cleared rig floor, changed handling gear
05:00 - 05:15: Performed pre- job meeting for handling BHA
05:15 - 07:00: P/u and m/u BHA as per baker DD instructions. Broke out 8 3/8" flex stab from ass stearing head. P/u module and changed bit.
07:00 - 07:15: Performed pre-job meeting with upcoming shift
07:15 - 08:15: P/u and m/u BHA in modules as per baker DD instructions
08:15 - 09:45: Plugged into tools and verified same, took scribe line from ontrak to testrak. M/u x/o, float sub and string stab.
09:45 - 10:30: Placed barriers, made announcement for handling radioactive sources. RPS installed sources.
10:30 - 11:15: Continued p/u and m/u BHA as per baker instructions
11:15 - 11:30: Installed PS 21 slips
11:30 - 12:45: RIH w/ 8 1/2" BHA on 5 1/2" DP from 198 m to 1000 m Avg. Tripping speed 641 m/hr.
12:45 - 13:30: Filled pipe and tested MWD tools w/ 2180 LPM and 118 bar.
13:30 - 14:15: Continued RIH with 5 1/2" DP from 1000 m to 1814 m.
14:15 - 14:30: Filled pipe at 1814 m.
14:30 - 15:15: RIH 5 1/2" DP from 1814 m to 2539 m Avg. Tripping speed 967 m/hr.
15:15 - 16:30: Filled pipe, washed from 2539 m to 2592 m w/ 1770 l/min, 90 bar, 30 RPM, 8 KNM. Tagged cement with 2 tons, soft cement.
16:30 - 20:30: Circulated and conditioned mud w/ 2450 l/min, 180 bar. Reduced MW from 1,32 SG to 1,28 SG. Reciprocated string while circ. Flushed all surface lines and took SCR with new mud weight. Meanwhile isolated and serviced all drillfloor equipment.
20:30 - 21:00: M/u next stand and washed in through soft cement from 2592 m to 2598 m, 1800 LPM, 95 bar, 60 RPM, 8 KNM. Firm cement at 2598 m, 5 ton wob. Pulled back into shoe to confirm string free.
21:00 - 21:30: Drilled cement from 2598 m to 2601 m, wob 2-3 tonne. 1800 l/min, 95 bar. 60 RPM 8 15 KNM.
21:30 - 22:00: Reamed back through shoe, broke out double and racked same. M/u new stand to enable continues kick-off
22:00 - 22:30: Reamed to bottom at 2601 m w/ 1800 l/min, 95 bar, 60 RPM, 8 12 KNM. Observed string stall and pressure increase to 200 bar. Not able to rotate and circulate, pressure increases immediatly.
22:30 - 23:00: Stuck with flex stab in 13 3/8" shoe, stab 5 m behind bit. Attempted to free string and regaining circulation by working 40 KNM torque in string and keeping 60 bar pressure on string. Pressure dropping off and flow reported in flowline.
23:00 - 23:30: Worked torque out of string and took 100 t overpull to 150 t hockload. Attempted to cock jar down and pick up to 250 ton, jar did not fire. Attempted to cock jar and picked up to 300 ton on hook t overpull). String was observed to be free. Pulled back into CSG shoe.
23:30 - 00:00: Worked string above shoe to clear BHA with 2500 LPM, 161 bar, 120 RPM, 6 15 KNM
| P/u, m/u 8 1/2" drilling BHA and RIH reduced MW from 1,32 SG to 1,28 SG drilled cement in casing and rathole freed stuck string |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 on 2013-08-23, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:30: Worked string in steps through shoe from 2592 m to 2601 m with 2500 LPM, 161 bar, 120 RPM, 6-25 KNM. String attempted to stall several time while working rathole. Oberserved pressure spikes while going to bottom. Worked area several times. Drilled to 2602 m.
01:30 - 03:00: Started to kick off from 2602 m. Send downlink to set tool in hold mode. Drilled from 2602 m to 2610 m, 2000 LPM, 113 bar, 80 RPM, 8 12 KNM, 2 4 tons wob, controlled ROP 5 m/h.
03:00 - 05:00: Sent downlink to increase build force. Drilled 8 1/2" hole from 2610 m to 2620 m, wob 4 tonne. 2000 l/min/ 116 bar. 80 RPM 8 12 KNM. Controlled ROP 7 m/h. 50 formation at 2620 m. Last report on f-1 continue to report on f-1a
| Worked and reamed shoe and rathole. Commenced kick off to f-1a |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-23, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 05:00 - 07:00: Drilled and oriented 8 1/2" hole from 2620 m to 2632 m, controlled ROP 10 m/hr. Wob 5 12 tonne. 2000 l/min/ bar. 80 RPM 8 12 KNM. Started bleeding in LCM premix, 4m3 per stand for drilling ty fm.
07:00 - 09:00: Drilled and oriented 8 1/2" hole through ty fm. From 2632 m to 2673 m, average ROP 20 m/hr. Wob 5 12 tonne. 2000 2400 l/min/ 143 170 bar, ECD 1,34. 80 140 RPM 11 22 KNM. Increased RPM after top stab out of casing shoe. Bleed in LCM premix as per plan to maintain particle concentration.
09:00 - 12:30: Drilled and oriented 8 1/2" hole through ty fm. From 2673 m to 2771 m maintaining constant drilling parameters and bleeding in LCM premix, average ROP 28 m/h. Wob 5 12 tonne. 2400 l/min/ 170 175 bar. 140 RPM 12 20 KNM. ECD 1,36 SG
12:30 - 17:00: Drilled and oriented 8 1/2" hole in shetland gp. From 2771 m to 2857 m, average ROP 19 m/hr. Wob 5 12 tonne. 2400 l/min/ 175 bar. 140-160 RPM 12 25 KNM. ECD 1,37. Increased RPM to 160 to combat high stick slip.
17:00 - 17:15: Took SCR
17:15 - 19:00: Drilled and oriented 8 1/2" hole in shetland gp. From 2857 m to 2892 m, average ROP 20 m/hr. Wob 10 12 tonne. 2400 l/min/ 175 bar. 160 RPM 11 26 KNM. ECD 1,37. Added four sacks baracarb 50/150 and steelseal 100/400 per stand to maintain LCM background concentration.
19:00 - 00:00: Drilled and oriented 8 1/2" hole in shetland gp. From 2892 m to 3004 m, average ROP 22 m/hr. Wob 10 14 tonne. 2400 l/min/ 175 178 bar. 160 RPM 12 25 KNM. ECD 1,37 1,38 SG. Added four sacks baracarb 50/150 and steelseal 100/400 per stand to maintain LCM background concentration.
| Kicked off well from f-1 drilled and steered 8 1/2" section to 3004 m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-24, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:00: Drilled and oriented 8 1/2" hole from 3004 m to 3070 m, average ROP 22 m/h wob 5 12 tonne. 2400 l/min/ 175 180 bar. 160 RPM 15 22 KNM. ECD 1,38 SG. Started to increase MW from 1,28 SG to 1,32 SG.
03:00 - 04:30: Drilled and oriented 8 1/2" hole from 3070 m to 3094 m, average ROP 15 m/hr. Wob 5 8 tonne. 2400 l/min/ 183 bar. 160 RPM 15 20 KNM. ECD 1,39 SG. Experienced problems in achieving required build rate, controlled ROP to 15 m/hr, set build force to 97 reduced walk force. Increased MW from 1,28 SG to 1,32 SG. Maintained LCM background concentration
04:30 - 08:00: Drilled and oriented 8 1/2" hole from 3094 m to 3128 m, average ROP 9,7 m/hr. Wob 1 3 tonne. 2400 l/min/ 183 bar. 160 RPM 12 17 KNM. ECD 1,40 SG. Controlled ROP to 10 m/hr to improve steering capability. MW in out 1,32 SG. Maintained LCM background concentration
08:00 - 19:00: Drilled and oriented 8 1/2" hole from 3128 m to 3317 m, average ROP 17,2 m/hr. Wob 2 14 tonne. 2400 l/min/ 183 189 bar. 160 RPM 12 24 KNM. ECD 1,40 SG. Took scrs at 3303 m maintained LCM background concentration
19:00 - 00:00: Drilled and oriented 8 1/2" hole from 3317 m to 3426 m, average ROP 22 m/hr. Wob 5 12 tonne. 2400 l/min/ 188 195 bar. 160 RPM 14 25 KNM. ECD 1,42 SG. Maintained LCM background concentration
| Drilled and oriented 8 1/2" hole from 3004 m to 3426 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-25, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 05:30: Drilled 8 1/2" hole from 3426 m to 3546 m, average ROP 22 m/hr. Wob 7 14 tonne. 2450 l/min/ 190 195 bar. 160 RPM 18 22 KNM. ECD 1,42 SG. Maintained LCM background concentration controlled ROP to 25 m/hr
05:30 - 05:45: Took SCR
05:45 - 07:45: Drilled 8 1/2" hole from 3546 m to 3576 m, average ROP 15 m/hr. Wob 7 14 tonne. 2450 l/min/ 190 195 bar. 160 RPM 18 22 KNM. ECD 1,42 SG. Maintained LCM background concentration controlled ROP to 25 m/hr
07:45 - 08:30: Circulated and reciprocated string while baker logging unit re-booted computer system
08:30 - 15:15: Drilled 8 1/2" hole from 3576 m to TD at 3682 m, average ROP 15,7 m/hr. Wob 2 14 tonne. 2450 l/min/ 195 199 bar. 160 RPM 11 26 KNM. ECD 1,42 SG. TD 3682 m MD. Controlled ROP from 3626 3640 m 15 m/hr 3640 3682 m 10 m/hr maintained LCM background concentration
15:15 - 15:30: Took final survey and downlinked
15:30 - 17:00: Circulated hole clean w/ 2450 l/min/ 197 194 bar, 140 RPM 12 20 KNM, ECD 1,41 SG. Circulated first b/u reciprocated string from 3682 3662 m
17:00 - 17:15: Racked back one stand
17:15 - 20:30: Circulated hole clean w/ 2450 l/min/ 192 bar, 140 RPM 21 20 KNM, ECD 1,40 SG, total 3 x b/u reciprocated string from 3662 3327 m. Hold TBT for taking pressure points and re-logging
20:30 - 21:00: POOH 5 1/2" stands from 3665 m to 3505 m. Limited pulling speed to 2-3 min/stand. Made up TDS.
21:00 - 21:45: Re-logged section from 3503,3 to 3491 m w/ 2000 LPM, 135 bar, 60 RPM, 12 17 KNM.
21:45 - 22:00: RIH from 3491 m to 3544 m.
22:00 - 23:45: Made up TDS and re-logged section from 3544 to 3506 m w/ 2000 LPM, 135 bar, 60 RPM, 12 17 KNM.
23:45 - 00:00: RIH to 3534 m. Took weights 188 t up, 144 t down, 157 t rot. Performed 10 min. Sticky test
| Drilled 8 1/2" hole to TD at 3682 m. Circulated hole clean. Re-logged interval and commenced taking pressure points. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-26, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Established circ. With 2000 LPM. 145 bar and positioned string at bit depth 3521,1 m. Adjusted string to neutral weight and hold stationary while taking testrak pressure point at 3493 m bad test.
00:30 - 01:00: POOH to 3523 m bit depth and positioned string. Performed second attempt for pressure point good test.
01:00 - 01:30: POOH to 3511 bit depth and positioned string. Took testrak pressure point at 3480 m bad test.
01:30 - 02:00: RIH to 3512 m bit depth, positioned string. Performed second attempt for pressure point bad test.
02:00 - 02:30: POOH to 3493 m bit depth, positioned string. Took testrak pressure point at 3462 m good test.
02:30 - 03:00: POOH to 3488 m bit depth, positioned string. Took testrak pressure point at 3457 m good test.
03:00 - 03:30: POOH to 3468 m bit depth, positioned string. Took testrak pressure point at 3437 m good test.
03:30 - 03:45: RIH from 3468 m to 3681 m.
03:45 - 04:00: Circulated at TD to confirm free circulation before droping gyro.
04:00 - 04:15: Flowchecked well for 10 min, broke connection and loaded gyro tool.
04:15 - 04:45: Pump down gyro tool w/ 500 LPM, 26 bar, 20 RPM, 15 17 KNM.
04:45 - 05:00: Pumped 3 m3 slug and chased same.
05:00 - 05:15: POOH from 3681 m to 3667 m, slug did not work.
05:15 - 05:45: Pumped 5 m3 slug and chased same.
05:45 - 07:00: POOH w/ 8 1/2" BHA on 5 1/2" DP from 3667 m to 3225 m Avg. Tripping speed 354 m/hr. Restricted tripping speed and stoped when required for gyro station.
07:00 - 07:45: POOH, observed swabing at 3225 3220 m. Ran back in, volumes correct. Continued to POOH from 3225 m to 2982 m. Observed swabbing and overpull, trip tank increased. Wiped single, trip trank decreased to correct volume.
07:45 - 08:15: Pumped OOH from 2982 m to 2940 m, 2200 LPM, 150 bar. Observed pressure increase while pulling. Reduced rate to 1350 LPM.
08:15 - 08:30: RIH from 2940 m 2982 m for gyro overlap.
08:30 - 11:00: POOH from 2982 m to 2580 m inside the casing shoe. Avg. Tripping speed 161 m/hr. Pulled wet, observed backflow, two slugs in annulus and float not holding. M/u TDS on every connection. Restricted speed due to gyro.
11:00 - 11:15: Flowchecked well for 15 min, well static.
11:15 - 11:30: POOH from 2580 m to 2499 m, pulled wet. Observed backflow. Restricted speed due to gyro.
11:30 - 11:45: Pumped slug and allowed levels to stabilise.
11:45 - 13:15: POOH from 2499 m to 1650 m. Avg. Tripping speed 566 m/hr. Restricted speed due to gyro.
13:15 - 13:30: RIH from 1650 m to 1770 m. Re-surveyed as per scientific intructions.
13:30 - 14:45: POOH from 1770 m to 480 m. Avg. Tripping speed 1032 m/hr.
14:45 - 15:00: Took rotational checks as per scientific instructions.
15:00 - 15:15: POOH from 480 m to 238 m.
15:15 - 15:30: Flowchecked well for 10 min, well static. Removed ps21 slips.
15:30 - 15:45: TBT with involved personnel for handling BHA.
15:45 - 16:00: POOH from 238 m to 171 m.
16:00 - 16:30: Broke double and layed out scientific gyro toolstring.
16:30 - 17:15: Pulled out to 50 m, layed out jar and accelerator.
17:15 - 18:00: Made announcement for handling ra sources, placed barriers. Baker RPS removed sources.
18:00 - 20:00: Plugged into tools and downloaded data. Dumped soundtrak and testrak, ontrak and copilot.
20:00 - 21:45: Cleaned and l/o BHA as per DD instructions.
21:45 - 22:15: Cleaned and cleared rigfloor.
22:15 - 23:30: Moved power rollers for 3 1/2" DP. Serviced TDS, dollies and both PRS.
23:30 - 23:45: Changed handling gear in slips and elevators from 5 1/2" to 3 1/2".
23:45 - 00:00: Picked up, made up and RIH with open ended 3 1/2" cement stinger to 40 m.
| Took pressure points. POOH and l/d 8 1/2" BHA m/u and RIH with 3 1/2" cement stinger |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-27, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:15: Picked up, made up and RIH with open ended 3 1/2" cement stinger from 40 to 317 m.
01:15 - 02:00: Installed x/o, changed elevator inserts to 5 1/2", m/u stand and changed slip inserts to 5 1/2".
02:00 - 03:00: RIH w/ 3 1/2" cement stinger on 5 1/2" DP from 317 m to 1366 m.
03:00 - 03:15: Hydraulic fitting broke on auto slips. Replaced same.
03:15 - 04:15: RIH on 5 1/2" DP from 1366 m to 2580 m Avg. Tripping speed 1214 m/hr.
04:15 - 05:00: Took up and down weights. RIH in open hole from 2595 m to 3141 m. Restricted speed due to open endend DP in open hole.
05:00 - 05:15: Broke circ. With 1000 LPM, 20 bar.
05:15 - 06:15: RIH from 3141 m to 3670 m Avg. Tripping speed 529 m/hr. Restricted speed due to open ended pipe.
06:15 - 06:30: M/u TDS and washed in from 3670 m to bottom at 3682 m, 500 LPM, 27 bar. Tagged bottom.
06:30 - 08:15: Pulled back to 3673 m and circulated prior to cement job 2450 l/min/ 205 bar, 60 RPM. Reciprocated string.
08:15 - 08:30: Spaced out string, m/u cement assy and surface line. Tested line to 20/200 bar for 5 min.
08:30 - 10:00: Balanced cement plug 3387 m) pumped 11,6 m3 of 1,60 SG spacer, 800 l/min/ 30 bar. Mixed and pumped 14 m3 of 1,90 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 3,6 m3 of 1,60 SG spacer. Displaced the cement with 29,1 m3 strokes) of mud, 2450 l/min/ 150 190 bar at 60 RPM.
10:00 - 10:15: Broke out surface line and l/d cement assy.
10:15 - 11:00: Pulled out of cement to 3387 m MD. Pulled dry, 2 3 min/ stand.
11:00 - 12:45: Circulated out excess cement and spacer 2450 l/min/ 203 bar, 80 RPM. Reciprocated string.
12:45 - 13:15: M/u cement assy and installed surface line. Tested surface line to 20/200 bar for 5 min.
13:15 - 14:30: Balanced cement plug m 3092 m) pumped 11,6 m3 of 1,60 SG spacer, 800 l/min/ 22 bar. Mixed and pumped 14 m3 of 1,90 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 3,61 m3 of 1,60 SG spacer from surface lines. Displaced the cement with 25,9 m3 strokes) of mud, 2450 l/min/ 170 bar at 60 RPM.
14:30 - 14:45: Broke off surface line and l/d cement assy.
14:45 - 15:15: Pulled out of cement to 3090 m MD. Pulled dry, 2 min/stand.
15:15 - 17:30: Circulated out excess cement and spacer 2450 l/min/ 190 bar, 80 RPM. Reciprocated string.
17:30 - 18:00: M/u cement assy and installed surface line. Tested surface line to 20/200 bar for 5 min.
18:00 - 19:15: Balanced cement plug m 2797 m) pumped 11,6 m3 of 1,60 SG spacer, 800 l/min/ 10 22 bar. Mixed and pumped 14 m3 of 1,90 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 3,6 m3 of 1,60 SG spacer from surface lines. Displaced the cement with 22,6 m3 strokes) of mud, 2500 l/min/ 116 153 bar at 20 RPM.
19:15 - 19:30: Broke off surface line and l/d cement assy.
19:30 - 20:00: Pulled out of cement to 2795 m MD. Pulled dry, 2 3 min/stand.
20:00 - 21:45: Circulated out excess cement and spacer 2500 l/min/ 180 bar, 60 RPM. Reciprocated string.
21:45 - 22:30: M/u cement assy and installed surface line. Tested surface line to 20/200 bar for 5 min.
22:30 - 23:30: Balanced cement k/o plug m 2547 m) pumped 11,6 m3 of 1,60 SG spacer, 800 l/min/ 20 bar. Mixed and pumped 13,3 m3 of 2,0 SG cement slurry, 600 l/min. Displaced the cement to the rig floor with 890 l of drill water. Zeroed volume counters. Pumped 3,6 m3 of 1,60 SG spacer fro msurface lines. Displaced the cement with 22,2 m3 strokes) of mud, 2500 l/min/ 68 155 bar at 20 RPM.
23:30 - 23:45: Broke off surface line and l/d cement assy.
23:45 - 00:00: Pulled out of cement. Pulled dry, 2 3 min/stand.
| RIH with cement stinger. Set cement plugs to |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-28, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Pulled out of cement to 2545 m MD. Pulled dry, 2 3 min/stand.
00:15 - 01:45: Circulated out excess cement and spacer 2500 l/min/ 172 bar, 60 RPM.
01:45 - 02:00: POOH 2 stand, installed 2 sponge balls.
02:00 - 03:30: Circulated b/u and flushed string, 3300 l/min/ 255 bar at 120 RPM.
03:30 - 05:30: POOH w/ 3 1/2" cement stinger on 5 1/2" DP.
05:30 - 06:00: Changed to 3 1/2" handling equipment.
06:00 - 07:30: L/d 33 joints of 3 1/2 cement stinger.
07:30 - 08:00: Changed to 5 1/2" handling equipment, cleanend rigfloor.
08:00 - 10:15: RIH to 1220 m with cement contaminated 5 1/2" stands.
10:15 - 11:00: Installed two sponge balls and flushed string, circ. 1,5 x string volume.
11:00 - 12:45: POOH 5 1/2" stands and r/b same.
12:45 - 13:00: Removed ps21 slips, installed master bushing. Cleaned and cleared rigfloor. Function tested shear ram.
13:00 - 13:15: Performed pre-job meeting prior to run BOP test tool.
13:15 - 14:30: M/u jet sub and BOP test tool. RIH w/ test tool. Jetted BOP/WELLHEAD area at 138 m with 1500 LPM, 15 bar. Landed BOP test tool in wellhead. Meanwhile lined up and tested line to 20/345 bar 5/5 min.
14:30 - 14:45: Displaced BOP to water using cement unit.
14:45 - 19:15: Tested BOP pipe rams and annular to 20 bar/ 5 min and 345 bar/ 10 min. Tested kill and choke lines to 20 bars 5 min and 345 bar/ 10 min with water.
19:15 - 19:30: Opened BOP and displaced same with OBM.
19:30 - 20:30: POOH and l/d BOP test tool. R/d handling equipment and cleared rig floor.
20:30 - 20:45: Performed pre-job meeting prior to m/u BHA.
20:45 - 22:00: P/u and m/u 12 1/4" BHA in moduls as per baker DD instructions
22:00 - 23:00: Plugged into tools and verfied same.
23:00 - 00:00: P/u and m/u 12 1/4"" BHA including HWDP as per baker DD instructions. Changed out one HWDP, damaged box observed.
| POOH with cement stinger. L/d 3 1/2" singles to deck. RIH and flushed 5 1/2" DP stands. Tested BOP. P/u and m/u 12 1/4" BHA. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 A on 2013-08-29, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:15: P/u and m/u 12 1/4" BHA, picked up HWDP, m/u jar and accelerator. Installed totco ring on top of accelerator.
02:15 - 02:30: Removed master bushing, installed ps21 slips.
02:30 - 03:45: RIH w/ 12 1/4" BHA on 5 1/2" DP from 247 m to 1020 m Avg. Tripping speed 618 m/hr.
03:45 - 04:15: Filled string and emptied TT
04:15 - 05:15: RIH on 5 1/2" DP from 1020 m to 1860 m Avg. Tripping speed 840 m/hr.
05:15 - 05:30: Filled string and emptied TT.
05:30 - 06:15: RIH on 5 1/2" DP from 1860 m to 2467 m. Avg. Tripping speed 810 m/hr.
06:15 - 06:30: Filled string and emptied TT.
06:30 - 07:30: Closed BOP and performed choke drill with both shifts, driller, ad and lead driller.
07:30 - 07:45: RIH from 2467 m to 2507 m, m/u TDS.
07:45 - 08:30: Washed from 2507 m to 2555 m w/ 2300 l/min, 120 bar, 20 RPM, 8 KNM. Tagged TOC at 2555 m.
08:30 - 11:00: Drilled excess cement from 2555 m to 2595 m, wob 6 tonne. 2300 l/min/ 123 bar. 20 RPM 12 18 KNM. Reduced MW while drilling cement from 1,32 SG to 1,28 SG.
11:00 - 11:30: Downlinked set tools ribs off.
11:30 - 12:00: Drilled from 2595 m to 2604 m in steps to clean shoe area and rathole with 2300 LPM, 113 bar, 20 RPM, 10 16 KNM, wob 1-3 tonne. Softer cement in the rat hole.
12:00 - 12:30: Pulled back to 2588 m, tared copilot, downlinked to set tools for k/o, reamed in to 2604 m.
12:30 - 15:30: Kicked off from 2604 m. Drilled from 2604 m to 2617 m, wob 3 5 tonne. 2800 l/min/ 153 bar. 40 RPM 13 17 KNM. Controlled ROP to 5 m/hr. Drilled as per baker DD instructions. Bending moment and NB inc. Indicating successful sidetrack at 2617 m. Last report on f-1 a, continue reporting on f-1 b.
| P/u and m/u 12 1/4" BHA. RIH on 5 1/2" DP. Performed choke drill. Drilled out cement and kicked off well to f-1 b. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-08-29, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 15:30 - 17:00: Continued to kick off from f-1 a. Drilled 12 1/4" hole from 2617 m to 2627 m as per baker DD instructions. Wob 2 5 tonne. 2800 l/min/ 153 bar. 40 RPM 13 17 KNM. Started bleeding in LCM premix, 4m3 per stand for drilling ty fm.
17:00 - 19:00: Drilled and oriented 12 1/4" hole from 2627 m to 2650 m. Average ROP 11,5 m/hr. Wob 3 6 tonne. 3500 l/min/ 215 220 bar. 80 RPM 15 KNM. ECD 1,32 SG. Bleed in LCM premix as per plan to maintain particle concentration. Initially controlled ROP to 10 m/hr.
19:00 - 00:00: Drilled and oriented 12 1/4" hole from 2650 m to 2763 m. Average ROP 22,6 m/hr, wob 2 6 tonne. 3500 l/min/ 215 220 bar. 80 RPM 17 21 KNM. ECD 1,32 SG. Bleed in LCM premix as per plan to maintain particle concentration.
| Kicked off well from f-1 a. Drilled 12 1/4" hole through ty fm. To 2763 m. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-08-30, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:30: Drilled and oriented 12 1/4" hole from 2763 m to 2820 m. Average ROP 21,6 m/hr wob 3 11 tonne. 3500 l/min/ 217 230 bar. 100 RPM 17 29 KNM. ECD 1,32 SG. Maintained LCM background concentration.
02:30 - 02:45: Cleared tripped cuttings conveyor.
02:45 - 07:00: Drilled 12 1/4" hole from 2820 m to 2903 m. Average ROP 19,5 m/hr. Wob 9 12 tonne. 3500 l/min 220 235 bar. 100 RPM 11 29 KNM. ECD 1,31 SG. Maintained LCM background concentration.
07:00 - 12:00: Drilled 12 1/4" hole from 2903 m to 3010 m, average ROP 21,4 m/hr, wob 9 12 tonne. 3500 l/min/ 225 230 bar. 100 RPM 20 30 KNM. ECD 1,31 SG. Maintained LCM background concentration.
12:00 - 17:15: Drilled 12 1/4" hole from 3010 m to TD at 3097 m. Average ROP 16,6 m/hr wob 10 14 tonne. 3500 l/min/ 225 238 bar. 100 RPM 20 25 KNM. ECD 1,31 SG. Section TD at 3097 m. Maintained LCM background concentration.
17:15 - 17:30: Took TD survey and downlinked to ribs off.
17:30 - 19:30: Circulated hole clean w/ 3500 l/min/ 212 220 bar, 100 RPM 12 15 KNM, ECD 1,30 SG.
19:30 - 21:15: Circulated hole clean w/ 3500 l/min/ 210 212 bar, ECD 1,30 SG. Circulated total 3 b/u, 690 m3. Racked one stand. Meanwhile repaired hydraulic leak on TDS allignment cylinder. Serviced TDS and dolly.
21:15 - 21:30: Flowchecked well for 15 min. Well stable. Meanwhile performed TBT for drop down gyro.
21:30 - 21:45: Dropped gyro.
21:45 - 22:00: RIH to bottom.
22:00 - 23:00: POOH w/ 12 1/4" BHA and drop gyro on 5 1/2" DP from 3096 m to 2900 m. Pulled 5 stands wet.
23:00 - 23:30: Pumped 4m3 slug and chased same. Filled trip tank.
23:30 - 23:45: Continued to POOH with 12 1/4" BHA and drop gyro on 5 1/2" DP. Baker mud logging unit shut down due to high winds.
23:45 - 00:00: Troubleshoot logging unit and prepared temporary wind protection on air intake.
| Drilled and oriented 12 1/4" hole to section TD at 3097 m. Circulated hole clean, circulated 3 x b/u. Dropped gyro and POOH with 12 1/4" BHA on 5 1/2 DP. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-08-31, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: POOH w/ 12 1/4" BHA. Controlled speed while monitoring volumes with rig sensors. Meanwhile arranged wind protection and re-booted logging unit.
01:00 - 01:30: POOH w/ 12 1/4" BHA and drop gyro into the casing shoe.
01:30 - 01:45: Flowchecked well for 15 min. Well stable.
01:45 - 03:45: POOH w/ 12 1/4" BHA on 5 1/2" DP from 2590 m to 448 m Avg. Tripping speed 856 m/hr.
03:45 - 04:15: Took rotational shot surveys as per scientific instructions.
04:15 - 04:30: POOH with 12 1/4" BHA from 448 m to 247 m.
04:30 - 04:45: Flow checked well for 15 min prior to pull BHA through BOP. Well stable. Hold TBT for handling BHA.
04:45 - 05:00: POOH 12 1/4" BHA on HWDP. Racked HWDP stands.
05:00 - 05:15: Recovered gyro tool string and l/d same.
05:15 - 05:45: Removed ps21 slips and installed master bushings.
05:45 - 08:15: L/d 12 1/4" BHA from 125 m to 32 m as per baker DD lay down plan.
08:15 - 09:00: Plugged into ontrak and downloaded data.
09:00 - 10:00: POOH to 3 m, plugged into copilot and downloaded data.
10:00 - 11:00: Cleaned and layed out BHA, inspected bit. Bit grading 0-2-wt-t-x-1/16-no-td.
11:00 - 11:30: Cleaned and cleared rigfloor.
11:30 - 12:00: Picked up bullnose jetting sub and wbrrt.
12:00 - 12:45: RIH to 138 m, restricted speed due to fullbore tool. M/u TDS and jetted well head area with 1500 LPM, 15 bar.
12:45 - 13:15: RIH from 138 m to 181 m, set down 5 tons and checked measurement for casing hanger run. Pulled WB with 37 tons overpull.
13:15 - 14:30: POOH from 181 m to 138 m, jetted wellhead area with 1500 LPM, 15 bar. Dropped drift and POOH to surface. L/d WB, reset tool and l/d same.
14:30 - 15:00: Cleaned and cleared rigfloor.
15:00 - 15:30: Moved weatherford tong into position, arranged hoses and jam unit.
15:30 - 15:45: Hold TBT prior to slip and cut operation.
15:45 - 17:30: Rigged up, slipped and cut 44 m drill line. Cleaned and cleared rig floor.
17:30 - 18:00: Calibrated blocks with both rig and baker systems.
18:00 - 18:45: Tidied rigfloor prior to rigging up casing equipment.
18:45 - 22:30: R/u handling equipment for 9 5/8" casing. Changed bails and installed elevators, function tested same. Removed bushings and installed FMS. Function tested same.
22:30 - 22:45: Performed pre-job meeting prior to pick up shoe joint.
22:45 - 23:00: P/u 9 5/8" shoe joint from deck, checked float OK.
23:00 - 23:30: Installed weatherford fill-up tool. Installed bypass baffle.
23:30 - 00:00: M/u shoe joint to float collar/intermediate stand from derrick. Thread locked connection.
| POOH with 12 1/4" BHA and drop gyro on 5 1/2" DP. L/d BHA. Retrieved wear bushing and jetted wellhead area. Performed slip cut. R/u for running 9 5/8" casing. P/u and RIH shoe joint, m/u stand w/ two intermediates and LC joint. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-01, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: RIH shoetrack, p/u single joint from deck and m/u same.
00:30 - 01:45: RIH with 9 5/8" 53,5ppf p110 VAM top casing from 63 m to 209 m Run casing in stands from derrick. Filled every stand.
01:45 - 02:00: Changed leaking mud saver valve.
02:00 - 07:00: RIH with 9 5/8" 53,5 ppf p110 VAM top casing from 209 m to 1207 m. Run stands from derrick. Filled casing every stand. Average running rate 5,5 stands/hr
07:00 - 12:00: RIH with 9 5/8" 53,5ppf p110 VAM top casing from 1207 m to 2489 m. Run stands from derrick. Filled casing every stand. Average running rate 7,1 stands/hr.
12:00 - 12:15: Changed to 10 3/4" elevators and tong jaws.
12:15 - 12:30: P/u x-over joint from deck and m/u same.
12:30 - 13:30: Changed out slips to 10 3/4" and changed die blocks in casing tong.
13:30 - 16:00: RIH with 10 3/4" 65,7ppf p110 VAM top casing from 2489 m to 2944 m. Run stands from derrick. Filled casing every stand. Average running rate 5 stands/hr.
16:00 - 16:15: Performed TBT before rigging down casing running equipment.
16:15 - 17:30: R/d casing fill-up tool, bails, elevator and rotator. Installed bails and elevators for 5 1/2" DP.
17:30 - 17:45: Performed TBT before picking up casing hanger.
17:45 - 18:00: P/u, cleaned and m/u casing hanger.
18:00 - 18:30: Removed ps30 slips and installed outer ring and master bushings. RIH hanger below rotary.
18:30 - 19:45: R/d handling equipment for 10 3/4" casing, r/d casing tongs and cleared rig floor.
19:45 - 20:30: RIH with 9 5/8" x 10 3/4" casing on 5 1/2 HWDP landing string from 2954 m to 2994 m. Circulated string with 500 LPM while RIH.
20:30 - 21:30: RIH on landing string from 2994 m to 3089 m. Circulated string with 500 LPM while RIH.
21:30 - 22:00: Broke out HWDP double from LS.
22:00 - 23:15: P/u cement stand. M/u cement hoses and control lines. M/u cement stand to landing string. Landed casing hanger in wellhead as per vetco instructions. Confirmed hanger set as per procedure.
23:15 - 00:00: Increased flow in 250 l/min steps to 2500 l/min/ 80 bar. Let flow and pressure stabilize on each step. No losses to formation.
| M/u and RIH 9 5/8" shoe track. M/u and RIH 9 5/8" casing in stands from derrick. M/u x-over joint and continued RIH with 10 3/4" casing stands from derrick. Installed casing hanger and RIH casing on 5 1/2" HWDP landing string. Landed casing and confirmed hanger set. Circulated well prior to cement job. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-02, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:00: Circulated prior to cement job 2500 l/min 80 85 bar. After 1,15 x b/u experienced a 5 bar pressure drop and indication of losses. Checked surface equipment, OK.
01:00 - 02:30: Established loss free rate at 1350 LPM/ 45 bar. Lost 3,2 m3 of mud in total during circulation. Held TBT prior to cement job.
02:30 - 05:15: Pumped 22 m3 of 1,60 SG spacer with rig pumps, pumped with loss free rate 1350 LPM. Lined up from cement unit and verified line-up. Released dart for bottom plug, verified flag indication. Mixed and pumped 14 m3 1,90 SG slurry at 680 LPM, released top dart and observed top plug release at 950 l pumped and 82 bar. Chased cement w/ rigpumps and 2500 LPM. Displaced cement with 1300 1600 LPM. Used bottom plug landing shear to calibrate pump efficieny 95,6 displaced cement into annulus with 2000 LPM, following pump plan. Bumped top plug at 5190 strokes efficency). Pressured up to 70 bar above final circulation pressure of 55 bar. Checked for back flow, floats holding. Lost in total 8 m3 OBM to formation.
05:15 - 05:45: Bleed off pressure and checked for back flow, floats holding.
05:45 - 06:00: Flushed manifolds after cement job and prepared for setting seal assembly.
06:00 - 06:15: Attempted to set seal assembly as per vetco procedure.
06:15 - 08:00: Leak on halliburton cement unit, trouble shoot and repaired same.
08:00 - 10:00: Set seal assembly as per vetco procedure. Took 45 ton overpull, closed annular preventer and confirmed seal assembly set. Tested annular BOP against seal assembly 20/345 bar 5/10 min.
10:00 - 12:15: Tested BOP pipe rams to 20 bar/ 5 min and 345 bar/ 10 min as per maersk procedure.
12:15 - 12:30: Opened BOP, released padprt according to vetco procedure.
12:30 - 13:15: L/d cement head. M/u double to landing string. Installed sponge balls and circulated w/ 3500 l/min/ 37 bar.
13:15 - 14:00: POOH from 139 m to surface, cleaned padprt and checked lead impression blocks. L/o tool to cantilever.
14:00 - 14:30: Cleaned and cleared rig floor.
14:30 - 15:15: M/u bullnose, wbrrt and wearbushing. RIH to 139 m and landed WB, took 5 ton overpull.
15:15 - 15:45: Lined up and tested middle pipe ram to 20 bar/ 5 min and 345 bar/ 10 min.
15:45 - 16:30: Released wbrrt with 5 right hand turns, POOH to surface. Cleaned and reset running tool, l/o same.
16:30 - 17:00: Cleaned and cleared rigfloor. Continue reporting on f-99 during maersk rig maintenance/rig survey.
| Circulated prior to cement job and established loss free rate. Cement 10 3/4" x 9 5/8" casing in place, bumped plug. Set and tested seal assembly, tested bops. Installed wear bushing. Suspended operations on f-1 b for maersk rig maintenance/rig survey. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-04, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 09:30 - 09:45: Report continuing from well 15/9-f-99, report performed prejob meeting prior to pick up and make up 8 1/2" bottom hole assembly.
09:45 - 11:15: Picked up and made up 8 1/2" bottom hole assembly to 47m MD.
11:15 - 13:30: Uploaded and iniated testrak and ontrak/copilot.
13:30 - 14:00: Picked up float sub and stabilizer. Washed and cleaned all ports.
14:00 - 15:00: Installed radioactive sources.
15:00 - 16:45: Picked up and made up 8 1/2" bottom hole assembly from 50m to 198m.
16:45 - 17:15: Changed to 5 1/2" handling equipment.
17:15 - 18:45: Ran in hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 198m to 1005m. Average tripping speed 530 m/hr.
18:45 - 19:30: Filled pipe. Performed shallow test of MWD tools.
19:30 - 21:00: Ran in hole with 8 1/2" bottom hole assembly from 1005m to 2013m. Average tripping speed 672 m/hr.
21:00 - 21:15: Filled drillpipe.
21:15 - 22:45: Ran in hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 2013m to 2981m. Average tripping speed 645 m/hr.
22:45 - 23:45: Performed choke drill.
23:45 - 00:00: Established circulation with 1500 LPM, 121 bar and 30 RPM. Washed in hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 2981m to 3027m.
| Picked up and made up 8 1/2" bottom hole assembly. Ran in hole with 8 1/2" bottom hole assembly to 2981m MD. Performed choke drill. Washed in hole with 8 1/2" bottom hole assembly to 3027m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-05, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Washed in hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe with 1500 LPM and 30 RPM from 3027m MD to 3044m MD. Tagged top of cement at 3044m MD with 5mt.
00:15 - 04:00: Established parameters at 2000 LPM, 192-200 bar and 60 RPM. Drilled through top wiper plug from 3044m MD to 3047m MD. Meanwhile increased mud weight from 1. 28 SG to 1. 32 SG.
04:00 - 08:00: Drilled shoetrack and shoe from 3047m MD to 3090m MD with 2000-2200 LPM, 198-206 bar, 60-80 RPM, 7-15 KNM and 5-8mt.
08:00 - 09:15: Drilled and cleaned out rat hole from 3090m MD to 3097m MD in 1m increments.
09:15 - 09:45: Drilled 3 meter of new formation from 3097m MD to 3100m MD with 2300 LPM, 189 bar, 80 RPM, 12-18 KNM, 3-6 MT and 1. 49 SG ECD.
09:45 - 10:45: Circulated and conditioned mud prior to perform fit.
10:45 - 11:00: Flushed lines and performed line test to 200 bar for 10 minutes.
11:00 - 11:30: Performed fit to 1. 60 SG by applying 80 bar down drill string and annulus with 1. 32 SG mud for 10 minutes. Pumped 650 liters, bled 600 liters back.
11:30 - 11:45: Performed slow circulation rates.
11:45 - 00:00: Drilled and oriented 8 1/2" hole from 3100m MD to 3306m MD with 2200 LPM, 201-210 bar, 110-140 RPM, 10-20 KNM, 1. 52-1. 55 SG ECD, 6-10 MT. Drilling ROP 30 m/hr. Average ROP connections) 17 m/hr.
| Drilled out and cleaned shoetrack and rathole to 3097m MD. Drilled 3 meters of new formation to 3100m MD. Performed fit to 1. 60 SG. Drilled and oriented 8 1/2" hole from 3100m MD to 3306m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-06, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:45: Drilled and oriented 8 1/2" hole from 3306m MD to 3343m MD with 2250 LPM, 201-204 bar, 140 RPM, 16-24 KNM, 1. 52-1. 53 SG ECD, 7-8 MT. Drilling ROP 30 m/hr. Average ROP connections) 21. 1 m/hr
01:45 - 02:00: Recycled pumps due to bad survey.
02:00 - 07:15: Drilled and oriented 8 1/2" hole from 3343m MD to 3465m MD with 2250 LPM, 203-206 bar, 140 RPM, 13-22 KNM, 1. 53-1. 55 SG ECD, 7-8 MT. Drilling ROP 30 m/hr. Average ROP connections) 23. 2 m/hr.
07:15 - 07:30: Performed TD survey.
07:30 - 09:45: Circulated hole clean with 2400 LPM, 238-240 bar and 140 RPM.
09:45 - 10:15: Performed flowcheck prior to start perform pressure surveys for 15 minutes well static. Meanwhile performed prejob meeting prior to start performing pressure surveys.
10:15 - 10:45: Downlinked MWD tools.
10:45 - 11:15: Relogged interval from 3462m MD to 3452m MD with 2100 LPM, 190 bar.
11:15 - 12:15: Pulled wet out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 3452m MD to 3365m MD.
12:15 - 12:30: Performed sticky test prior to start pressure surveys.
12:30 - 16:45: Performed pressure surveys with testrak at 3362. 4 m MD 3333. 9 m MD 3328. 4 m MD 3323. 4 m MD 3312. 9 m MD 3305. 9 m MD 3298. 9 m MD 3293. 4 m MD 3287. 4 m MD 3279. 4 m MD
16:45 - 19:00: Relogged interval from 3253 3214m MD with 2200 LPM, 187 bar and 60 RPM.
19:00 - 19:15: Performed flowcheck prior to start pulling out of hole with 8 1/2" bottom hole assembly in open hole for 15 minutes well static.
19:15 - 20:00: Pumped slug and dropped 3" drift.
20:00 - 20:45: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 3237m MD to 3090m MD at 240 sec/stand.
20:45 - 21:00: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 3090m MD to 2985m MD at 210 sec/stand.
21:00 - 21:15: Performed free torque readings for liner hanger reference.
21:15 - 21:30: Performed flow check prior to pull out of hole with 8 1/2" bottom hole assembly in cased hole for 15 minutes well static.
21:30 - 22:00: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 2985m MD to 2750m MD at 210 sec/stand.
22:00 - 23:00: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 2750m MD to 2400m MD at 180 sec/stand.
23:00 - 00:00: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 2400m MD to 1926m MD at 120 sec/stand.
| Drilled and oriented 8 1/2" hole from 3306m MD to 3465m MD. Circulated hole clean. Performed pressure surveys with testrak. Pulled out of hole with 8 1/2" bottom hole assembly to 1926m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-07, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 1926m MD to 1600m MD at 1. 5 min/stand. Average pulling speed 600 m/hr
00:30 - 02:30: Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 1600m MD to 386m MD at 1 min/stand. Average pulling speed 620 m/hr
02:30 - 02:45: Performed flowcheck prior to pull bottom hole assembly through BOP for 15 minutes well static. Meanwhlie performed prejob meeting prior to brake out and lay down 8 1/2" bottom hole assembly.
02:45 - 06:30: Pulled out and laid down 8 1/2" bottom hole assembly to 47m MD. Removed radioactive sources.
06:30 - 08:00: Downloaded MWD tools.
08:00 - 09:00: Pulled out and laid down 8 1/2" bottom hole assembly from 47m MD to deck.
09:00 - 10:00: Removed excess equipment from drill floor. Cleaned and cleared rig floor.
10:00 - 10:15: Performed prejob meeting prior to rig up to run 7" liner.
10:15 - 11:45: Rigged up to run 7" liner.
11:45 - 12:45: Moved rollers and connected hydraulic power. Meanwhile serviced travelling block and dolly.
12:45 - 13:00: Performed prejob meeting prior to run 7" liner.
13:00 - 16:00: Picked up and made up FMS. Picked up shoe to rotary. Verified floats by hosing water through it. Picked up and made up 3 x intermediate joints and landing collar pup to 60m MD. Crane used for picking up shoe track joints due to hydraulic leak on catwalk.
16:00 - 19:30: Ran 7" liner from 60m MD to 334m MD. Filled liner every 5th joint.
19:30 - 20:15: Experienced problems with casing tong guide arm. Not possible to retract due to faulty shuttle valve. Attempted to repair shuttle valve no go. Continued in manual mode.
20:15 - 22:00: Ran 7" liner from 334m MD to 474m MD. Filled liner every 5th joint.
22:00 - 22:15: Changed handling equipment and removed power rollers. Meanwhile performed prejob meeting prior to pick up and make up 7" liner hanger assembly.
22:15 - 00:00: Broke out and laid down fill up crossover. Picked up 7" liner hanger assembly. Made up and installed ball seat and wiper plugs.
| Pulled out of hole with 8 1/2" bottom hole assembly on 5 1/2" drill pipe from 1926m MD, and laid down same to deck. Rigged up to run 7" casing. Ran 7" liner to 474m MD. Picked up and made up 7" liner hanger assembly. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-08, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:45: Continued making up 7" liner hanger assembly.
01:45 - 02:30: Ran in hole with 7" liner on 5 1/2" heavy weight drill pipe from 474m MD to 688m MD. Average trip speed 285 m/hr.
02:30 - 02:45: Filled pipe.
02:45 - 09:30: Ran in hole with 7" liner on 5 1/2" drill pipe from 688m MD to 3090m MD. Average trip speed 356 m/hr. Filled running string every 5th stand.
09:30 - 10:00: Made up top drive and circulated one liner volume with 800 LPM and 42 bar. Performed up/down weight measurements.
10:00 - 11:45: Ran in hole with 7" liner on 5 1/2" bottom hole assembly from 3090m MD to 3435m MD. Average trip speed 230 m/hr. Filled running string every 5th stand.
11:45 - 12:15: Established circulation with 400 LPM and 32 bar. Washed down last stand from 3435m MD to 3465m MD. Tagged bottom at 3465 with 5mt. Laid out one single 5 1/2" drill pipe.
12:15 - 12:30: Performed prejob meeting prior to pick up and make up cement head.
12:30 - 13:30: Picked up and made up one 3m pup and cement head.
13:30 - 14:30: Established circulation with 1200 LPM and 86 bar. Washed in hole with 7" liner on 5 1/2" drill pipe and cement stand and tagged TD at 3465m MD. Pulled up 1. 5m to setting depth. Circulated 2 x open hole volume.
14:30 - 16:00: Established rotation with 20 RPM and circulated bottoms up with 1200 LPM and 87 bar. Meanwhile performed prejob meeting prior to set liner hanger and cement job.
16:00 - 17:15: Stopped rotation and flow. Dropped ball and chased same with 500 LPM and 34 bar. Observed landing by pressure increase. Pressured up to 170 bar to set liner hanger. Confirmed liner set by slacking off 30mt.
17:15 - 17:30: Applied 10mt weight on liner hanger. Released liner hanger running tool by rotating clockwise. Confirmed liner hanger running tool released by torque indications.
17:30 - 18:00: Pumped 10m3 1. 32 SG oil based mud at 1500 LPM and 115 bar. Lined up and pumped 15m3 1. 38 SG spacer with rig pumps. Closed IBOP and applied 30 bar pressure.
18:00 - 18:45: Mixed and pumped 11. 2m3 1. 90 SG cement slurry. Displaced cement line to drill floor with drill water.
18:45 - 19:30: Lined up to mud pumps down string. Displaced cement with 41m3 1. 32 SG oil based mud. Bumped the plug with 95. 3 effeciency at 100 bar final circulating pressure. Pressured up to 170 bar.
19:30 - 20:15: Lined up to pump down string with cement unit and closed IBOP. Pressured up to 170 bar to equalize lo-torque. Pressure tested liner to 340 bar for 10 minutes. Observed pressure increase from 340 bar to 345 bar in 10 minutes. Bled off pressure to 5 bar and observed for pressure build up. Pumped a total of 290 liters, bled 300 liters back. Observed pressure build up from 5 bar to 10 bar in 10 minutes OK. Disconnected lo-torque valve and observed for back flow no back flow.
20:15 - 21:00: Pulled up 4. 5m to activate packer actorators. Ran in hole to apply weight to set packer. Attempted to apply 40mt weight to set packer. Observed shear at 14mt and 24mt weight. No additional weight increase was oberved. Pulled back to re-activate actorators. Attempted to apply 40mt weight to packer no go. Pulled back and rotated string at 20 RPM. Ran in hole to set packer with 40mt OK. Held 40mt on packer in 5 minutes. Slacked off weight.
21:00 - 21:45: Closed upper pipe ram and lined up to pump with cement unit down annulus. Pressure tested packer to 340 for 10 minutes OK. Pumped a total of 1780 liters, bled back same.
21:45 - 22:30: Opened upper pipe ram. Applied 30 bar on string and pulled out of hole 5m to release hanger no pressure release observed. Pulled additional 2 meters no pressure release observed. Bled off pressure and functioned IBOP close and open and applied 30 bar to string observed running tool free from PBR.
22:30 - 00:00: Increased flow to 2000 LPM and 128 bar. Ran in hole 2 meters to top of PBR. Circulated out excess cement at 2000 LPM and 128 bar.
| Picked up and made up 7" liner hanger assembly. Ran in hole with 7" liner from 474m MD to 3463. 5m MD. Set and cemented liner hanger. Pressure tested liner to 340 bar for 10 minutes. Set liner packer. Pressure tested liner packer to 340 bar for 10 minutes. Released liner hanger running tool and circulated out excess cement. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-09, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Continued circulating out spacer and excess cement at 2000 LPM and 183 bar. Diverted 20m3 spacer and excess cement to slop.
00:30 - 02:00: Broke out cement head, 3 meter pup and 2 drill pipe singles. Laid down same to deck. Inserted 2 x wiper balls and circulated same through string.
02:00 - 07:00: Pumped slug. Pulled out of hole with liner hanger running tool on 5 1/2" drill pipe from 2970m MD to 230m MD.
07:00 - 07:15: Performed prejob meeting prior to pull out of hole with liner hanger running tool.
07:15 - 07:30: Removed ps21 slips and installed master bushings.
07:30 - 07:45: Pulled out of hole with liner hanger running tool on 5 1/2" drill pipe and 5 1/2" heavt weight drill pipe from 230m MD to 24m MD.
07:45 - 08:45: Pulled out of hole and laid down liner hanger running tool to deck.
08:45 - 09:30: Cleaned and tidied rig floor.
09:30 - 10:30: Performed BOP function test.
10:30 - 11:15: Picked up and made up jetting sub and ran in hole to 15m MD. Jetted BOP with 3000 LPM.
11:15 - 11:45: Changed handling equipment.
11:45 - 12:15: Picked up and made up cleanout assembly.
12:15 - 13:00: Moved power rollers. Installed 3 1/2" auto slips and dog collar.
13:00 - 13:15: Performed prejob meeting prior to pick up and make up 3 1/2" drill pipe from deck.
13:15 - 17:15: Ran in hole with cleanout assembly on 3 1/2" drill pipe to 404m MD. Average trip speed 101 m/hr.
17:15 - 17:30: Changed to 5 1/2" handling equipment.
17:30 - 18:45: Picked up and made up well commisioner assembly, circulating sub and well patroler assembly.
18:45 - 19:00: Installed PS 21 slips.
19:00 - 19:15: Performed prejob meeting prior to run in hole with cleanout assembly.
19:15 - 20:30: Ran in hole with cleanout assembly from 404m MD to 1040m MD 5/8" scraper at 600m MD).
20:30 - 21:45: Established circulation with 1500 LPM, 58 bar and 40 RPM and scraped and cleaned area from 592m MD to 623m MD.
21:45 - 00:00: Ran in hole with cleanout assembly from 1040m MD to 2163m MD.
| Circulated out excess spacer and cement. Pulled out of hole with liner hanger running tool and laid down same. Picked up and made up cleanout assembly and ran in hole to 2163m MD. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-10, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:15: Ran in hole with cleanout assembly from 2163m MD to 2822m MD.
01:15 - 01:45: Picked up and made up 10 3/4" scraper and drift assembly.
01:45 - 02:15: Ran in hole with cleanout assembly from 2779m MD to 2961m MD at 139m MD), established circulation with 1200 LPM, 25 bar and 20 RPM. Attempted to drift casing no go. Observed weight dropped 80mt.
02:15 - 03:15: Stopped rotation. Attempted to pass restriction with up to 50mt several times no go.
03:15 - 04:15: Pulled out of hole with cleanout assembly on 5 1/2" drill pipe from 2961m MD to 2822m MD.
04:15 - 06:45: Prepared to break out and lay down 9. 5" drift from cleanout assembly. Broke out 9. 5" drift and laid out same.
06:45 - 07:45: Ran in hole with cleanout assemblyfrom 2822m MD to 2978m MD OK.
07:45 - 08:15: Ran in hole with cleanout assembly from 2978m MD to 3017m MD.
08:15 - 08:30: Removed master bushings and installed ps21 slips.
08:30 - 10:15: Ran in hole with cleanout assembly from 3017m MD to 3354m MD.
10:15 - 11:30: Made up top drive and filled pipe. Established circulation with 1000 LPM, 81 bar and 40 RPM. Scraped and cleaned production packer setting depth from 2934m MD to 2964m MD.
11:30 - 12:00: Continued washing down with cleanout assembly from 3400m MD to 3410m MD and landed polish mill in PBR at 2978m MD. Cleaned and polished PBR with 2000 LPM, 95 bar and 40 RPM.
12:00 - 12:45: Circulated and conditioned liner volume with 1. 32 SG oil based mud with 2000 LPM and 250 bar.
12:45 - 15:30: Sheared out pins in circulation sub with 15mt. Verified ports open. Circulated and conditioned casing and riser volume with 3500 LPM, 250 bar and 90 RPM.
15:30 - 16:30: Cycled circulating tool to closed position. Ran in hole and landed on top of PBR. Cycled circulation tool to locked closed position. Pressure tested well commissioner element to 70 bar for 10 minutes OK. Cycled well commissioner to open position.
16:30 - 18:30: Displaced drill string with 22. 5m3 base oil. Observed back pressure of 93 bar. Activated well commissioner packer.
18:30 - 19:00: Took thermal expansion reference trend by observing pressure for 30 minutes pressure increased from 93 bar to 110 bar in 30 minutes.
19:00 - 19:15: Performed toolbox talk prior to perform inflow test.
19:15 - 19:45: Lined up to cement unit and pressured up lined to equalize backpressure in standpipe to 110 bar. Opened lo-torque valve to cement unit.
19:45 - 20:45: Performed inflow test in steps of 30 bar from 93 bar to 5 bar. Observed pressure for 30 minutes. Pressure increased 2 bar in 30 minutes. Meanwhile performed prejob meeting prior to displace well to 1. 03 SG brine.
20:45 - 22:00: Pressured up string to 100 bar to equalize pressure differential on well commissioner packer. Deactivated well commissioner packer and pulled polish mill 8 m, out of PBR while rotating with 10 RPM.
22:00 - 00:00: Pumped wash-train 15 m3 push pill, 39 m3 cleaning pill, 1 x hole volume packer fluid. Displaced well to 1. 03 SG brine with 1700 LPM and 160 bar.
| Ran in hole with cleanout assembly from 2163m MD to 2822m MD. Ran in hole with cleanout assembly without 9. 5" drift from 2822m MD to 3354m MD. Scraped and cleaned production packer setting area and polished PBR. Circulated and conditioned mud. Performed inflow test. Displaced well to 1. 03 SG brine. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-11, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:30: Continued displacing well to 1. 03 SG brine. Observed large amounts of foam in flowline.
01:30 - 01:45: Prepared to perform pressure test. Lined up to cement unit and pressured up same to 20 bar. Opened lo-torque and verified pressure drop.
01:45 - 02:30: Pressure tested well to 345 bar for 10 minutes OK. Pumped a total of 1700 liters, bled 1700 liters back.
02:30 - 03:00: Performed flowcheck for 30 minutes with 1. 03 SG brine well static.
03:00 - 08:30: Pulled out of hole with cleanout assembly on 5 1/2" drill pipe from 3402m MD to 1042m MD.
08:30 - 08:45: Observed hole not taking correct volume of mud while tripping out performed flowcheck for 15 minutes with 1. 03 SG brine well static.
08:45 - 09:00: Pumped 10m3 1. 03 SG brine at 1800 LPM, 64 bar and 90 RPM.
09:00 - 09:30: Performed flowcheck for 30 minutes with 1. 03 SG brine well static.
09:30 - 11:30: Pulled out of hole with cleanout assembly on 5 1/2" drill pipe from 1042m MD to 464m MD.
11:30 - 11:45: Performed flowcheck for 15 minutes with 1. 03 SG prior to pull cleanout assembly through BOP well static.
11:45 - 12:30: Laid down cleanout assembly, magnet, circulation sub and well commissioner.
12:30 - 13:00: Changed to 3 1/2" handling equipment.
13:00 - 14:00: Pulled out of hole with cleanout assembly on 3 1/2" drill pipe from 420m MD to 220m MD. Laid 3 1/2" drill pipe singles out to cantilever.
14:00 - 15:00: Calibrated HTS arm.
15:00 - 17:30: Pulled out of hole with cleanout assembly on 3 1/2" drill pipe from 420m MD to 10m. Laid 3 1/2" drill pipe singles out to cantilever.
17:30 - 17:45: Laid down cleanout assembly to deck.
17:45 - 18:00: Changed to 5 1/2" handling equipment.
18:00 - 18:30: Picked up and made up 9. 5" drift and crossover. Installed ps21 slips.
18:30 - 19:00: Ran in hole with 9. 5" drift to 139m MD. Attempted to enter 10 3/4" casing with 9. 5" drift no go. Observed 4mt weight. Rotated pipe 1/2 turn and attempted to enter 10 3/4" casing no go.
19:00 - 19:30: Pulled out of hole with 9. 5" drift on 5 1/2" drill pipe from 139m MD.
19:30 - 20:00: Broke out drift assembly and crossover. Laid out same to cantilever.
20:00 - 21:45: Picked up and made up well protector assembly and crossover. Made up 4 stands 5 1/2" drill pipe and magnetosweep, jetting sub and crossover. Ran in hole with cleanout assembly on 5 1/2" drill pipe to 312m MD jet at 139m MD).
21:45 - 22:30: Spaced out and shut well in on middle pipe ram. Displaced choke manifold and poorboy to seawater.
22:30 - 23:15: Displaced riser to seawater at 1500 LPM.
23:15 - 00:00: Jetted riser with seawater from 139m MD to 85m MD.
| Displaced well to 1. 03 SG brine. Pressure tested well to 345 bar with 1. 03 SG brine. Pulled out of hole with cleanout assembly from 3402m MD. Laid down same to deck. Attempted to enter casing with 9. 5" drift no go. Displaced riser to seawater. Jetted riser and BOP. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-12, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:45: Jetted BOP and riser from 139m MD to 15m MD.
00:45 - 01:15: Broke out and laid down magnetosweep, jetting sub and crossover to cantilever.
01:15 - 02:15: Pulled out of hole with well protector and crossover on 5 1/2" drill pipe from 173m MD. Broke out well protector and crossover and laid down same to cantilever.
02:15 - 02:45: Picked up and made up safelock plug.
02:45 - 03:15: Ran in hole with safelock plug on 5 1/2" heavy weight drill pipe to 120m MD.
03:15 - 05:00: Ran in hole with safelock plug on 5 1/2" drill pipe from 120m MD to 607m MD.
05:00 - 05:15: Performed prejob meeting prior to set safelock plug.
05:15 - 05:30: Established circulation with 1100 LPM and washed setting area from 605m MD to 609m MD.
05:45 - 06:15: Set safelock plug by rotating 20 turns clockwise and applying 20mtweight for 5 minutes. Verified plug set by pulling 10mt overpull.
06:15 - 06:30: Lined up to cement unit. Pressured up to 30 bar with cement unit by pumping 100 liters of seawater. Volume used indicated open ball valve. Bled down pressure.
06:30 - 07:15: Set down 2mt weight on safelock plug and applied 6knm torque to shear and close ball valve. Pressured up string to 30 bar using rig pumps. Rotated 1/2 turn clockwise and observed pressure drop.
07:00 - 07:45: Pressure tested safelock plug from below to 345 bar for 10 minutes OK. Pumped 1471 liters, bled 1463 liters back.
07:45 - 08:00: Closed ball valve by rotating 1/2 turn anti-clockwise. Verified ball valve closed by pressuring string up to 345 bar and comparing volumes OK. Released safelock running tool.
08:00 - 08:15: Spotted 5m3 high visc pill on top of safelock plug and displaced same with 2000 LPM, 12 bar and 40rpm.
08:15 - 09:00: Pulled out of hole with safelock running tool on 5 1/2" drill pipe from 607m MD to 140m MD.
09:00 - 09:30: Displaced riser and BOP to seawater with 2200 LPM and 10 bar.
09:30 - 10:00: Pulled out of hole with safelock running tool on 5 1/2" drill pipe from 140m MD. Laid out safelock running tool to cantilever.
10:00 - 10:30: Closed shear ram. Pressure tested safelock plug from above to 345 bar for 10 minutes. Pumped 723 liter, bled 723 liters back.
10:30 - 10:45: Cleaned and tidied rig floor.
10:45 - 11:00: Picked up and made up wearbushing retrieval tool and jet sub to 5 1/2" heavy weight drill pipe.
11:00 - 11:15: Ran in hole with wearbushing retrieval tool and jet sub to 139m MD. Jetted wellhead area with 1400 LPM and 8 bar.
11:15 - 12:00: Landed off with wearbushing retrieval tool with 5mt weight. Picked wearbushing free with 39mt overpull.
12:00 - 13:00: Pulled out of hole with wearbushing from 139m MD. Laid out wearbushing to cantilever. Broke out and laid down wearbushing running tool to cantilever. Inspected wearbushing and found id to 9. 5".
13:00 - 13:15: Picked up and made up 9. 5" drift and crossover to 5 1/2" drill pipe.
13:15 - 14:30: Ran in hole with 9. 5" drift on 5 1/2" drill pipe to 575m MD OK.
14:30 - 15:30: Pulled out of hole with 9. 5" drift on 5 1/2" drill pipe from 575m MD. Laid out same to cantilever.
15:30 - 15:45: Picked up and made up lockdown sub.
15:45 - 16:45: Ran in hole with lockdown sub on heavy weight drill pipe to 139m MD. Installed lockdown sub by landing off with 7mt and rotating 4 1/2 turns clockwise. Observed drop to verify installed lock down assembly.
16:45 - 17:15: Pressure tested lockdown sub to 207 bar for 10 minutes OK. Pumped 262 liters, bled 260 liters back.
17:15 - 17:30: Applied 30mt overpull OK. Rotated 5 turns clockwise to release running tool.
17:30 - 18:00: Pulled out of hole with lockdown assembly running tool from 139m MD, and laid down same to cantilever.
18:00 - 19:00: Bled down koomey-unit and prepared to pull diverter. Meanwhile performed general maintanence.
19:00 - 19:15: Performed prejob meeting prior to pull diverter element and slick joint.
19:15 - 21:00: Pulled master bushings and outer ring and installed lift eyes to diverter. Pulled diverter and landed on set back.
21:00 - 22:45: Pulled slick joint and landed in set back. Installed master bushings and ring.
22:45 - 23:00: Performed prejob meeting prior to nipple down BOP.
23:00 - 00:00: Nippled down BOP.
| Jetted BOP and riser with seawater. Installed safelock plug at 607m MD. Pressure tested safelock plug to 345 bar from below and above. Pulled 10 3/4" wearbushing. Performed 9. 5" drift run to 575m MD. Installed lockdown assembly. Nippled down diverter, slick joint and moved BOP to carrier. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-13, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 01:30: Continued nippling down BOP and placed back on carrier.
01:30 - 01:45: Performed prejob meeting prior to rigging up to pull high pressure drilling riser.
01:45 - 07:00: Rigged up to pull high pressure drilling riser. Picked up and made up claxton tool to 5 1/2" drill pipe. Landed off claxton tool to NT-2 connector. Verified make up by applying 5mt overpull.
07:00 - 07:15: Performed prejob meeting prior to rig down tensioning system.
07:15 - 12:30: Rigged down tension cylinders and tension ring. Rigged up sheaves for running guide wires. Meanwhile prepared 24" elevator, c-plate and bails on rig floor.
12:30 - 14:30: Ran guide wire on tugger to seabed. ROV attached same.
14:30 - 15:00: Ran hot stab to seabed and installed same in tieback connector with ROV.
15:00 - 16:30: Pressured up hot stab connection to 3000 psi. Unlatched tieback connector and picked riser off wellhead.
16:30 - 16:45: Retrieved hotstab and reinstalled dummy stab.
16:45 - 17:15: Picked up clear of wellhead and retrieved VX gasket with ROV. Installed debris cap on wellhead.
17:15 - 17:30: Performed prejob meeting prior to pull out of hole with riser.
17:30 - 18:15: Pulled up with tieback connector and high pressure drilling riser. Racked back 5 1/2" drill pipe stand. Removed crossover.
18:15 - 19:00: Removed master bushings and outer ring. Prepared to install riser spider and hydraulic hoses.
19:00 - 19:15: Performed prejob meeting prior to install riser spider.
19:15 - 20:15: Installed riser spider and function tested same.
20:15 - 20:30: Performed prejob meeting prior to pull high pressure drilling riser out of hole and lay out same to cantilever.
20:30 - 21:00: Picked up BOP joint and closed spider dogs. Installed c-plate and side door elevator onto spider. Landed off BOP joint in side door elevator on top of spider.
21:00 - 22:15: Disconnected BOP joint. Laid out BOP joint and claxton tool to cantilever.
22:15 - 23:15: Removed BX-ELEVATOR and attached bails to side door elevator. Picked up tension joint and set in spider.
23:15 - 00:00: Disconnected tension joint and laid out same to cantilever.
| Nippled down BOP and riser. Rigged down tensioning cylinders and tension ring. Rigged up to pull high pressure drilling riser. Pulled BOP joint and stress joint out of hole and laid out same to deck. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-14, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:00: Pulled double riser joint pup and splash zone joint). Disconnected same and laid out to cantilever.
03:00 - 04:30: Pulled double riser joint joint and Disconnected same and laid out to cantilever.
04:30 - 07:00: Pulled single joint Disconnected same and laid out to cantilever.
07:00 - 09:00: Retrieved guidelines from seabed.
09:00 - 10:30: Pulled single joint Disconnected same and laid out to cantilever.
10:30 - 12:00: Pulled lower riser pup joint. Disconnected same and laid out to cantilever.
12:00 - 12:45: Laid out stress joint and tieback connector to cantilever.
12:45 - 13:30: Transferred tension rings and wellhead equipment to rig floor.
13:30 - 00:00: Waited on weather. Meanwhile performed general maintenance. Serviced forward and aft pipe racking systems.
| Retrieved high pressure drilling riser. Waited on weather. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-15, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:00: Waited for weather. Time significant waveheight wind speed 00 00 1. 7 m 8. 0 kt 06 00 1. 4 m 23. 0 kt 12 00 4. 2 m 34. 0 kt 18 00 5. 0 m 21. 0 kt 24 00 3. 2 m 17. 0 kt meanwhile performed general maintenance. Split tension ring. Moved tension ring to moon pool. Installed tension ring. Performed 5 year choke manifold service. Installed top cover onto f-1 split hatch. Greased and inspected top drive and travelling block. Housekeeping.
| Waited on weather for running production riser. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-16, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:00: Waited for weather for running production riser. Time significant waveheight wind speed 00 00 3. 2 m 17. 0 kt 06 00 2. 9 m 8. 0 kt 12 00 2. 3 m 15. 0 kt 18 00 1. 9 m 16. 0 kt 24 00 3. 6 m 22. 0 kt meanwhile performed general maintenance. Continued performing 5 year choke manifold service. Cleaned pits. Lifted wing valves for multibowl to rig floor. Lowered same through rotary. Changed bladders on koomey bottles. Pressure tested BOP on stump to 345 bar. Housekeeping.
| Waited on weather for running production riser. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-17, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:00: Waiting on weather for running production riser. Time significant waveheight wind speed 00 00 3. 6 m 22. 0 kt 06 00 3. 6 m 24. 0 kt 12 00 3. 5 m 22. 0 kt 18 00 2. 8 m 18. 0 kt 24 00 2. 6 m 13. 0 kt meanwhile changed out wires on moonpool tuggers. Changed oil cooler on top drive. Greased manifolds. Performed drive chain check on mud pump Performed general mainenance.
| Waited on weather for running production riser. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-18, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 11:00: Waiting on weather. Time significant waveheight wind speed 00 00 2,5 m 14. 0 kt 06 00 2,2 m 9. 0 kt at 09 40 hrs commenced shut down of production. At 11 00 hrs production shut down completed. Meanwhile pressure tested kill and choke manifold, standpipe manifold, upper and lower ibops. Performed general maintenance and housekeeping. Troubleshot leak on TDS oil cooler, repaired same. Prepared riser guide funnel on deck.
11:00 - 11:15: Performed pre-job meeting prior to run riser guide funnel.
11:15 - 13:45: Installed riser guide funnel on wellhead.
13:45 - 15:00: Waited on the crane handling supply vessel. Meanwhile performed general maintenance and housekeeping.
15:00 - 15:15: Performed pre-job meeting prior to removal of split hatch.
15:15 - 16:15: Removed split hatch. Meanwhile ROV installed VX ring. Performed pre-job meeting prior to make up landing string
16:15 - 17:00: Installed lifting nubbing onto riser tension joint on deck.
17:00 - 17:15: Performed pre-job meeting prior to run riser.
17:15 - 20:15: Picked up tieback connector and stress joint and landed same in rotary. Picked up and made up riser pup joint to stress joint. Installed fairings. Lowered production riser through rotary to test connector.
20:15 - 21:30: Function tested tieback connector.
21:30 - 23:45: Picked up standard riser joint made up to riser pup joint. Pressure tested flange connection.
23:45 - 00:00: Installed flange protection fairings.
| Waited on weather. Ran production riser. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-19, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Installed guide wires and ROV hooks.
00:15 - 01:45: Picked up standard riser joint and made up to riser joint Inspected seal faces and installed IX-14 ring gasket. Made up flange connection with bolt tensioner. Pressure tested flange connection to 3000 psi through test port, OK. Installed fairings.
01:45 - 02:15: Ran guideline wires to seabed and attached same to template.
02:15 - 10:00: Waiting on weather. Time significant waveheight wind speed 03 00 2,5 m 22,0 kt 06 00 2,2 m 16,0 kt 09 00 2,1 m 10,0 kt meanwhile performing planned maintenance and housekeeping. Replaced faulty fingers in DP fingerboard. Performed pre-job meeting prior to run production riser.
10:00 - 12:00: Picked up standard riser joint and made up to riser joint Inspected seal faces and installed IX-14 ring gasket. Made up flange connection with bolt tensioner. Pressure tested flange connection to 3000 psi through test port, OK. Held pre-job meeting prior to run through splash zone. Lowered riser through splash zone and sat in riser spider. Installed fairings.
12:00 - 13:30: Picked up standard riser joint and made up to riser joint Inspected seal faces and installed IX-14 ring gasket. Made up flange connection with bolt tensioner. Pressure tested flange connection to 3000 psi through test port, OK. Lowered riser and sat in riser spider. Installed fairings.
13:30 - 14:45: Picked up riser splash zone joint and made up to riser joint Inspected seal faces and installed IX-14 ring gasket. Made up flange connection with bolt tensioner. Pressure tested flange connection to 3000 psi through test port, OK. Lowered riser and sat in riser spider. Installed fairings.
14:45 - 16:00: Picked up upper riser pup joint and made up to riser splash zone joint. Inspected seal faces and installed IX-14 ring gasket. Made up flange connection with bolt tensioner. Pressure tested flange connection to 3000 psi through test port, OK. Lowered riser and sat in riser spider. Installed fairings.
16:00 - 18:15: Picked up riser tension joint and made up to splash zone joint. Inspected seal faces and installed IX-14 ring gasket. Made up flange connection with bolt tensioner. Pressure tested flange connection to 3000 psi through test port, OK. Lowered riser and sat in riser spider. Installed fairings.
18:15 - 18:30: Disconnected riser running tool from riser tension joint and cleaned seal face.
18:30 - 19:00: Picked up pre-made landing string.
19:00 - 19:15: Performed pre-job meeting with oncoming crews.
19:15 - 20:00: Made up pre-made riser running tool to tension joint.
20:00 - 20:15: Held pre-job meeting prior to landing production riser.
20:15 - 20:30: Made up TDS to riser running tool and removed hang off plates.
20:30 - 22:00: Lowered riser to safe distance above riser landing guide funnel. Verified VGX ring installed with ROV. Stabbed riser into vertical guide and onto WH.
22:00 - 00:00: Removed riser guide funnel.
| Ran production riser. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-20, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Continued to remove riser guide funnel.
00:30 - 01:15: Lowered hot stab and connected same to tieback connector using ROV.
01:15 - 02:30: Landed off tieback connector on wellhead with 15 ton. Locked connector by applying 3000 psi until stroke indicator indicated fully set.
02:30 - 02:45: Performed 10 ton overpull test to verify connector fully latched.
02:45 - 04:15: Recovered riser guide funnel to deck. Att 04 15 hrs started production as per simops procedure. Meanwhile removed riser spider from rotary. Filled riser. Confirmed line up from cement unit and tested lines to 20 200 bar 5 10 min.
04:15 - 05:30: Pressure tested production riser to 20 200 bar 5 10 min. Pumped 670 liter. Took 650 liter return.
05:30 - 06:15: Flushed tieback connector control lines. Sat all valves to parking position. Recovered hot stab.
06:15 - 08:00: Retrived guide line wires to surface.
08:00 - 14:30: Installed riser centralizers, tension ring and tension cylinders.
14:30 - 16:45: Performed pre-job meeting. Performed 3d survey to verify correct cutting height of production riser.
16:45 - 00:00: Waited on parts for cutting tool. Meanwhile performed planned maintenance and housekeeping. Moved multi bowl to drill floor. Transferred x-mass tree from deck to moonpool.
| Landed production riser. Pressure tested production riser. Installed riser tension system. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-21, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:45: Waited on parts for cutting tool. Meanwhile performed planned maintenance and housekeeping.
03:45 - 04:45: Cut production riser.
04:45 - 05:15: Pulled cut off piece to drill floor and laid out same.
05:15 - 08:45: Bewelled production riser edge. Meanwhile picked up BOP riser joint and claxton tool.
08:45 - 09:15: Picked up multibowl and landed at well center and made up same to BOP joint. Performed pickup test to 15 cm above deck,ok.
09:15 - 09:30: Performed pre-job meeting. Informed production to shut down well f11 f12.
09:30 - 10:00: Prepared to remove master bushings and cover from split hatch while production shuts down.
10:00 - 12:15: Removed master bushings and cover from split hatch. Ran multi bowl and BOP joint assembly through rotary. Installed master bushings. Picked up single and ran in with multibowl assembly. Removed master bushings. Retrached TDS to align multibowl. Landed out multibowl.
12:15 - 14:30: Tested multibowl BT and FS seals. Energized plastic in upper and lower BT seals and tested same.
14:30 - 15:00: Energized multibowl slips. Performed 5 ton overpull test, OK.
15:00 - 15:30: Installed hatches around production riser.
15:30 - 17:15: Erected scaffolding around claxton tool in moonpool. Meanwhile made up annulus valves on multibowl. Tested annulus valves to 30 345 bar 5 10 minutes. Replaced damaged fitting on claxton tool.
17:15 - 19:45: Released claxton tool. Pulled out with claxton tool and laid down same to cantilever. At 19 00 informed production to shut down well f14.
19:45 - 00:00: Performed pre-job meeting. Moved BOP to well center and landed same onto riser. Made up nt2 connector. Ran slick joint and made up same. Installed diverter. Connected tension system. At 21 15 informed production to start.
| Cut production riser. Installed multi bowl and surface riser. Nippled up BOP |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-22, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:30: Connected tension system. Meanwhile rigged down diverter handling equipment.
00:30 - 01:00: Filled riser with seawater.
01:00 - 02:00: Picked up bowl protector RT and made up to 5 1/2" DP. RIH and installed bowl protector at 20,53 meter. POOH with RT.
02:00 - 04:00: Picked up jetting sub and RIH on 5 1/2" DP to 150 meter. Closed upper pipe ram. Pumped seawater at 550 liter/min through choke and kill lines until clean returns observed. Opened upper pipe ram. Pumped 14 m3 hi-vis pill at 2000 liter/min, 5 bar and chased same with 3,5 m3 seawater. RIH to 162 meter and circulated with seawater at 3000 liter/min, 25 bar, 5 RPM. POOH with jetting sub.
04:00 - 07:30: Picked up and RIH with annulus insert retrieval tool. Engaged annulus insert at 139,95 meter. Released annulus insert with 6000 NM. Displaced riser to brine. POOH with annulus insert retrieval tool and insert, laid down same.
07:30 - 07:45: Performed pre-job meeting.
07:45 - 08:45: RIH with bowl protector retrieval tool and retrieved bowl protector. POOH with bowl protector and RT.
08:45 - 09:00: Cleaned and cleared drill floor.
09:00 - 09:15: Performed pre-job meeting prior to rig up handlling equipment.
09:15 - 12:15: Rigged up 10 3/4" handling equipment for tie-back casing.
12:15 - 12:30: Performed pre-job meeting prior to run tie-back connector.
12:30 - 15:30: Picked up 10 3/4" tie-back connector, inspected same, OK. Picked up and RIH with 10 3/4" tie-back string as per running tally from surface to 119,34 meter.
15:30 - 16:00: Picked up 10 3/4" surface casing hanger assembly with adjustment sub and continued to RIH.
16:00 - 16:15: Tagged land off point with 3 ton. Landed off tie-back string at 139,88 meters.
16:15 - 16:30: Rotated string to engage threads in tie-back adapter.
16:30 - 16:45: Released riser RT and POOH with same. Meanwhile drained riser.
16:45 - 18:00: Performed pre-job meeting prior to rig down handling equipment. Rigged down handling equipment for 10 3/4" tie-back casing and cleared drill floor. Rigged up 5 1/2" handling equipment.
18:00 - 19:45: Picked up and made up tie-back torque tool. RIH with tie-back connector torque tool on 5 1/2" DP. Landed and engaged torque tool in tie-back adapter at 139,55 meter and sat down 3 ton. Made up tie-back connector to 9500 NM. POOH with tie-back connector torque tool on 5 1/2" DP.
19:45 - 20:30: Rigged 10 3/4" handling equipment for tie-back casing. Performed pre-job meeting.
20:30 - 21:30: Picked up casing hanger landing string and RIH to top of casing hanger at 20,5 meter. Engaged same.
21:30 - 22:45: Rigged up swedge and hose for tie-back adapter test. Flushed lines and tested lines to 345 bar 5 minutes. Pressure tested tie-back adapter to 20 345 bar 5 10 minutes. Observed b annulus at multibowl. Pumped 486 liter, bled back 486 liter. Rigged down swedge and hose.
22:45 - 23:15: Changed to 5 1/2" DP handling equipment.
23:15 - 00:00: Picked up adjustable sub setting tool and RIH to 28,3 meter.
| Nippled up BOP. Recovered annulus insert. Ran 10 3/4" surface tieback casing and hanger. Pressure tested tie-back adapter. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-23, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Applied 140 bar to adjustable sub setting tool, picked up to 1 ton overpull and bleed off pressure. Turned string 14 turns with 5 RPM, 200-1500 NM. No drop observed on casing.
00:15 - 00:45: Repositioned string at 28,3 meter. Applied 150 bar, picked up to 1 ton and bled off pressure. Turned string 14 turns with 5 RPM, 200-1500 NM. No drop observed on casing.
00:45 - 01:30: POOH with adjustable sub setting tool and inspected same, OK.
01:30 - 01:45: RIH with adjustable sub setting tool and RIH to 28,3 meter.
01:45 - 03:15: Applied 140 bar, picked up to 7 ton and bleed off pressure. Turned string 14 turns and picked up to 35 ton overpull. Continued to turn untill 9000 NM torque achieved. Observed correct movement on casing stickup and on annulus port on multibowl.
03:15 - 04:30: POOH with adjustable sub setting tool. Changed to 10 3/4" handling equipment.
04:30 - 05:15: Made up swedge and hose, tested same. Pressure tested adjustable sub internal seal to 20 345 bar 5 10 minutes. Pumped 486 liter, bled back 486 liter.
05:15 - 08:00: Disengaged casing hanger running tool. POOH and laid down casing hanger landing string. Rigged down 10 3/4" handling equipment.
08:00 - 10:00: Picked up 10 3/4 MS-T seal assembly RT and made up same to 5 1/2" DP. Connected hydraulic lines to RT and flushed through same. Function tested 10 3/4" MS-T seal assembly. Installed MS-T seal on RT. RIH with seal assembly on 5 1/2" DP, landed off at 20,75 meter. Locked seal assembly into riser, confirmed lock with 10 ton overpull. Set MS-T seal assembly.
10:00 - 11:15: Tested MS-T seal assembly to 345 bar 10 minutes through multi bowl port. POOH with 10 3/4" MS-T seal assembly RT and laid down same.
11:15 - 12:00: Picked up bowl protector RT and made up to 5 1/2" DP. RIH and installed bowl protector at 20,53 meter. POOH and laid down bowl protector RT.
12:00 - 12:15: Performed pre-job meeting prior to line up and pressure test.
12:15 - 12:45: Closed shear rams and lined up to test. Pressure tested BOP connection against safe lock plug to 20 345 bar 5 minutes. Pumped 478 liter, bled back 448 liter. Opened shear rams.
12:45 - 13:00: Performed pre-job meeting prior to retrieval of safe lock plug.
13:00 - 16:00: Picked up safe lock plug RT and made up to 5 1/2" DP. RIH with safe lock plug RT on 5 1/2" DP from surface to 601 m with restricted speed. Stopped operation due to contamination of active pit.
16:00 - 19:15: Cleaned contaminated pit. Prepared new brine.
19:15 - 19:30: At 601 meter made up TDS and commenced circulation with 200 liter/min, 2,8 bar. Pulled back to 591 meter.
19:30 - 20:45: Increased flow rate to 2000 liter/min, 7-8 bar and displaced hi-visc pill out of well decreased rate to 300 liter/min, 2-3 bar and washed back down to 601,6 meter. Continued to wash down with 150 liter/min to top of plug at 607,7 m.
20:45 - 22:30: Latched onto plug. Set down 20 ton on plug, rotated string 1/2 RH turn, took 15 ton overpull. Slacked off 2 ton weight and applied 35 bar, observed pressure drop to 15 bar, bleed off pressure to 0 bar. Took 2 ton overpull and rotated 24 right hand turns to release plug. Performed flow check for 10 minutes, OK. RIH to below plug setting point to ensure plug was retrieved and free, OK. POOH with safe lock plug on 5 1/2" DP from 611 m to surface with restricted speed. Inspected safe lock plug and RT, laid down same to cantilever.
22:30 - 23:15: Picked up bowl protector RT and made up same to 5 1/2" DP. RIH to 21,1 meter and retrieved bowl protector. POOH with bowl protector.
23:15 - 00:00: Cleaned and cleared rigfloor. Performed pre-job meeting prior to rig up tubing equipment.
| Activated adjustment sub. Pressure tested tie-back adapter. Ran and sat MS-T seal assembly. Pressure tested BOP connection. Installed bowl protector. Retrieved safe lock plug. Prepared to run completion. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-24, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:45: Changed to 7" handling gear, BX elevators, installed rotator. Installed 7" casing tong and tested same. Rigged up cable drums on rigfloor and installed sheave for DHPG. Prepared completion assembly and on deck. Installed vario spider slips and tested same.
02:45 - 03:00: Performed pre-job meeting with all involved personnel prior to run completion string.
03:00 - 05:30: Picked up and RIH 7" completion from surface to 59 meter. Assembly with 7" perforated stem and mule shoe. Assembly with pre installed EVO plug and auto fill valve. Assembly with bot granite packer. 2 ea. Plain 7" tubing joints. Assembly with DHPG. Observed 1 rejected joint.
05:30 - 07:00: Picked up and RIH assembly with DHPG. Installed 1 ea. Plain 7" tubing joint and RIH to 78 meter. Terminated cable to down hole pressure gauge. Function tested DHPG.
07:00 - 07:15: Performed pre-job meeting prior to RIH with completion string.
07:15 - 07:30: Rigged down DHPG test equipment.
07:30 - 10:45: RIH with 7" tubing from 78 m to 203 m. Average running speed 3,2 joints/hr.
10:45 - 11:00: Replaced tong die mesh due to poor grip. Broke out and checked connection, made up same.
11:00 - 15:15: RIH with 7" tubing from 203 m to 510 m. Average running speed 6,0 joints/hr.
15:15 - 15:30: Replaced tong die mesh due to poor grip. Broke out and checked connection, made up same.
15:30 - 17:45: RIH with 7" tubing from 510 m to 650 m. Average running speed 5,2 joints/hr. Observed trouble with HTS.
17:45 - 18:00: Repaired sensor on HTS.
18:00 - 19:00: RIH with 7" tubing from 650 m to 697 m. Average running speed 4 joints/hr.
19:00 - 19:15: Performed pre-job meeting prior to RIH with completion string.
19:15 - 00:00: RIH with 7" tubing from 697 m to 1096 m. Average running speed 7 joints/hr.
| Ran 7" completion from surface to 1096 meter. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-25, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: RIH with 7" tubing from 1096 m to 1108 m. Average running speed 4 joints/hr.
00:15 - 01:00: Replaced make up tong dies.
01:00 - 07:00: RIH with 7" tubing from 1108 m to 1662 m. Average running speed 7,7 joints/hr.
07:00 - 07:15: Performed pre-job meeting prior to RIH with completion string.
07:15 - 10:00: RIH with 7" tubing from 1662 m to 1873 m. Average running speed 6,4 joints/hr.
10:00 - 10:15: Emptied trip tank. Greased automatic slips.
10:15 - 17:00: RIH with 7" tubing from 1872 m to 2482 m. Average running speed 7,5 joints/hr.
17:00 - 17:15: Performed pre-job meeting
17:15 - 20:15: Picked up and made up assembly DHSV and made up same to string. RIH with completion string from 2482 m to 2490 m. Installed and terminated DHSV control lines. Tested DHSV control lines to 520 bar. Tested DHSV control lines to 345 bar and maintained DHSV open while RIH from 2490 m to 2502 m.
20:15 - 00:00: RIH with 7" tubing from 2502 m to 2759 m. Average running speed 5,7 joints/hr.
| Ran 7" completion from 1096 m to 2756 m. Picked up and terminated DHSV. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-26, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 00:15: Flow checked well for 10 min, OK.
00:15 - 02:30: RIH with 7" tubing from 2759 m to 2958 m. Average running speed 7,4 joints/hr.
02:30 - 04:45: Recorded up down weights, 181 145 ton. Changed to 5 1/2" DP elevators. Picked up landing string and made up to 7" tubing. Removed automatic slips. Installed masterbushings and manual slips.
04:45 - 05:30: Performed pre-job meeting prior to space out run. RIH with 7" tubing from 2958 m to 2980 m at 2980 m commenced washing down with at 200 liter/min, 4,6 bar stung into PBR at 2981 m, no pressure increase observed, stopped pumps. Continued to RIH and sheared pins with 6,1 ton down on PBR no-go ring. Marked pipe and POOH to up weight 0,80 meter.
05:30 - 07:15: POOH with 5 1/2" DP landing string. Changed to 7" elevator inserts. Picked up and made up 3,0 meter space out pup.
07:15 - 12:00: Picked up and made up tubing hanger to space out joint. Landed tubing hanger in c-plate. Broke out th handling tool. Installed tubing hanger running tool and made up landing string. Terminated and tested lines to 520 bar 10 minutes, OK.
12:00 - 13:45: Picked up and made up landing joints to string. RIH with hanger and landed same on 7" landing string. Observed 1,32 meter stick up. Verified correct hanger seal integrity by testing to 70 bar 5 min through ports on multi-bowl. Engaged tubing hanger lock down ring. Performed pull test to 15 ton overpull, OK. Meanwhile drained riser.
13:45 - 14:00: Pressure tested liner hanger seal to 35 345 bar 5 10 min.
14:00 - 14:15: Rigged up swedge and cement hose, tested same to 345 bar 10 min.
14:15 - 14:30: Pressure tested control lines to 570 bar 10 minutes.
14:30 - 14:45: Dropped ball for setting packer.
14:45 - 15:30: Circulated ball down with 3500 liter/min, 29 bar, pressure increased to 70 bar at landing. Held 70 bar pressure for 5 min to check integrity of completion string.
15:30 - 16:00: Increased pressure to 275 bar and held same for 15 minutes to set packer. Meanwhile observed vent line on annulus a. Observed leaking cap on swedge.
16:00 - 16:30: Bled off pressure and replaced gasket on leaking cap for swedge.
16:30 - 18:15: Pressure tested tubing to 345 bar 30 minutes. Bled pressure down to 280 bar. Closed DHSV. Bled pressure down to 210 bar and performed low pressure inflow test, 70 bar, 30 min. Bled pressure down to 10 bar and performed high pressure inflow test, 280 bar, 10 min. Bled pressure back to 0 bar and opened DHSV.
18:15 - 19:45: Lined up and tested connection from cement unit to a annulus. Performed pressure test of production packer though a annulus to 35 345 bar, 5 10 min.
19:45 - 20:00: Performed pre-job meeting prior to rig up and run wilreline.
20:00 - 20:45: Rigged up wireline sheaves and equipment. Made up wireline tool string.
20:45 - 00:00: RIH with wireline tool string and retrieved EVO plug.
| RIH with completion string to tol. Pulled back and installed space out pups. Installed tubing hanger. Landed and tested hanger. Retrived EVO plug. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-27, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 02:45: While POOH EVO plug stopped inside DHSV, jarred twice and continued to POOH to surface. Laid out EVO plug and wireline tool string. Laid down wireline sheaves and equipment.
02:45 - 04:30: Pressure tested line up from cement unit to drill floor to 355 bar. Pressure tested production packer from below to 345 bar- 30 minutes. Pumped 1201 liter, bled back 1201 liter. Closed DHSV. Rigged down test equipment.
04:30 - 05:30: Held pre-job meeting. Disconnected tubing hanger RT by rotating 9 turns clockwise. POOH with 7" landing string and tubing hanger, laid out same.
05:30 - 07:15: Rigging down tubing handling and completion equipment.
07:15 - 08:00: Picked up and made up BPV running tool to 5 1/2" DP. RIH from surface to 20,55 meter and installed BPV plug. POOH and laid down RT.
08:00 - 13:15: Performed pre-job meeting prior to nipple down BOP. At 09 00 production was shut down. Rigged up handling equipment for nipple job on rigfloor. Nippled down diverter, pulled same to rigfloor and secured. Removed riser tension cylinders. Disconnected BOP from HP riser and skidded same to stump. Pulled riser to rigfloor.
13:15 - 16:30: Terminated wellhead control lines. Prepared XMT.
16:30 - 21:30: Removed masterbushings and hatch in moonpool. Ran down with spacer spool and landed same on multi-bowl. Made up spool piece. Tested connection to 35 345 bar 5 15 minutes.
21:30 - 21:45: Performed pre-job meeting.
21:45 - 23:15: Removed f-1 hatch covers. Lowered down flow line spool piece to well head deck.
23:15 - 00:00: Performed housekeeping and maintenance on drill floor. Worked with termination and test of control lines for DHSV and DHPG.
| Installed BPV plug. Nippled down BOP. Installed spool piece. Prepared to install XMT. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-28, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 03:00: Performed housekeeping and maintenance on drill floor. Worked with termination and test of control lines for DHSV and DHPG.
03:00 - 04:30: Held pre-job meeting prior to installation of XMT. Transferred XMT from overhead crane to TDS. Ran down with XMT to 15 cm above land off.
04:30 - 11:00: Landed and orientated XMT. Closed hatches above well. Installed clamp on XMT connection. Installed flow line spool to ensure correct line up. At 06 00 hrs informed production to restart production according to simops. Meanwhile performed housekeeping and maintenance on drill floor. Rigged up hose and valves for pressure testing.
11:00 - 13:00: Made up HXT clamp connection and tested same.
13:00 - 14:00: Prepared for handing over well to production for commissioning. Well handed over to maersk production at 14 00 hrs.
14:00 - 00:00: Prepared wire line equipment. Pressure tested TDS.
| Installed XMT and tested same. Handed over well to maersk production for XMT commissioning. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-29, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 04:45: Prepared wire line equipment. Pressure tested TDS. Performed slip cut. At 04 45 hrs well was handed over from maersk production to drilling.
04:45 - 06:30: Erected scaffolding around XMT. Removed XMT cap. Retrived BPV and laid out same.
06:30 - 07:00: Rigged up wire line equipment, installed x-over on XMT.
07:00 - 07:15: Performed pre-job meeting prior to rig up.
07:15 - 12:00: Rigged up wire line riser and BOP. Erected scaffolding around WL BOP in moonpool. Installed grease head. Hooked up control lines for WL BOP. Filled WL riser with MEG and tested rig up to 30 200 bar 5 minutes.
12:00 - 00:00: Rigged up and prepared equipment for perforation. Made up perforation tool string. Meanwhile prepared to pressure test BOP on stump. Pressure tested stand pipe manifolds.
| Maersk production performed XMT commissioning. Retrieved BPV. Rigged up and prepared for wire line operations. |
You are a Rig Supervisor working at an oil and gas offshore drilling operation. Your company is currently on a drilling campaign and you are the on-site Drilling Engineer (DE). As a DE, one of your jobs is to oversee the operations at the drilling rigs. As such, you know the ins and outs of the operation, down to the hourly activities. Every day, activities are recorded either by the Driller, Mud Logger, MWD / LWD engineer or the Drilling Operations Coordinator throughout the day. As a DE representative for your company, you are required to prepare the 24-hour summary for the Daily Drilling Report (DDR) based on the hourly activities reported. You must always maintain the language of report along with the terminologies and mnemonics of the Drilling Engineer.
Given the following activities for well NO 15/9-F-1 B on 2013-09-30, please prepare the 24-hour summary for the Daily Drilling Report (DDR).
Only return the 24-hour summary, and nothing else.
| 00:00 - 04:30: Rigged up and prepared equipment for perforation. Made up perforation tool string. Meanwhile performed housekeeping and planned maintenance in all drilling areas. Pressure tested stand pipe manifolds.
04:30 - 07:00: Rigged up and prepared equipment for perforation. Made up perforation tool string and tested same. Meanwhile filled lubricator with MEG. Leak tested WL lubricator and quick test sub rig up to 30 200 bar 5 minutes. Observed WL string stuck.
07:00 - 10:00: Observed WL string stuck. Not able to pull through lubricator tubes. Broke QTS sub and released wire and tool. Re-tested WL lubricator and quick test sub rig up to 30 200 bar 5 minutes.
10:00 - 11:45: Broke off lubricator. Performed pre-job safety meeting prior to handling of explosives.
11:45 - 14:45: Picked up and made up perforation gun assembly Made up and leak tested WL lubricator and quick test sub rig up to 30 200 bar 5 minutes.
14:45 - 20:00: RIH with perforation gun assembly from surface to 3360 m. WHP 18 bar.
20:00 - 22:00: Correlated across perforation interval. Positioned gun with top shot at 3296 m. WHP 36 bar, bled down to 1,2 bar.
22:00 - 22:15: Perforated interval between 3296 m to 3304 m. WHP stabilized at 32 bar.
22:15 - 00:00: POOH with perforation gun assembly from 3304 m to 1361 m.
| Rigged up and prepared for wire line operations. Perforated well. |
Subsets and Splits